Kjd, LLC v. City of Tea

2025 S.D. 22
CourtSouth Dakota Supreme Court
DecidedApril 9, 2025
Docket30439
StatusPublished

This text of 2025 S.D. 22 (Kjd, LLC v. City of Tea) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kjd, LLC v. City of Tea, 2025 S.D. 22 (S.D. 2025).

Opinion

#30439-a-PJD 2025 S.D. 22

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

KJD, LLC, Appellant,

v.

CITY OF TEA, SOUTH DAKOTA Appellee.

APPEAL FROM THE CIRCUIT COURT OF THE SECOND JUDICIAL CIRCUIT LINCOLN COUNTY, SOUTH DAKOTA

THE HONORABLE JOHN PEKAS Judge

JAMES E. MOORE CHRISTOPHER A. DABNEY of Woods Fuller Shultz & Smith P.C. Sioux Falls, South Dakota Attorneys for appellant.

CLINT SARGENT RALEIGH HANSMAN of Meierhenry & Sargent, LLP Sioux Falls, South Dakota Attorneys for appellee.

ARGUED APRIL 24, 2024 OPINION FILED 04/09/25 #30439

DEVANEY, Justice

[¶1.] The City of Tea passed a resolution imposing a special assessment

against property abutting a road construction project, including property owned by

KJD, LLC, after finding that the City’s improvement conferred special benefits on

the property abutting the project above and beyond that experienced by the public

at large. KJD filed an appeal in circuit court, objecting to the assessment the City

imposed against its property. The parties submitted written arguments, and after a

hearing, the court held that KJD did not rebut the presumption that the City’s

assessment is valid and did not prove by clear and convincing evidence that the

City’s findings in support of its assessment were incorrect. The court therefore

entered a judgment denying KJD’s objection. KJD now appeals to this Court, and

we affirm.

Factual and Procedural Background

[¶2.] The City approved a plan (the Project) to improve and expand its main

corridor and connection to Interstate 29. To complete the Project, the City passed a

resolution that would allow it to institute condemnation actions against landowners

abutting the Project, and on June 11, 2020, the City commenced a condemnation

action against KJD. This appeal does not concern the condemnation action, which

according to KJD, settled in December 2023.

[¶3.] While the condemnation action was pending, the City passed a

resolution of necessity in April 2021, declaring that the City would finance a portion

of the Project by levying a special assessment against properties fronting and

-1- #30439

abutting the Project, including KJD’s, that specially benefited from the Project. The

resolution listed the following findings in support of the assessment:

• The project will make the property abutting the project a better place in which to conduct business.

• The property will only be assessed the costs for the special benefit of the improvements.

• The adjacent property will receive a special benefit by changing the properties[’] highest and best use from rural in character to urban.

• The improvement will provide easier access to the abutting properties.

• The improvements will provide a special benefit to the assessed properties by improving and enhancing the aesthetics and safety, thus enhancing the value, use, and enjoyment of the property.

• The improvements will enhance the market value of the properties abutting the improvement.

• The property abutting the improvements will receive a special benefit above and beyond that benefit enjoyed by the general public.

• That the value of the special benefit equals or exceeds the special assessment.

• Failure to assess property abutting the improvements would result in a windfall to the property owners.

The resolution further provided that the City “considered the character of the

improvements, the situation, the surrounding conditions, and whether the

substantial benefits to be derived from the improvements are local or general in

their nature.” It also stated that the City “calculated the portion of the

improvements which confers a local special benefit and the general benefit and

advantage on the property of the whole community.” The resolution further stated

-2- #30439

that the total estimated cost of the Project is $16,000,000, with part financed by

special assessments and the City paying the “over size” costs of $14,945,000.

[¶4.] Thereafter, on October 4, 2021, the City passed a separate resolution

approving a special assessment roll detailing the total amount each of the

approximately 30 properties abutting or fronting the Project would be assessed. As

it relates to KJD’s property, the resolution approved a total assessment of

$61,623.38, representing “Water, Sewer, Curb and Gutter, Street Lighting and

Sidewalk Assessments.” KJD appealed the assessment to the circuit court.

[¶5.] In a written brief to the circuit court, KJD noted this Court’s statement

in Hubbard v. City of Pierre that “[a] municipality’s power to impose special

assessments is limited by the constitutional requirement that the project confer a

special benefit on the assessed property.” 2010 S.D. 55, ¶ 13, 784 N.W.2d 499, 505.

KJD then argued that the City’s assessment is unconstitutional because, in its view,

the Project did not confer a special benefit on its property. In support, KJD relied

on the information in documents attached to an affidavit of KJD’s counsel

submitted with its brief. These include an appraisal report the City obtained for the

condemnation action and an appraisal KJD obtained after the special assessment.

KJD also relied on the City’s admission made in response to KJD’s request for

admissions that the Project did not benefit KJD’s property within the meaning of

SDCL 21-35-17, a statute governing condemnation actions. KJD additionally

challenged the City’s method of calculating the amount of the assessment based on

the cost of the Project rather than by determining “the value of the special benefits

received by an individual property.” KJD asked the court to declare the assessment

-3- #30439

unconstitutional and enter an order invalidating the assessment against its

property or enjoining the City from collecting it.

[¶6.] In the City’s responsive brief, it asserted that KJD’s property received

special benefits from the Project as identified “in both its Resolution of Necessity

and its discovery responses in this [challenge].” The City then quoted its answer to

KJD’s interrogatory asking what special benefit KJD’s property would receive:

• The rural county road abutting the Property will be replaced with an urbanized multi-lane municipal roadway. The new roadway will include additional lanes of travel, curb and gutter, sidewalks, access control, a municipal water main and improved drainage conveyance.

• Curb and gutter will make the Property safer by creating a barrier that keeps vehicle traffic within the roadway and off of the Property. Curb and gutter will improve the drainage conveyance. Curb and gutter will enhance the aesthetics of the Property.

• Street lighting and sidewalks will enhance the aesthetics of the Property and make the Property safer for its current and future customers, suppliers and employees.

• Adding lanes of travel to the roadway abutting the Property and access control in the vicinity of the Property via a median and traffic signal will reduce congestion, improve traffic flow and improve safety for current and future customers, suppliers and employees while traveling to and from the Property and while being present on the Property.

• The municipal water main will provide fire protection with the installation of fire hydrants, which will improve safety, as well as, potentially lower casualty insurance rates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norwood v. Baker
172 U.S. 269 (Supreme Court, 1898)
United States v. Miller
317 U.S. 369 (Supreme Court, 1943)
United States v. Reynolds
397 U.S. 14 (Supreme Court, 1970)
Rupert v. City of Rapid City
2013 S.D. 13 (South Dakota Supreme Court, 2013)
Hubbard v. CITY OF PIERRE
2010 SD 55 (South Dakota Supreme Court, 2010)
Krsnak v. South Dakota Department of Environment & Natural Resources
2012 S.D. 89 (South Dakota Supreme Court, 2012)
Hurley v. State
143 N.W.2d 722 (South Dakota Supreme Court, 1966)
Hawley v. City of Hot Springs
276 N.W.2d 704 (South Dakota Supreme Court, 1979)
Ruel v. Rapid City
167 N.W.2d 541 (South Dakota Supreme Court, 1969)
State Highway Commission v. Bloom
93 N.W.2d 572 (South Dakota Supreme Court, 1958)
State Ex Rel. Department of Transportation v. Miller
2016 SD 88 (South Dakota Supreme Court, 2016)
CED Properties, LLC v. City of Oshkosh
2018 WI 24 (Wisconsin Supreme Court, 2018)
Winona & St. P. R. v. City of Watertown
44 N.W. 1072 (South Dakota Supreme Court, 1890)
State Highway Commission v. Emry
244 N.W.2d 91 (South Dakota Supreme Court, 1976)
Lewis & Clark Rural Water System, Inc. v. Seeba
2006 SD 7 (South Dakota Supreme Court, 2006)
S.D. Dep't of Transportation v. Legacy Land Co.
2023 S.D. 58 (South Dakota Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2025 S.D. 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kjd-llc-v-city-of-tea-sd-2025.