Kohl Ex Rel. Southridge Co. v. F. J. A. Christiansen Roofing Co.

289 N.W.2d 329, 95 Wis. 2d 27, 1980 Wisc. App. LEXIS 3101
CourtCourt of Appeals of Wisconsin
DecidedJanuary 10, 1980
Docket79-090
StatusPublished
Cited by10 cases

This text of 289 N.W.2d 329 (Kohl Ex Rel. Southridge Co. v. F. J. A. Christiansen Roofing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kohl Ex Rel. Southridge Co. v. F. J. A. Christiansen Roofing Co., 289 N.W.2d 329, 95 Wis. 2d 27, 1980 Wisc. App. LEXIS 3101 (Wis. Ct. App. 1980).

Opinion

BROWN, J.

This is an appeal from a summary judgment dismissing the owner’s complaint against various defendants, all of whom were involved in the construction of Southridge Shopping Center. The owner is Sidney Kohl on behalf of The Southridge Company, a co-partnership. The defendants are the Taubman Company, Inc., the general contractor; F. J. A. Christiansen Roofing Co., the roofing subcontractor; Wah Yee, and Wah Yee Associates, the architects; Py-Vavra Architects-Engineers, Inc., the sub-architect, and W. R. Grace & Com *30 pany and Certain-Teed Products Corporation, manufacturers of roofing materials. The only defendant not dismissed from the action was Taubman Company, Inc. The trial court ruled that Kohl had been alerted to the existence of injury more than six years prior to the commencement of the action and dismissed all claims on the basis that the applicable six-year statutes of limitations had run. We disagree.

On January 2, 1968, The Southridge Company, a co-partnership, whose members included Sidney Kohl, A. Alfred Taubman and Richard Paul Kughn hired the Taubman Company, Inc. to be the general contractor in the construction of a shopping mall. A. Alfred Taubman and Richard Paul Kughn, partners in The Southridge Company, were also officers, directors and shareholders of the general contractor, Taubman Company, Inc. Taub-man Company, Inc. engaged the services of all defendants except the sub-architect (Py-Vavra) who was subcontracted by Wah Yee Associates, the primary architect.

Sometime in May or June of 1970, 12,000 square feet of the 300,000 square foot roof under construction experienced wind uplift damage but was immediately repaired. The roof was inspected on June 3 by Donald J. McNeil of Construction Consultants, Inc. because the wind uplift had occurred. On July 10, Construction Consultants, Inc. issued what we will refer to as the McNeil report. This report asserted that there were deficiencies still remaining in the roofing installation. No further repair was made at that time. About four years later, however, Southridge began to experience problems with the roof. In 1977, the entire roof was replaced.

Southridge Company commenced a civil action against all defendants except the sub-architect (Py-Vavra) on July 21,1976. The pleadings indicated several alternative claims for relief against the various defendants sounding in fraud, misrepresentation, negligence, strict liability, breach of contract and breach of implied warranty.

*31 The fraud action was based on an allegation that the defendants wrongfully concealed the defect ¡from Kohl and Southridge and that the defendants misrepresented the roof to be in sound condition. The trial court, however, found that even if there was concealment, such concealment would have been exposed by the McNeil report. Since a plaintiff in a fraud action must begin his law suit within six years after discovery of the concealment, the trial court was inclined to dismiss the claim. Kohl, however, argued that it did not know about the McNeil report and thus could not have discovered the concealment by reading the report. The trial court dismissed the claim, finding that the report was given to Taubman Company, Inc. Since the report was given to Taubman Company, Inc., and since A. Alfred Taubman was an officer in the construction company that authorized the report, the trial court reasoned that the knowledge Taub-man acquired from the report, Kohl must also have acquired. The trial court concluded that Taubman was the agent of Kohl and that Kohl necessarily had notice of the concealment of the wind uplift damage because he was Taubman’s partner. The trial court thus granted summary judgment finding that discovery of the concealment took place on July 10, 1970 when the McNeil report was delivered to Taubman Company, Inc. and that the Kohl complaint was not filed until more than six years after the discovery.

The negligence action was also dismissed. The trial court noted that the wind uplift damage had occurred no later than July 10, 1970. Defendants argued that since the action was commenced on July 21, 1976, it was thereby barred by the six-year statute of limitations of sec. 893.19(5), Stats., because it was more than six years from the time of actual injury to the filing of the complaint. The trial court agreed that the six-year statute of *32 limitations began to run at the time of the wind uplift damage.

' Although we do not have the benefit of the trial court’s reasoning behind this finding, we assume the trial court felt the damage, by itself, was sufficiently significant to alert Southridge of the defect before July 10, 1970. The trial court also dismissed the strict liability action on the same ground.

An action for breach of contract against the architect, Wah Yee, was dismissed on the basis that the architect completed his contractual obligations more than six years prior to the commencement of the action. The trial court found that if Wah Yee did breach its contract, the breach had to have occurred at or prior to the sufficiently significant injury of July 10, 1970. The trial court also dismissed a separate implied warranty claim against the defendants Christiansen Roofing and Grace because the court found no privity of contract between Kohl and those two defendants.

In deciding that the trial court’s use of various statutes of limitations incorrectly warranted summary judgment, we first note that summary judgment is not appropriate if there is a material issue of fact or if different inferences may be drawn from the facts. Krezinski v. Hay, 77 Wis.2d 569, 572, 253 N.W.2d 522, 524 (1977). If there is no genuine issue of material fact, summary judgment must be granted. Sec. 802.08(2), Stats. Our review on appeal from a grant of summary judgment is to independently make this determination. Wright v. Hasley, 86 Wis.2d 572, 578-79, 273 N.W.2d 319, 322-23 (1979).

Because of the number of defendants and the number of claims, we will discuss each claim separately. Further facts will be set forth as are necessary to the determination of each claim. The term “defendants” will refer to all defendants except Taubman Company, Inc. unless specifically noted otherwise.

*33 FRAUD CLAIM

The statute of limitations in a fraud action begins to run from the time the fraud is first discovered. Sec. 893.19 (7), Stats. Kohl claims that the defendants knew the wind uplift damage was due to the roof not being built according to specifications or existing industry standards. Kohl accuses the defendants of concealing this knowledge. Kohl further claims that he did not know of this fraud until the roof began experiencing problems in 1973 resulting in the replacement of the roof in 1977.

Defendants claim that on the basis of the pleadings and affidavits before us, Kohl, as a matter of law, discovered the concealment when the McNeil report was issued on July 10, 1970, more than six years prior to the commencement of the action. Defendants submit two arguments in support of their claim. Defendants’ first claim is that Taubman Company, Inc. was an agent of Southridge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ellerman v. City of Manitowoc
2003 WI App 216 (Court of Appeals of Wisconsin, 2003)
State v. Timblin
2002 WI App 304 (Court of Appeals of Wisconsin, 2002)
Grove Holding v. First Wisconsin Nat. Bank of Sheboygan
12 F. Supp. 2d 885 (E.D. Wisconsin, 1998)
Henderson v. Milwaukee County
543 N.W.2d 544 (Court of Appeals of Wisconsin, 1995)
Select Creations, Inc. v. Paliafito America, Inc.
830 F. Supp. 1223 (E.D. Wisconsin, 1993)
Olympia Hotels Corp. v. Johnson Wax Development Corp.
908 F.2d 1363 (Seventh Circuit, 1990)
Young Radiator Co. v. Celotex Corp.
881 F.2d 1408 (Seventh Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
289 N.W.2d 329, 95 Wis. 2d 27, 1980 Wisc. App. LEXIS 3101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kohl-ex-rel-southridge-co-v-f-j-a-christiansen-roofing-co-wisctapp-1980.