KMS Fusion, Inc. v. United States

37 Cont. Cas. Fed. 76,224, 24 Cl. Ct. 582, 1991 U.S. Claims LEXIS 564, 1991 WL 255865
CourtUnited States Court of Claims
DecidedDecember 4, 1991
DocketNo. 649-87C
StatusPublished
Cited by2 cases

This text of 37 Cont. Cas. Fed. 76,224 (KMS Fusion, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KMS Fusion, Inc. v. United States, 37 Cont. Cas. Fed. 76,224, 24 Cl. Ct. 582, 1991 U.S. Claims LEXIS 564, 1991 WL 255865 (cc 1991).

Opinion

OPINION

SMITH, Chief Judge.

This is a direct access suit under the Contract Disputes Act, 41 U.S.C. § 601 et seq. (1982). Plaintiff, KMS Fusion, Inc. (KMS) claims it is entitled to recover amounts allegedly due under a contract with the United States Department of Energy (DOE). KMS maintains that it is entitled to approximately $1,000,000 in indirect costs incurred in calendar years 1983 and 1984 which were improperly denied in a final decision of the contracting officer (CO).

This case comes before the court on the parties’ cross-motions for summary judgment. There are six types of indirect costs in dispute. For the reasons given below, the court grants plaintiff’s motion for summary judgment as to four of the cost types, grants defendant’s motion for summary judgment as to one of the cost types, and denies both parties’ motions as to a sixth cost type.

FACTS

On December 22, 1981, DOE awarded KMS contract no. DE-AC08-82DP40152 to perform research and development in connection with DOE’s inertial confinement fusion (ICF) program through its Nevada Operations Office. The cost plus fixed-fee contract provided for a five-year performance period beginning on January 1, 1982, and ending on December 31, 1986. The contract was later extended through April 30, 1987. The total estimated contract price was $64,430,700 which included a fixed fee of $5,055,000.

Pursuant to the contract, KMS billed DOE during the course of contract per[584]*584formance for its direct costs (labor and material) and its indirect costs. The indirect costs usually consisted of general and administrative (G & A) and labor overhead expenses. KMS billed using interim indirect rates.1 As soon as possible after each calendar year, KMS submitted a final indirect cost proposal based upon that year’s actual overhead and G & A costs that were allocated to and allowable under the contract. These indirect rates were to be finalized after each completed year based upon audits conducted by the Defense Contract Audit Agency (DCAA).

The DCAA would audit KMS’ accounts to verify the indirect cost proposal and forward an advisory audit report to DOE to be used in negotiating final indirect cost rates. Upon receiving DCAA’s revised audit reports for calendar year (CY) 1983 and CY 1984, DOE proposed to disallow a total amount of $1,288,760. KMS disputed the disallowance and requested that the CO prepare a final decision on the issue. The CO’s final decision disallowed a total amount of $1,059,968 in indirect costs.

Six types of disallowed indirect costs are in dispute: (1) bid and proposal (B & P) costs in excess of a formula ceiling; (2) the cost of operating a Washington, D.C., office; (3) costs related to travel by plaintiff’s vice president, Mr. Terence C. Liddy; (4) the cost of retaining government affairs consultants; (5) costs incurred in marketing and installing for demonstration purposes a product called the Multiplexor; and, (6) profit realized on the sale of an option to purchase real property as a recovery of home office rental costs. Each type of indirect cost will be discussed separately.

DISCUSSION

1. Bid & Proposal Costs

For most of its history KMS has been almost wholly dependent on its inertial confinement fusion contracts with DOE. At the end of the 1970s KMS recognized that it had to expand its business base beyond the DOE contract in order to ensure its long-term survival.

The DOE encouraged KMS to diversify. Many DOE officials believed that the ICF program would benefit from KMS’ participation. This participation would be jeopardized if KMS, because of its undue reliance on its ICF contract, could not withstand reductions in ICF program funds. KMS’ diversification would also result in a reduction in indirect costs allocated to the DOE contract in future years.

As part of the diversification effort KMS began to implement an extensive B & P program in mid-1982. The federal procurement regulations in effect on the date of the contract award generally permit recovery of B & P expenses.2 41 C.F.R. § 1-15.205-3 (1981). In contrast, the DOE procurement regulations limit recovery through the application of a ceiling based on an average of the contractor’s actual B & P costs for its three most recent years. 41 C.F.R. § 9-15.205-3 (1981). The regulation further provides that a different ceiling could be established by the contracting officer should application of the formula result in inequitable recovery.3

Factual Dispute

KMS contends that an agreement existed between it and DOE to negotiate B & P ceilings individually for the years 1982, [585]*5851983, 1984, and 1985. DOE admits that it encouraged KMS to diversify and agreed not to apply a regulatory formula to limit KMS’ recovery of B & P expenses for CY 1983 and CY 1984. DOE denies agreeing to negotiate individual B & P ceilings and asserts that an unpublished DOE formula controls, so that recovery is limited to an average of the most recent years available.

According to the affidavit of KMS’ Director of Contracts, Robert F. McCarthy, because KMS had almost no history of B & P he contacted DOE’s Contract Administrator, Rex Purcell, regarding establishment of a ceiling different from the one that would be established by the formula. A letter dated August 31,1982 from Mr. Purcell stated that the letter was a follow-up to a discussion on August 18, 1982, and that KMS should submit a petition for cost reimbursement for B & P. On October 25, 1982, Mr. McCarthy submitted a 1982 B & P plan. A letter which accompanied the plan stated, “we propose that the reasonableness of B & P/IR & D4 costs be negotiated with the Contracting Officer____” The total estimated for B & P for CY 1982 was $307,000.

On November 16, 1982, the acting CO, John R. Gilpin, sent a letter to KMS that stated, “... allocation base ceiling amounts for B & P and IR & D are established at $299,0005 and $138,000 respectively.” The letter went on to say, “[irrespective of the above, CY 82 B & P and IR & D costs claimed by [KMS] for reimbursement under Government contracts will be subject to prior audit review and a determination of allowability in accordance with contract terms and conditions.” Based on these letters and on discussions with Mr. Purcell, Mr. McCarthy understood that ceilings for B & P costs would be negotiated with the contracting officer until KMS had developed a representative base for application of the three-year formula. The actual B & P costs incurred by KMS in CY 1982 were $265,512. KMS was reimbursed for this entire amount.

On November 4, 1983, Mr. McCarthy submitted a B & P plan for CY 1983. The accompanying letter stated, “[w]e are again proposing that the reasonableness of the B & P/IR & D costs be negotiated with you.” The total estimated for CY 1983 for B & P was $407,000. A letter dated March 20, 1984 from Mr. Purcell stated that, with one exception,6 all the B & P and IR & D projects met the test of “benefit to DOE.” In his affidavit Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Teknowledge Corp. v. United States
85 Fed. Cl. 235 (Federal Claims, 2009)
Allenfield Associates v. United States
42 Cont. Cas. Fed. 77,267 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,224, 24 Cl. Ct. 582, 1991 U.S. Claims LEXIS 564, 1991 WL 255865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kms-fusion-inc-v-united-states-cc-1991.