Knox Energy, LLC v. Gasco Drilling, Inc.

54 F. Supp. 3d 489, 2014 U.S. Dist. LEXIS 147642, 2014 WL 5310719
CourtDistrict Court, W.D. Virginia
DecidedOctober 16, 2014
DocketCase No. 1:12CV00046
StatusPublished
Cited by1 cases

This text of 54 F. Supp. 3d 489 (Knox Energy, LLC v. Gasco Drilling, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knox Energy, LLC v. Gasco Drilling, Inc., 54 F. Supp. 3d 489, 2014 U.S. Dist. LEXIS 147642, 2014 WL 5310719 (W.D. Va. 2014).

Opinion

OPINION AND ORDER

JAMES P. JONES, District Judge.

In this breach of contract action arising under Virginia law, the party alleged to have breached the contract moved at trial for judgment as a matter of law. The parties argued their positions and I announced my intention to grant the oral motion and then discharged the jury. This opinion sets forth my basis for granting the motion. In summary, I find that there was insufficient proof of mutual assent to the contract sued upon and thus it is unenforceable as a matter of law.

I.

Knox Energy, LLC, a natural gas producer, filed this action seeking a declaratory judgment that no contractual relationship existed between it and Gaseo Drilling, Inc. (“Gaseo”), a gas drilling company.1 Gaseo in turn filed a Counterclaim against both Knox Energy, LLC, and an additional party, Consol Energy, Inc.2 In its Counterclaim, Gaseo sought recovery of over $14 million under an expired drilling contract that Gaseo claimed had been resurrected by a form agreement mistakenly sent to Gaseo. Without objection, I ruled prior to trial that Gaseo would be treated as a plaintiff and had the burden of proof as to the existence of an enforceable contract.

The essential facts of this case are largely uncontested. Gaseo presented its casein-chief at trial through the testimony of three witnesses: Clyde B. Ratliff (“Ratliff’), Gasco’s CEO and principal owner; Freda Rasnake (“Rasnake”), Ratliffs clerical assistant; and Todd M. Shumaker (“Shumaker”), Knox/Consol’s Director of [491]*491Contract Services. The testimony of Gas-co’s three witnesses and the exhibits admitted during that testimony are the basis for the court granting Knox/Consol’s motion for judgment as a matter of law.

Gaseo is a family owned and operated gas drilling company that has been in business since the late 1980s. Gaseo has had business dealings with Knox/Consol, a natural gas producer, since the early 1990s. During this period, the parties have entered into numerous contracts for the drilling of gas wells.

Ratliff, Gasco’s CEO, exercises exclusive control over the execution of drilling contracts entered by Gaseo. In contrast, no single individual exercises exclusive contracting authority for Knox/Consol. Ratliff has negotiated drilling contracts with various individuals exercising contracting authority on behalf of Knox/Consol during the course of the parties’ relationship.

The first critical event occurred in June 2008 when the parties entered into a written contract for well drilling services to begin on July 7, 2008 (“2008 Drilling Contract”). The term of the 2008 Drilling Contract was stated to be “until drilling operations are completed ..., or for a term of 2 years.” (Countercl. Pl.’s Trial Ex. 1 § 6.1, ECF No. 264-2.)

Pursuant to the 2008 Drilling Contract, Gaseo was hired to provide drilling services at undefined sites throughout eastern Tennessee, eastern Kentucky, and, at times, in Virginia and northern West Virginia. Gaseo was also obligated to have two drilling rigs and associated equipment available for use during the term of the 2008 Drilling Contract.

In compensation for providing drilling services, Knox/Consol was required to pay Gaseo for each drilling rig at work on horizontal gas drilling, either $13,500 or $12,000 per day, depending upon whether the drilling was performed with or without pipe. In addition, Knox/Consol had to pay Gaseo a per-foot fee during vertical drilling, prior to the horizontal drilling work.3

Central to Gasco’s claim, it was also entitled to a standby rate of $10,800 per day for each drilling rig at all times when drilling was not being performed. This standby rate was unique in that it was in the form of a “take or pay” provision, entitling Gaseo to a minimum of 328 days of compensation per year. In short, Gaseo was guaranteed 328 days of compensation at a minimum daily rate of $10,800 for each of two drilling rigs even if no drilling rig was in service.

The “take or pay” provision of the 2008 Drilling Contract was included in the contract at Knox/Consol’s request. At the time, natural gas was at market highs, and the “take or pay” provision ensured that two of Gasco’s drilling rigs would be available for use on Knox/Consol’s well sites. This provision was so unique that, according to Gasco’s CEO Ratliff, Gaseo had only entered into two drilling contracts with “take or pay” provisions in the company’s history, both of which were signed in 2008.

Following its execution, the parties amended the 2008 Drilling Contract three times following significant drops in the market price of natural gas. On February 17, 2009, the parties agreed to reduce the standby rate under the “take or pay” provision to $6,800 per day. The reduced rate was to remain in effect until Gaseo was instructed by Knox/Consol to recommence drilling operations, at which time, the standby rate would revert to $10,800 per [492]*492day. Following this amendment, Gaseo recommenced drilling operations for Knox/Consol; however, as an apparent oversight, Gaseo never again billed for standby time at a rate of $10,800 per day.

On May 1, 2009, the parties amended the 2008 Drilling Contract again to reduce the compensation rates for Gasco’s drilling services. Specifically, the daily drilling rates for drilling with and without pipe were reduced to $12,500 and $11,500, respectively. The vertical footage drilling rate under the contract was also reduced from $22.50 to $20.50 per foot.

The parties’ final amendment to the 2008 Drilling Contract was effective May 10, 2010. Pursuant to this amendment, the parties identified two drilling rigs that were actively drilling wells for Knox/Con-sol in Tennessee, and agreed to release one drilling rig upon completion of an identified well. After completion of the identified well, the parties agreed that Knox/Consol would no longer be obligated under the 2008 Drilling Contract for the released drilling rig. The parties also agreed that the unreleased drilling rig would continue drilling operations on five identified wells. The May 10, 2010, amendment represented the final scope of drilling work performed under the 2008 Drilling Contract.4 Drilling operations were completed and the 2008 Drilling Contract terminated according to its terms on July 24, 2010.

On June 6, 2011, well after work under the 2008 Drilling Contract terminated, a temporary clerical employee of Knox/Con-sol emailed Rasnake a one-page form document entitled “Addendum to Contract Purchase Order” (hereafter called the “Addendum”), which Gaseo dated, signed and returned on June 14, 2011. Knox/Consol signed the Addendum and returned a copy to Gaseo in July 2011. The Addendum and the events surrounding its execution were the primary issues addressed at trial.

The fully executed Addendum contains the following language:

Addendum to Contract Purchase Order
This Addendum to contract purchase order (“Addendum”) is entered into effective this 13th day of June, 2011, by and between Consol Energy, Inc. and its affiliates (“Company”) and Gaseo Drilling, Inc. (“Contractor”).
Whereas, Company and Contractor are parties to a contract purchase order (PO No. 5600000439) (the “Contract Purchase Order”); and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knox Energy, LLC v. Gasco Drilling, Inc.
258 F. Supp. 3d 709 (W.D. Virginia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
54 F. Supp. 3d 489, 2014 U.S. Dist. LEXIS 147642, 2014 WL 5310719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knox-energy-llc-v-gasco-drilling-inc-vawd-2014.