Klein v. Mr. Transmission, Inc.

318 So. 2d 676, 294 Ala. 437, 1975 Ala. LEXIS 1222
CourtSupreme Court of Alabama
DecidedAugust 21, 1975
DocketSC 773
StatusPublished
Cited by8 cases

This text of 318 So. 2d 676 (Klein v. Mr. Transmission, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Klein v. Mr. Transmission, Inc., 318 So. 2d 676, 294 Ala. 437, 1975 Ala. LEXIS 1222 (Ala. 1975).

Opinion

*439 SHORES, Justice.

This is an appeal from a judgment entered on a jury verdict in the amount of $15,800 in favor of Mr. Transmission, Inc. (plaintiff) against B. H. Klein Realty Corporation (Klein) and Andrew & Dawson, individually and as partners doing business as a general building contractor. Roosevelt Jackson was also a defendant. He had entered into a subcontract with Andrew & Dawson to finish the wall after the original subcontractor walked off the job when the wall was approximately 70% complete. The jury returned a verdict in his favor.

Andrew & Dawson had contracted to build an addition to a building owned by Klein. Plaintiff occupied a building located directly north of the new addition and separated from it by approximately one and one-half feet. The north wall of the addition to the Klein building was 115 feet across and- three stories high. It consisted of a brick veneer, 2-inch air space, and concrete block.

As of the end of work on May 23, 1973, the third floor portion of the north wall was tied in to the remainder of the building as follows:

At the floor level, the brick and block were resting on the floor. The brick had been “raised” all the way to the roof; and the block had been “raised” all the way to the ceiling. At the roof level, the brick was connected to the roof by dovetail anchors. The brick and block were connected to each other by metal ties. Pursuant to the specifications, these metal ties were to be spaced at 16-inch intervals, vertically. The north and east walls connected at the northeast corner of the addition. The west wall was complete through the second floor level, thus there was no connection for the north wall at its northwest corner. The north wall of the new addition collapsed on the night of May 23, and the third floor portion of the wall fell through the roof of the building occupied by the plaintiff.

Plaintiff’s suit charged negligence in the construction of the wall in failing to brace it during the construction, and in failing to follow the specifications with regard to placing metal ties at 16-inch intervals.

The action was defended on the assertion that there was no negligence in failing to brace the wall; that it was constructed in accordance with procedures normally followed in the construction of buildings in Montgomery; and that the wall fell not because of any negligence on the part of the defendants, but because of an act of God. According to Taylor Dawson, the fall was caused by “A wind that you couldn’t anticipate and couldn’t protect against.”

Andrew & Dawson, on appeal, argue that the trial court erred in denying the motion for directed verdict offered by them, because it is contended that the record is devoid of any evidence that the wall collapsed by virtue of any negligence on their part.

There is no question that the wall fell and damaged the building occupied by the plaintiff. What caused it to fall was a jury question. Each side offered evidence to support its position. From the plaintiff’s side came testimony from an expert witness, a structural engineer, who testified that he examined the construction site on May 24, 1973, not at the request of the plaintiff but at the request of the owner of the damaged building; and that, based upon his examination of the building specifications for the addition and an examination of the building itself, it was his opinion that the wall should have been braced. The witness testified:

“A In my opinion, given the circumstances that I know and the peculiar sit *440 uation of this wall, I think it should have been braced.
“Q Tell the jury what you mean by peculiar situation relating to this wall. What was unique about this wall ?
“A As has already been described the wall is a hundred and fifteen feet long, or was a hundred and fifteen feet long, and eleven feet, five inches high. It did not have any intersecting walls or partitions except, of course, the east wall, northeast corner. . . .”

This witness also testified:

“A At the stage of construction, it was not supported at the northwest corner, because of the absence of the west wall at the third floor. The wall was in effect supported only at the floor and, if completed, only at the roof. And I would — my evaluation as a structural engineer, I would think, it would be very weak in its structural strength in this condition until it had attained a full age as far as curing of the wall is concerned.”

He defined curing as meaning that it takes a 28-day period for mortar to obtain its designed strength; and that the mortar in this wall had not obtained that strength, the last part of the wall having just been completed prior to the time the wall fell.

The defendants introduced evidence which tended to show that the building was constructed in accordance with standard acceptable practice for construction, and assert that there was no evidence that any improper construction in the wall itself contributed to its collapse.

However, the building specifications were admitted into evidence and provide in part:

“THE CONTRACTOR MUST TAKE ALL NECESSARY PRECAUTIONS TO INSURE THE SAFETY OF THE WORKMEN EMPLOYED ON THE JOB, TO PREVENT DAMAGE TO PERSONS AND PROPERTY NOT CONNECTED WITH THE JOB AND TO PREVENT THE OCCURRENCE OF ANY ACCIDENTS WHATSOEVER DURING THE PROGRESS OF THE WORK.
“THE CONTRACTOR . . . SHALL PROTECT AND CARE FOR SURROUNDING BUILDINGS, SHOULD THERE BE ANY DANGER TO TPIEM CAUSED BY THE WORIC.’¿

Additionally, Mr. Dawson, one of the contractors, testified that the Southern Standard Building Code applies to construction in Montgomery; and, although there was disagreement among the parties as to whether certain provisions applied, it was conceded by Mr. Dawson that Section 2101.10 did apply to construction in Montgomery. That section provides:

“When a building or structure is to be carried above the roof of an adjoining building, protection for the skylights and roof of such adjoining building shall be provided, at his own expense, by the person constructing or causing the construction of such building or structure; provided that if the owner, lessee or tenant of the adjoining building should refuse permission to have the roofs and skylights protected, the responsibility and expense for the necessary protection shall devolve on the person refusing such permission.”

Mr. Dawson testified that he had not sought permission, nor had the owners of the adjoining buildings refused to allow him, to protect the roofs of their buildings.

Roosevelt Jackson’s pretrial deposition was entered in evidence. It disclosed that when he took over the job of finishing the wall, the brick was approximately three feet short of the third floor and the con *441 Crete block was up to the third floor. When the wall fell on May 23, the block had been up to the third floor ceiling about two days. The brick had been “topped out” on May 23.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Speedway LLC
N.D. Alabama, 2024
Upton v. Heaton
653 So. 2d 938 (Supreme Court of Alabama, 1995)
Elmore County Com'n v. Ragona
540 So. 2d 720 (Supreme Court of Alabama, 1989)
Dunn v. Wixom Bros.
493 So. 2d 1356 (Supreme Court of Alabama, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
318 So. 2d 676, 294 Ala. 437, 1975 Ala. LEXIS 1222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/klein-v-mr-transmission-inc-ala-1975.