Kitchin v. Gary Steel Products Corp.

83 S.E.2d 348, 196 Va. 259, 1954 Va. LEXIS 219
CourtSupreme Court of Virginia
DecidedSeptember 8, 1954
DocketRecord 4255
StatusPublished
Cited by6 cases

This text of 83 S.E.2d 348 (Kitchin v. Gary Steel Products Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kitchin v. Gary Steel Products Corp., 83 S.E.2d 348, 196 Va. 259, 1954 Va. LEXIS 219 (Va. 1954).

Opinion

Whittle, J.,

delivered the opinion of the court.

The case here under review is a contract action brought by Gary Steel Products Corporation, hereinafter called Gary, against J. F. Kitchin, trading as Norfolk Contracting Company, hereinafter called Kitchin, and Bay City Shovels, Incorporated, hereinafter called Bay City, for the recovery of $11,611.02. For this sum Gary obtained judgment in the court below against Kitchin.

Monsanto Chemical Company, hereinafter called Monsanto, was engaged in the manufacture of chemicals in the City of Norfolk. It desired to have fabricated and erected upon its boilerhouse a new steel smokestack, and contracted with Gary to do the work. In the process of erection a section of the stack fell through the boilerhouse, causing the damage for which Monsanto sued Gary and recovered a judgment in the amount of $11,611.02.

The instant suit was brought by Gary against Kitchin for reimbursement of this sum which Gary paid Monsanto. Gary based its claim on a contract which it allegedly had with Kitchin for the erection of the stack, after its fabrication by Gary.

Numerous motions and pleadings were filed and passed *261 upon by the trial court before the issue was finally joined upon the motion for judgment filed by Gary against Kitchin and Kitchin’s answer thereto.

In addition to his answer to the motion Kitchin filed a counterclaim against Gary for $3,008, as “rental for the cranes” used in the erection of the stack.

Bay City, which manufactured the crane used in erecting the stack, was joined as a party defendant, but upon motion, the evidence against Bay City was stricken by the court, to which ruling an exception was taken. This exception, however, was not insisted upon on appeal and therefore Bay City is no longer involved.

The motion for judgment contained the following allegation:

“The defendant Kitchin entered into a contract with the undersigned plaintiff Gary, by which the said Kitchin agreed to erect and put in place on the said boiler the aforesaid steel smokestack, and it was further agreed between Gary and Kitchin that if in the erection of the smokestack there should be any failure on the part of the smokestack the liability for the resulting damages should be upon Gary, and if there should be any failure on the part of the crane or its operation the liability for the resulting damages should be upon Kitchin.”

It was further alleged that “the said crane collapsed and failed as the result of the insufficiency of the crane and the carelessness and negligence” of Kitchin, his servants, agents and employees; that when Gary was sued by Monsanto, Kitchin was notified of the pending suit and was invited to defend it, which invitation was declined; that upon Kitchin’s refusal to defend the suit Gary defended it; that Monsanto recovered the judgment aforesaid which was paid by Gary; and that Gary should now be reimbursed by Kitchin, under the contract, for the payment so made.

While Kitchin’s answer to the motion for judgment denied the existence of the contract alleged by Gary, it did not point out the relationship which Kitchin claimed to exist. *262 Only in his counterclaim was his position made known. There it was contended that Gary “rented certain cranes from the defendant”, to be used in the erection of the smokestack. Kitchin asserted that he “fully performed (the) rental agreement” with Gary and had not been paid for the use of the cranes.

Gary’s answer to the counterclaim denied owing in full the amount so claimed; it denied the existence of the alleged rental agreement and reasserted the contract stated in the motion for judgment which was that Kitchin agreed to erect the stack and to be solely responsible therefor. The answer further asserted that Kitchin’s compensation for the work was to be “based on reasonable time to accomplish the work but in no way (had Gary) rented any crane or cranes from the defendant”, as alleged by Kitchin in the counterclaim.

Further answering the counterclaim, Gary asserted that Kitchin had agreed to raise the stack in one section but changed his plans and undertook to raise it in “more than one section”, and instead of using the “Northwest” crane originally planned, substituted another; the change in the agreed manner of erecting the stack resulting in additional time being consumed for which Gary should not be required to pay.

The issue in the case thus narrowed down to one question: What was the understanding between the parties relative to the erection of the smokestack? If the contract was as Gary claimed in its motion for judgment and in its answer to Kitchin’s counterclaim, the judgment for Gary was proper. If, on the other hand, Kitchin, as alleged in his counterclaim, only rented a usable crane to Gary, without assuming further responsibility, he owed Gary nothing.

The evidence regarding the alleged contract between Kitchin and Gary was conflicting. Gary introduced testimony to the effect that it was engaged in the business of working metals and that it was equipped to fabricate the smokestack but had no means of erecting it; that it attempted *263 to bid on the fabrication of the stack only; that Monsanto insisted upon a bid for a completed job, one covering both fabrication and erection; that Monsanto would not entertain separate bids; that Gary saw Kitchin’s advertisement seeking employment in the erection of smokestacks; that Kitchin was contacted regarding the Monsanto job; that the oral contract alleged in the motion for judgment resulted; that when the terms of the contract between Gary and Kitchin for the erection of the stack had been agreed upon Gary submitted to Monsanto its bid on the completed job which was accepted; that the stack was properly fabricated by Gary; that Monsanto notified Gary that its plant would be shut down at a certain time and the stack could then be erected, and Gary so notified Kitchin; that Kitchin changed the plans as contemplated in the original contract and undertook to erect the stack in two sections instead of one; that Kitchin also changed his original plan to use the “Northwest” crane and substituted the Bay City equipment; that Kitchin then undertook the erection of the stack and a section thereof fell through the boilerhouse causing the damage complained of; that Monsanto sued Gary for the resultant damage and recovered the sum of $11,611.02; that Gary paid Monsanto the judgment thus recovered and was suing Kitchin, under the contract, for reimbursement.

The evidence introduced by Kitchin tending to prove his theory of the case was that Gary, not having the equipment necessary to erect the stack after its fabrication, rented the equipment from Kitchin; that Kitchin was only obligated to furnish the crane and operator at $20 per hour; that Gary was to use the equipment and the operator in erecting the smokestack and that Kitchin was not to be responsible therefor.

On the evidence thus adduced the jury, as aforesaid, returned a verdict for Gary in the amount sued for, upon which judgment was entered.

Kitchin agrees that the jury’s verdict, based upon conflicting evidence, properly admitted, and under proper in *264

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estes Exp. Lines v. Chopper Exp.
641 S.E.2d 476 (Supreme Court of Virginia, 2007)
Aldridge v. Atlantic Rural Exposition
67 Va. Cir. 404 (Richmond County Circuit Court, 2005)
Hiett v. Lake Barcroft Community Ass'n
418 S.E.2d 894 (Supreme Court of Virginia, 1992)
Nido v. Ocean Owners' Council
378 S.E.2d 837 (Supreme Court of Virginia, 1989)
Duszynski v. B & T Riding Academy, Inc.
145 N.W.2d 736 (Wisconsin Supreme Court, 1966)
Gary Steel Products Corp. v. Kitchin
90 S.E.2d 120 (Supreme Court of Virginia, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
83 S.E.2d 348, 196 Va. 259, 1954 Va. LEXIS 219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kitchin-v-gary-steel-products-corp-va-1954.