Klug v. Ireland

64 P.2d 131, 99 Colo. 542, 1936 Colo. LEXIS 263
CourtSupreme Court of Colorado
DecidedDecember 31, 1936
DocketNo. 14,044.
StatusPublished

This text of 64 P.2d 131 (Klug v. Ireland) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Klug v. Ireland, 64 P.2d 131, 99 Colo. 542, 1936 Colo. LEXIS 263 (Colo. 1936).

Opinion

Mr. Justice Burke, sitting for Mr. Chief Justice Campbell,

delivered the opinion of the court.

This was a statutory adjudication for the settlement of priorities to water for irrigation. These parties appear here as in the trial court. For convenience we refer to them as Klug and Ireland respectively.

*543 The question here presented, and the only one raised by the assignments, is the correct date of Klug’s priority for his reservoir No. 3. This the court fixed as of December 13, 1921. He contends it should have been July 6, 1918. The question is solely one of evidence. Klug says that on July 6, 1918, he decided to build his reservoir. Thereafter he had a survey made and filed his map and statement of claim September 9, 1919. On April 7, 1920, he contracted with Ireland, then the owner, for the purchase of the land on which to build, paying $100, and in the fall of that year surveyed his outlet ditch. Other work consisted principally in unsuccessful attempts to raise money. Said $100 was on a total of $4,800. Other payments under that contract were never made. December 13, 1921, an entirely new contract was entered into which took no note of the former payment. There is evidence that actual work of construction thereunder did not begin until the late spring of 1922. There is also evidence that on July 1, 1920, Klug told Ireland to keep the $100 as he did not intend to complete the deal. Other conflicting evidence need not be recited. Enough has been set forth to show ample justification for the date fixed by the trial court under the well recognized rule that diligence must be shown from inception to completion. Holbrook Irr. Dist. v. Ft. Lyon Canal Co., 84 Colo. 174, 269 Pac. 574. What constitutes diligence depends upon the facts of each particular case. Conley v. Dyer, 43 Colo. 22, 28, 95 Pac. 304. Trivial labor and expenditures will not carry the appropriation back by relation to the first substantial act of the appropriator for its acquisition. Fruitland Irr. Co. v. Kruemling, 62 Colo. 160, 162 Pac. 161. Moreover, the record affords ample justification for the conclusion that on July 1, 1920, Klug had abandoned all intention of prosecuting tire work under his contract of April 7, 1920, and that conclusion is reinforced by his new contract of December 13, 1921.

The judgment is accordingly affirmed.

Mr. Justice Hilliard and Mr. Justice Holland concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holbrook Irrigation District v. Fort Lyon Canal Co.
269 P. 574 (Supreme Court of Colorado, 1928)
Conley v. Dyeb
95 P. 304 (Supreme Court of Colorado, 1908)
Fruitland Irrigation Co. v. Kruemling
162 P. 161 (Supreme Court of Colorado, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
64 P.2d 131, 99 Colo. 542, 1936 Colo. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/klug-v-ireland-colo-1936.