Knowlton Riverside Estates, Inc. v. Planning Board

790 A.2d 194, 347 N.J. Super. 362, 2002 N.J. Super. LEXIS 56
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 5, 2002
StatusPublished
Cited by1 cases

This text of 790 A.2d 194 (Knowlton Riverside Estates, Inc. v. Planning Board) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knowlton Riverside Estates, Inc. v. Planning Board, 790 A.2d 194, 347 N.J. Super. 362, 2002 N.J. Super. LEXIS 56 (N.J. Ct. App. 2002).

Opinion

The opinion of the court was delivered by

SKILLMAN, P.J.A.D.

This appeal involves the interpretation of N.J.S.A 40:55D-52(d), which entitles a developer to a mandatory extension of the two-[364]*364year period of exemption from a change in the zoning of its property conferred by final subdivision approval, if the developer can prove it was “barred or prevented ... from proceeding with the development because of delays in obtaining legally required approvals from other governmental entities and that [it] applied promptly for and diligently pursued these approvals.”

On December 26, 1989, plaintiffs predecessor in title obtained conditional preliminary major subdivision approval for twenty-two residential building lots on a forty-three acre tract in Knowlton Township. The approved subdivision plan also included a nine acre lot for open space and water detention purposes.

When this approval was obtained, the property was zoned for single family homes on lots with a minimum size of one acre. In 1992, the Township adopted an amended zoning ordinance, under which plaintiffs property was placed in a Farmland Preservation Zone that requires a minimum of five acres for a residential building lot. However, under N.J.S.A. 40:55D-49(a), plaintiffs property was exempted from this zoning change for a three-year period following preliminary subdivision approval, and under the Permit Extension Act, N.J.S.A 40:55D-130 to 136, this exemption was extended for an additional four years to December 31, 1996, N.J.S.A 40:55D-133(a).

Near the end of this extension, plaintiff applied for final subdivision approval. On December 30, 1996, the defendant Knowlton Township Planning Board (Board) granted plaintiff final subdivision approval, which was memorialized by a resolution adopted on January 28, 1997. Pursuant to N.J.S.A. 40:55D-52(a), this final subdivision approval granted plaintiff an additional two-year exemption from the 1992 rezoning of its property. This approval was subject to twenty conditions, including “outside agency review,” most of which had to be satisfied within ninety days.

However, because plaintiff was unable to satisfy these conditions in a timely manner, it had to apply for an extension of time, which the Board granted by a resolution adopted on June 24,1997. [365]*365With respect to the condition that plaintiff obtain required outside agency review, this resolution stated:

[T]he Attorney for the Applicant indicates that they have begun the process of completing those approvals. It was recommended that the letters from those agencies be provided to the Secretary of the Board.

Plaintiff subsequently determined that there was a two-and-a-half foot error in the flood plain line shown on the maps submitted in support of its application for preliminary subdivision approval, which required a reconfiguration of the lots and a modification of the proposed detention basin. The Board concluded that these revisions in the subdivision plan “materially impacted” the preliminary and final major subdivision approvals. Therefore, the Board granted an amended final subdivision approval of a revised subdivision plan, which was memorialized by a resolution adopted on January 27, 1998. The Board also apparently concluded that this amended approval extended plaintiffs exemption from the 1992 rezoning of its property for another year, from January 28,1999 to January 27, 2000.

On February 15, 2000, plaintiff applied to the Board for a one-year extension of the revised final subdivision approval granted on January 27, 1998. In support of this application, plaintiff claimed that it was entitled to a mandatory extension of time under N.J.S.A 40:55D-52(d), because delays in obtaining legally required approvals from other governmental entities had prevented it from proceeding with the development. In the alternative, plaintiff requested the Board grant a discretionary one-year extension under N.J.S.A. 40:55D-52(a).

The Board conducted a two day evidentiary hearing, following which it voted to deny plaintiffs application for an extension of time under both N.J.S.A 40:55D-52(d) and N.J.S.A 40:55D-52(a). The Board concluded that plaintiff had failed to show that it had applied for and diligently pursued the required government approvals, or that there had been undue delay by any governmental entity in reviewing plaintiffs applications for those approvals. The Board also concluded that plaintiff had failed to show that the alleged delay in receipt of the required governmental approvals [366]*366had prevented it from proceeding with the subdivision prior to the January 27, 2000 deadline. Consequently, the Board ruled that plaintiff had failed to demonstrate its entitlement to an extension of time under N.J.S.A. 40:55D-52(d).

In addition, the Board found that plaintiff had not “duly recorded the plat” for its proposed subdivision, which is a precondition of seeking a discretionary extension under N.J.S.A. 40:55D-52(a). The Board also indicated that even if plaintiff had satisfied this precondition, it still would not have been granted a discretionary extension of time because plaintiffs proposed development was inconsistent with the Township’s current master plan and zoning. Moreover, the Board noted that “[i]n light of [plaintiffs] difficulty in obtaining financing, the exhaustion of [its] financial resources and [its] history of abandoning partially completed subdivisions there is no assurance that this subdivision would be diligently and promptly completed to all required standards.”

Plaintiff brought this action in lieu of prerogative writs challenging the denial of its application for an extension of the period of exemption from the 1992 rezoning of its property. In addition to challenging the denial, the complaint sought declaratory relief and damages based on a number of alleged constitutional violations.

The matter was brought before the trial court by an order to show cause, and the court decided to consider the validity of the Board’s denial of plaintiffs extension application in a summary manner, see R. 4:67-l(b), severing the remaining counts of the complaint. The court concluded in an oral opinion, without detailed findings of fact, that even though plaintiff had not “acted with the greatest of speed” in seeking the required approvals from other governmental entities, it had nevertheless satisfied the requirement of N.J.S.A. 40:55D-52(d) that a developer “applfy] promptly for and diligently pursuef ] these approvals.” The court also stated, again without detailed findings, that plaintiff had experienced “difficulties in obtaining a permit from one state agency, while another one was expiring[,][a]nd then going back to the other agency[.]” The court further indicated that if plaintiff had failed to show that it was entitled to a mandatory extension of [367]*367time under N.J.S.A. 40:55D-52(d), it would not have been entitled to a discretionary extension under N.J.S.A. 40:55D-52(a) because it had not satisfied the precondition of “duly record[ing] the plat” for its proposed subdivision. The court memorialized its decision by a final judgment, which reversed the Board’s denial of plaintiffs application and granted a one-year extension of the exemption from the current zoning ordinance conferred by plaintiffs amended final subdivision approval.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.J.P. Builders, Inc. v. Township of Woolwich
824 A.2d 1114 (New Jersey Superior Court App Division, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
790 A.2d 194, 347 N.J. Super. 362, 2002 N.J. Super. LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knowlton-riverside-estates-inc-v-planning-board-njsuperctappdiv-2002.