Koller Construction Co. v. Southern Utility Supply Co.

156 So. 2d 110
CourtLouisiana Court of Appeal
DecidedJuly 1, 1963
DocketNos. 5931, 5932
StatusPublished
Cited by1 cases

This text of 156 So. 2d 110 (Koller Construction Co. v. Southern Utility Supply Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koller Construction Co. v. Southern Utility Supply Co., 156 So. 2d 110 (La. Ct. App. 1963).

Opinion

LOTTINGER, Judge.

These two suits were consolidated for purposes of trial and will therefore be treated herein together. The first numbered suit is a rule to show cause, filed by Roller Construction Company against Southern Supply Company, why a material-man’s lien filed against the petitioner in rule by defendant in rule should not be erased and cancelled. The second numbered suit is a suit on open account by Southern Utility Supply Company against Roller Construction Company. At trial, the petitioner in the second suit attempted to amend its petition so as to convert the action to a suit on a promissory note. The Lower Court gave judgment in both suits in favor of Southern Utility Supply Company, and Roller Construction Company has appealed.

The evidence reflects that DeFraites Associates was engaged as consulting engineers for the St. Mary Parish Sewer District No. 2 in the construction of a sanitary sewer system in the Parish of St. Mary, Louisiana. The engineers prepared plans and specifications for the construction of said sanitary sewerage system and same was let for public bidding. Roller Construction Co., the defendant, was the low bidder.

With regard to the portion of the said system about which this suit revolves, the plans and specifications called for a force main pipeline of a length of some 11,000 feet, of which 3,500 feet was on solid ground, on the berm of a levee, and some [111]*1117,500 feet of which was through marshy-ground, where both stable and unstable soil was found. The pipeline was to be laid relatively straight, with only one or two curves. The specifications of the engineer called for a 12 inch asbestos-cement pipe, of a class 150, to be used on a force main with ring-tite couplings as manufactured by Johns-Manville or approved equal. The specifications further provided that the manufacturer of the pipe should send a representative to the job to properly instruct the contractor on the procedure to be used in making up the joints.

Shortly before or after the award of the bids to Koller Construction Company, the time is immaterial, Mr. Earl Koller,. the president of the company, was approached by the representatives of Keasbey and Mat-tison Company, the manufacturer of K and M pipe, and their supply house in Baton Rouge, Southern Utility Supply Co., with the request that K and M pipe be used on the job. Several conferences were held between Mr. Koller, the representatives of K and M Company, the representatives of Southern Utility and the consulting engineers after which a “change order” was issued by the engineering firm authorizing the use of K and M asbestos-cement, Type 150, pipe instead of Johns-Manville pipe.

The 11,000 foot of pipeline was laid by the contractor. After the laying of same, the tests, as required for acceptance of said pipeline was commenced by the defendant contractor. Of some 33 tests made at a pressure of 100 pounds per square inch, there were some 19 blowouts or explosions. These blowouts or explosions form the basis of this lawsuit. In repairing these defects, the contractor claims to have expended some $27,549.93. Mr. Koller, the president of the contracting company, claims that he forwarded a letter to Southern Utility in which he back charged the petitioner for the said amount, he claiming, that these expenditures occurred because of defective pipe or fittings supplied him. In response to this letter, the Southern Utility filed a materialman’s lien against Koller in the sum of $32,337.65, alleging that said amount represents the balance due for pipe shipped to this job.

Southern Utility Supply Co. claims that the sole cause of'the blowouts or explosions to the pipeline was caused by defective workmanship by Koller Construction Company; or because of the engineers’ failure to provide proper plans and specifications for the installation. Koller Construction Co., on the other hand, claims that the blowouts or explosions were the result of faulty pipe or couplings furnished it by Southern Utility Company.

On April 4, 1962 Koller Construction Co. filed a rule to show cause against Southern Utility why the lien and privilege should not be erased and cancelled. On April 6th, 1962, Southern Utility Co. filed suit against Koller Construction Co. on open account for $32,327.05, the amount alleged to be due for pipe furnished. The two cases were consolidated for trial. For the purposes of this opinion, Southern Utility Co. will hereafter be referred to as petitioner, Kol-ler Construction Co. will be hereafter referred to as defendant, and Keasbey and Mattison Company will be referred to as K and M.

At the start of trial on the merits, the petitioner sought to amend its petition so as to convert its suit to one on the balance due on a promissory note in the sum -of $39,765.03. In its amended petition it prayed for judgment for $28,231.18 with interest on $21,325.03 from July 18, 1961, until paid and 10% additional on said amount of $21,325.03 and the interest thereon as attorney fees and the additional sum of $6,906.15 and legal interest thereon until paid. Defendant objected to the filing of the amended petition on the grounds that it converted the suit from one on an open account to a suit on a promissory note. It was finally agreed between the parties that, if anything, a balance of $27,549.93 was due on the pipe, and the Lower Court awarded judgment for petitioner in said amount. The defendant has appealed.

[112]*112The record' discloses that Koller Construction Company has been in business for some 42 years. Its business is mainly in the construction of water and sewerage systems and plants. Mr. Earl Koller, the President of the company, testified that he has been with the company for some ten years during which period he has laid some 100,000 feet of K and M pipe. He testified that he was first approached by either the petitioner or K & M relative to the use of K & M pipe. In this connection several meetings were held between himself, the representatives of petitioner, the representatives of K & M and members of the engineering firm. At these meetings the representatives of K & M and petitioner represented that their pipe would withstand the tests under the circumstances. At the time of these representations, it was questionable as to whether or not K & M pipe would be used on the job.

Mr. Koller who is a graduate civil engineer, testified that the total length of the line was about eleven thousand feet. For about fifteen hundred to two thousand feet near each end of the line, the ground was solid and didn’t contain much moisture. The central two-thirds of the line was in a marshy condition, wherein the ground was soft and the water table was very close to the surface. There was some variation within this central two-thirds area, some parts were harder and drier than others. Several hundred feet of this area required repeated excavation and pumping. In the remaining portion they had no trouble maintaining the trench until the pipe was installed.

Mr. Koller testified that about two-thirds of the line had been backfilled prior to testing. A total of thirty-three tests were run in an effort to get 100 pounds per square inch pressure on the line. There were nineteen explosions or blowouts all occurring at the collars. The thirty-fourth test was made to achieve a lower pressure test. Of these explosions, some occurred on solid ground, on the berm of a levee, and some occurred in marshy terrain. Some explosions occurred after the line had been staked to assure stability. After these explosions, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koller Construction Co. v. Southern Utility Supply Co.
157 So. 2d 233 (Supreme Court of Louisiana, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
156 So. 2d 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koller-construction-co-v-southern-utility-supply-co-lactapp-1963.