Knapp Refractory Ore Processing Co. v. Idaho Lakeview Mines Co.

178 P.2d 304, 27 Wash. 2d 358, 1947 Wash. LEXIS 286
CourtWashington Supreme Court
DecidedMarch 14, 1947
DocketNo. 30038.
StatusPublished

This text of 178 P.2d 304 (Knapp Refractory Ore Processing Co. v. Idaho Lakeview Mines Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knapp Refractory Ore Processing Co. v. Idaho Lakeview Mines Co., 178 P.2d 304, 27 Wash. 2d 358, 1947 Wash. LEXIS 286 (Wash. 1947).

Opinion

Jeffers, J.

This action was instituted by Knapp Refractory Ore Processing Company, a corporation (herein *359 after referred to as Knapp), against Idaho Lake view Mines Company, a corporation (hereinafter referred to as Idaho), in the superior court for Spokane county, about September 25, 1944.

The general basis of plaintiff’s cause of action, as shown by its amended complaint filed October 25, 1944, is that defendant failed to mill and treat certain ores delivered by plaintiff to defendant, in accordance with a certain written contract made and entered into between the parties on September 11, 1942 (plaintiff’s exhibit No. 1), and that, because of the inefficient milling and treatment of the ore, a substantial amount of the value of the ore was lost.

It is alleged by plaintiff that approximately seven hundred tons of ore was transported to defendant’s mill, and that such ore had an assay value of thirty-five dollars per ton, and could be milled at a profit. It is further alleged that there is due plaintiff from defendant a substantial sum of money, the exact amount of which is unknown, because defendant has failed to account to plaintiff, as required by the contract.

The amended complaint is long and involved. It contains many alleged violations of the contract on the part of defendant, in that defendant did not mill and treat the ore in accordance with a flow sheet furnished by plaintiff; that it did not grind the ore to such a degree of fineness that it would go through an eighty mesh screen; that it had failed to furnish plaintiff with a daily mill shift report and other information to which it was entitled.

As a result of the many claimed violations of the contract on the part of defendant, this action was brought by plaintiff to compel defendant to produce its records for plaintiff’s examination and inspection, and to account to plaintiff for ores, moneys, materials, and concentrates entrusted to its care and custody pursuant to the contract of September 11th.

The amended answer and counterclaims of defendant denied that defendant had breached the contract herein-before referred to. Defendant specifically denied that the ore transported to its mill by plaintiff had an assay value of *360 thirty-five dollars per ton, or any assay value in excess of from twenty to twenty-five dollars per ton, and specifically denied that any of the ore could be milled and treated at a profit.

As a first counterclaim, defendant alleged that, had plaintiff delivered to defendant’s mill, for milling, treatment, and marketing, in accordance with the terms of the contract, fifty-five hundred tons of ore, defendant could have made a profit of not less than twenty thousand dollars, by reason of such milling, treatment, and marketing; that, by reason of plaintiff’s failure to deliver such ore, defendant has been damaged in the sum of twenty thousand dollars.

It is alleged, as a basis for its second counterclaim, that defendant, at plaintiff’s request, paid for work in connection with hauling ore and constructing ore bin, over and above certain credits for materials and supplies, the sum of $660.70, no part of which has been paid.

As a basis for its third counterclaim, defendant alleged that plaintiff delivered to defendant, for milling and treatment, 383 tons of ore, all of which defendant has milled and treated; that, of this amount, concentrates from 269 tons have been shipped to the smelter and settlement therefor received by defendant; that a detailed statement of the cost of milling ,and treating such ore, together with a charge of five dollars per ton, as provided in the contract, was furnished to plaintiff on January 10, 1944, and according to such statement, there is due and owing to defendant, over and above all credits and offsets, the sum of $2,457.49; that, since the furnishing of such statement, defendant has milled and treated the remainder of the ore delivered to it, to wit, 114 tons, and that the cost of milling, including the five dollars per ton charge provided for in the contract, amounts to a total of $719.55; that, as a result of the milling and treatment of the 114 tons of ore, defendant has on hand between four and five tons of zinc concentrate, and two or three tons of lead concentrate, which, on the basis of previous concentrates from such operations which have been shipped to the smelter, would return to defendant the sum of $50.18, less the expense of hauling amounting to $46.62, or a net return *361 to defendant of $3.56, as a credit upon the cost of milling and delivering the ore, leaving a balance of $715.99 due from plaintiff to defendant, or a grand total of $3,173.48 due from plaintiff to defendant for all ore milled, treated, and shipped.

Plaintiff’s reply consists of some twenty pages, wherein is set out and reiterated, only in more detail, many of the allegations of the amended complaint. However, the reply denies and puts in issue the affirmative matter set out in defendant’s answer and counterclaims.

We appreciate that, in view of the fact that the statement of facts comprises some 1,176 pages, it is an extremely difficult matter to present this case within the reasonable confines of an opinion. There are some eighty-seven exhibits, many of them lengthy and containing much phraseology which is technical and understandable only by one who has had at least some experience with mining and milling operations. There are pages of testimony in the record by men who claimed to be experts in mining and milling operations, relative to whether or not the ore which was delivered to defendant’s mill could be profitably milled and treated by the methods employed by defendant, or in accordance with the flow sheet furnished by plaintiff to defendant.

The trial court gave to the case and the different contentions of the respective parties more time and thought than is possible in most cases. It heard oral argument at the close of the case. Written briefs were then submitted, after a consideration of which the court filed a memorandum decision. While this decision was favorable to defendant, the question of the amount of damages to be awarded to defendant on its counterclaims was left open for further discussion. A further hearing was had, and apparently the entire case was reargued orally and upon written briefs, after which the trial court made and filed a very full and comprehensive supplemental memorandum opinion.

When a decree was presented, at least some aspects of the case were reargued, and again upon plaintiff’s motion for a new trial. The original and supplemental memorandum opinions indicate the time and thought which the trial *362 court gave to its consideration of the record, and that it considered all the controlling questions involved.

It is apparent that in this opinion we can discuss only what we consider the controlling questions and, in such discussion, refer to only parts of the evidence. As to the many other questions raised, all we can do is to check the record and see if there is substantial testimony to support the trial court’s conclusions, as set out in the memorandum opinions and carried into the judgment. We do not desire to be understood as holding that the memorandum opinions have been considered as formal findings of fact

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
178 P.2d 304, 27 Wash. 2d 358, 1947 Wash. LEXIS 286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knapp-refractory-ore-processing-co-v-idaho-lakeview-mines-co-wash-1947.