Knight v. South Mississippi Electric Power Ass'n

943 So. 2d 81, 2006 Miss. App. LEXIS 667, 2006 WL 2599631
CourtCourt of Appeals of Mississippi
DecidedSeptember 12, 2006
DocketNo. 2004-CA-02082-COA
StatusPublished
Cited by1 cases

This text of 943 So. 2d 81 (Knight v. South Mississippi Electric Power Ass'n) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knight v. South Mississippi Electric Power Ass'n, 943 So. 2d 81, 2006 Miss. App. LEXIS 667, 2006 WL 2599631 (Mich. Ct. App. 2006).

Opinion

KING, C.J.,

for the Court.

¶ 1. Willie George Knight and Ellen D. Knight (the Knights) appeal the judgment of the Covington County Circuit Court, sitting as a Special Court of Eminent Domain, condemning a portion of their property for a right-of-way and easement for the construction, maintenance, and operation of an electric transmission line system. Finding no error, we affirm.

FACTS

¶2. South Mississippi Electric Power Association (SMEPA) is a non-profit, rural electrical co-op which has eleven distribution co-op members to whom it provides electricity. The distribution co-ops, in turn, provide electricity to residential and commercial customers. Southern Pine [83]*83Electric Power Association (Southern Pine) is the SMEPA member which provides electricity to Covington County, as well as ten other counties in the region. Southern Pine’s North Collins substation provides electricity to approximately 1,900 customers. An analysis of the transmission system revealed that the North Collins substation was providing below adequate voltage to its consumers.1 As a result, on April 1, 1997, SMEPA filed for a certificate of convenience and necessity with the Mississippi Public Service Commission (PSC) to construct a 69 kilovolt power line, Line 104, in the North Collins area in order to provide adequate voltage to its customers. The proposed line would run approximately five miles from Station Creek substation to Southern Pine’s North Collins substation. Notice of the filed petition and the pending PSC hearing was published in The Clariortr-Ledger, a newspaper of general circulation published in Jackson, Mississippi, and in The News-Commercial, a newspaper of general circulation in Covington County, Mississippi. The PSC notice appeared as follows:

MISSISSIPPI PUBLIC SERVICE COMMISSION
Jackson, Mississippi
April 01, 1997
1997-UA-188
SOUTH MISSISSIPPI EPA
EA123075000
In Re: Petition of South Mississippi Electrical Power Association For Certificate Of Public Convenience and Necessity Authorizing Them To Acquire, Construct, Own and Operate Electrical Transmission Facilities In Covington County, Mississippi (Station Creek-North Collins)
Notice
Notice is hereby given that on the 1st day of April, 1997, South Mississippi EPA filed with the Mississippi Public Service Commission the above referenced matter.
Any person desiring to participate in or receive further notice of these proceedings is required under Rule 6J of the Commissions Public Utility Rules of Practice and Procedure to file a written petition to intervene on or before twenty (20) days from the date of this notice.
This cause is returnable to the next regular meeting of the Commission to be held at 10:00 A.M., Tuesday, the 6th day of May, 1997, at the Mississippi Public Service Commission, 19th Floor, Walter Sillers State Office Building, Jackson, Mississippi. This cause may be heard on said return date, if a hearing is necessary, or be subject to being set for disposition on a hearing date not less than twenty (20) days from the date of publication of this Notice. If protest, answer or other appropriate pleading is on file in response to this matter, the Commission will consider same on said hearing date.
WITNESS MY HAND AND THE OFFICIAL SEAL of the Mississippi Public Service Commission, on this, the 1st day of April, 1997.
Brian U. Ray
Executive Secretary
(Seal)
1 Time: April 9,1997

[84]*84¶ 3. On May 6, 1997, the PSC held a hearing on SMEPA’s petition for a certificate of public convenience and necessity. No objections to the granting of the certificate had been filed. The PSC found that public convenience and necessity required the award of the certificate, and ordered that the certificate be granted to SMEPA. After having been awarded the certificate of public convenience and necessity, SME-PA engineers began drawing construction plans for Line 104. Thereafter, Larry Griffin, SMEPA Director of Land, began negotiations with landowners to obtain rights-of-way for Line 104. By January 21, 2000, SMEPA had obtained a right-of-way from all landowners on whose property Line 104 would run except the Knights. On January 21, 2000, SMEPA filed in the Covington County Circuit Court an application for a condemnation hearing before a special court of eminent domain. On January 22, 2000, the court granted SMEPA’s petition, and set a trial date for May 22, 2000.

¶ 4. On March 20, 2000, the Knights filed a motion to dismiss the eminent domain proceeding, alleging that (1) they had not been provided reasonable notice of the PSC hearing in which the certificate of public convenience and necessity was granted, (2) the condemnation of their property was for private, rather than public, use, and (3) no public necessity existed for the taking of the their property. A hearing on the motion to dismiss was held on June 9 and June 14, 2000. On June 14, 2000, the court denied the Knights’ motion to dismiss. On July 12, 2000, the Knights filed a motion in the circuit court seeking permission to file an interlocutory appeal. On September 19, 2000, the court denied certification. The case proceeded to trial, and on September 10, 2004, the court ordered the portion of the Knights’ property in question to be condemned in order for SMEPA to construct, maintain, and operate Line 104. The court also entered a verdict setting the Knights’ compensation at $7,410.50.

ANALYSIS

¶ 5. This Court reviews motions to dismiss eminent domain proceedings to determine “whether or not the trial judge had sufficient basis to dismiss the condemnation petitions.” Mayor of Vicksburg v. Thomas, 645 So.2d 940, 941-42 (Miss.1994) (quoting Am. Tel. and Tel. Co. v. Purcell Co., 606 So.2d 93, 96 (Miss.1990)). Mississippi Code Annotated Section 11-27-15 (Rev.2004) provides three grounds for dismissal of an eminent domain action:

(1) that the plaintiff seeking to exercise the right of eminent domain is not, in character, such a corporation, association, district or other legal entity as is entitled to the right; (2) that there is no public necessity for the taking of the particular property or a part thereof which it is proposed to condemn; or (3) that the contemplated use alleged to be a public use is not in law a public use for which private property may be taken or damaged.

¶ 6. The Knights’ first issue on appeal is whether they received proper notice regarding SMEPA’s certificate of convenience and necessity hearing before the PSC. However, the Knights’ attorney stipulated that SMEPA had complied with both the statutory notice requirement as well as SMEPA’s procedural rules regarding notice. Therefore, this claim is barred from review. We now consider whether the trial court erred in denying the Knights’ motion to dismiss.

Public Use

¶ 7. Whether a taking is for public use is a judicial question. Mayor of Vicksburg, 645 So.2d at 942. The condem-[85]*85nor has the burden of proving that the taking is for public use. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peggy J. Sturdivant v. Coahoma County, Mississippi;
Court of Appeals of Mississippi, 2020

Cite This Page — Counsel Stack

Bluebook (online)
943 So. 2d 81, 2006 Miss. App. LEXIS 667, 2006 WL 2599631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knight-v-south-mississippi-electric-power-assn-missctapp-2006.