[Cite as Kirn v. Heifner, 2014-Ohio-535.]
IN THE COURT OF APPEALS FOR GREENE COUNTY, OHIO
KATHRYN KIRN :
Plaintiff-Appellant : C.A. CASE NO. 2013 CA 44
v. : T.C. NO. 13CVI500
BRIAN HEIFNER : (Civil appeal from Municipal Court) Defendant-Appellee :
:
..........
OPINION
Rendered on the 14th day of February , 2014.
KATHRYN KIRN, 241 S. Dawson Avenue, Columbus, Ohio 43209 Plaintiff-Appellant
BRIAN HEIFNER, 4770 Old Rt. 35 East, Jamestown, Ohio 45335 Defendant-Appellee
DONOVAN, J.
{¶ 1} This matter is before the Court on the pro se Notice of Appeal of
Kathryn [Cite as Kirn v. Heifner, 2014-Ohio-535.] Kirn, filed August 14, 2013. Kirn appeals from the July 17, 2013 decision of the Xenia
Municipal Court in favor of Brian Heifner on Kirn’s Small Claims Complaint. We hereby
affirm the decision of the trial court.
{¶ 2} Kirn’s complaint provides that “B. Heifner installed propane / heat pump
furance (sic) 12/3/12. At 4864 OLS (sic) U.S. 35 E but heat pump didn’t work * * * See
attached small claim information sheet.” The information sheet provides that Kirn sought
$953.00 plus interest, and it provides: “B. Heifner installed propane heat pump furnace
12/3/12 at 4864 old U.S. 35 East but heat pump didn’t work. Brian returned several times
but was unable to find problem. Finally had to call Lowes HVAC. 2 men worked 3 hours
($370.) Fan stayed on continually so Lowes returned for 1 hour ($140). Heat pump went
out again. So Rheem installer came from Dayton. Found too small a wire used which
overheated and blew (2) time delay fuses. Replaced for $192.70. Heifner added $400 later
to bill for $100 thermostat. Bill paid thinking installation completed, but wasn’t.”
{¶ 3} A trial was held on July 16, 2013. Kirn testified that Heifner installed a
furnace and heat pump at her rental property, and that she paid him on December 3, 2012.
She stated that she “chose the heat pump because it takes the heat from the air, it’s less
expensive; and then after thirty degrees, there’s no more heat left in the air. So as a backup,
we discussed another oil or propane [furnace]. * * * we went to propane for this second
furnace. So it’s heat pump down to thirty degrees, then propane from there on down in cold
weather.” Kirn stated that her renters advised her in February that the “propane was on but
the heat pump, which should be on, was not. The day I was there, it was forty-three degrees
and the propane was on.” She stated that “Brian had come several times but couldn’t fix
it.” She testified that the “heat pump never did get installed properly.” Kirn stated that she 3
told her tenants to contact Heifner, and that they “said he’d been back several times, couldn’t
figure the problem.” Kirn stated that she phoned Heifner Heating and Cooling and “said I
wanted a different person to come out and look at the installation. She said, well, Brian did
this on his own, we are not backing it up.”
{¶ 4} Kirn stated that she contacted “Lowe’s brothers, Lowe’s HVAC,” and that
“two men worked three hours.” She stated that the men “changed from twenty-five degrees
on the heat pump back to what is called for in the manual at thirty degrees, because there’s
no heat in the air under thirty degrees.” Kirn stated that the temperature at the time “was
under thirty degrees so they couldn’t tell if the heat pump was going to work after they
checked everything.” Kirn stated that the pump “didn’t work when it warmed up,” and that
the men from Lowes came back and determined that the “blower was running full-time.
They corrected that. They checked the Freon. They checked it out as much as they could.”
According to Kirn, the heat pump “still wasn’t working. It had never been installed to
where it was working properly.”
{¶ 5} Kirn stated that she “called a third person named Patrick who installs
Rheems in Dayton. He came out and he found that the heat pump had a wire - - one of the
two wires was too small. And he used the word this bigger one is a thirty-five, the smaller
one’s only a thirty; it’s overheating, throwing the two breakers. And he said that’s been
your problem the whole time.”
{¶ 6} Kirn asserted that “the first tank of propane had a leaky valve and [the
renters] lost a lot of propane and the dealer supposedly compensated them. I think he
undercompensated.” She stated that the renters “sneaked out owing me January, February, 4
March, April’s rent. They couldn’t pay their bills.”
{¶ 7} Kirn submitted two bills from “Lowe’s HVAC,” one of which is dated March 7,
2013, in the amount of $140.00, and provides, “Checked refrigerant charge, adjusted charge and
tstat,” and indicates a charge of $70.00 for labor and $70.00 for a service call, and another which
indicates it was paid on March 5, 2013, in the amount of $370.00, and provides, “rewired
control wiring on heat pump and LP gas furnace. Set thermostat for dual fuel and heat pump,”
and indicates a charge of $300 for three hours of labor by two men, and a $70.00 service call
charge. Kirn also submitted “Dale’s Bill,” dated May, 2013, which contains multiple unrelated
charges but includes a highlighted charge of $80.00 for “heat pump re-wire-extra,” and Kirn
stated that it was from Dale Peckham “for installing the wire” for the heat pump. Kirn stated
that the system has worked since Dale Peckham installed the new wire. Finally, Kirn submitted
a receipt, dated April 12, 2013, from “Lowe’s Home Centers, Inc.,” in the amount of $112.70, “to
buy the new breakers and the wire.”
{¶ 8} Kirn asserted that “Lowe’s told me that * * * I was really overcharged for the
thermostat and kit * * *. So I got on the internet this week and first thing under the Honeywell,
they gave FocusPRO thermostats, no need for external kits, no need for wires, reduces the backup
heat needed.” Kirn stated that she “found one on line for a hundred and eighty five dollars plus
eleven to ship it. So it was two hundred. * * * .” The following exchange occurred:
MS. KIRN: And I had also asked - -said that he had overcharged on the
thermostat according to Lowe’s.
THE COURT: Well, I don’t have anything from Lowe’s that tells me that,
do I? 5
MS. KIRN. No. That was personal, yes.
THE COURT: And I’m not going to take anything off the internet.
MS. KIRN. Okay. All I’ve got is the cost of the Honeywell, three copies
of it. I don’t know if she wants these or not.
THE COURT: * * * That’s total of seven hundred and two dollars. * * *
What do you have that you don’t know if I want?
MS. KIRN: Lowe’s said I was terribly overcharged so I got what it - - the
thermostat, the Honeywell recommended thermostat.
THE COURT: Off the internet?
MS. KIRN: Off the internet.
THE COURT: I don’t want those.
{¶ 9} The following exchange occurred in the course of Heifner’s testimony:
MR. HEIFNER: * * * Ma’am, on the thing of the thermostat, she got the
cost of the thermostat, not of running the twenty-five feet of two different types of
wire, the modem to make a fossil fuel, dual fuel, where you have a heat pump and
a propane furnace running together because usually it’s an electric furnace. Well,
when you run a fuel, they cannot run together at the same time so you have to buy
a fossil fuel kit which is what it’s called. And it alone is over a hundred dollars
just for the module.
Free access — add to your briefcase to read the full text and ask questions with AI
[Cite as Kirn v. Heifner, 2014-Ohio-535.]
IN THE COURT OF APPEALS FOR GREENE COUNTY, OHIO
KATHRYN KIRN :
Plaintiff-Appellant : C.A. CASE NO. 2013 CA 44
v. : T.C. NO. 13CVI500
BRIAN HEIFNER : (Civil appeal from Municipal Court) Defendant-Appellee :
:
..........
OPINION
Rendered on the 14th day of February , 2014.
KATHRYN KIRN, 241 S. Dawson Avenue, Columbus, Ohio 43209 Plaintiff-Appellant
BRIAN HEIFNER, 4770 Old Rt. 35 East, Jamestown, Ohio 45335 Defendant-Appellee
DONOVAN, J.
{¶ 1} This matter is before the Court on the pro se Notice of Appeal of
Kathryn [Cite as Kirn v. Heifner, 2014-Ohio-535.] Kirn, filed August 14, 2013. Kirn appeals from the July 17, 2013 decision of the Xenia
Municipal Court in favor of Brian Heifner on Kirn’s Small Claims Complaint. We hereby
affirm the decision of the trial court.
{¶ 2} Kirn’s complaint provides that “B. Heifner installed propane / heat pump
furance (sic) 12/3/12. At 4864 OLS (sic) U.S. 35 E but heat pump didn’t work * * * See
attached small claim information sheet.” The information sheet provides that Kirn sought
$953.00 plus interest, and it provides: “B. Heifner installed propane heat pump furnace
12/3/12 at 4864 old U.S. 35 East but heat pump didn’t work. Brian returned several times
but was unable to find problem. Finally had to call Lowes HVAC. 2 men worked 3 hours
($370.) Fan stayed on continually so Lowes returned for 1 hour ($140). Heat pump went
out again. So Rheem installer came from Dayton. Found too small a wire used which
overheated and blew (2) time delay fuses. Replaced for $192.70. Heifner added $400 later
to bill for $100 thermostat. Bill paid thinking installation completed, but wasn’t.”
{¶ 3} A trial was held on July 16, 2013. Kirn testified that Heifner installed a
furnace and heat pump at her rental property, and that she paid him on December 3, 2012.
She stated that she “chose the heat pump because it takes the heat from the air, it’s less
expensive; and then after thirty degrees, there’s no more heat left in the air. So as a backup,
we discussed another oil or propane [furnace]. * * * we went to propane for this second
furnace. So it’s heat pump down to thirty degrees, then propane from there on down in cold
weather.” Kirn stated that her renters advised her in February that the “propane was on but
the heat pump, which should be on, was not. The day I was there, it was forty-three degrees
and the propane was on.” She stated that “Brian had come several times but couldn’t fix
it.” She testified that the “heat pump never did get installed properly.” Kirn stated that she 3
told her tenants to contact Heifner, and that they “said he’d been back several times, couldn’t
figure the problem.” Kirn stated that she phoned Heifner Heating and Cooling and “said I
wanted a different person to come out and look at the installation. She said, well, Brian did
this on his own, we are not backing it up.”
{¶ 4} Kirn stated that she contacted “Lowe’s brothers, Lowe’s HVAC,” and that
“two men worked three hours.” She stated that the men “changed from twenty-five degrees
on the heat pump back to what is called for in the manual at thirty degrees, because there’s
no heat in the air under thirty degrees.” Kirn stated that the temperature at the time “was
under thirty degrees so they couldn’t tell if the heat pump was going to work after they
checked everything.” Kirn stated that the pump “didn’t work when it warmed up,” and that
the men from Lowes came back and determined that the “blower was running full-time.
They corrected that. They checked the Freon. They checked it out as much as they could.”
According to Kirn, the heat pump “still wasn’t working. It had never been installed to
where it was working properly.”
{¶ 5} Kirn stated that she “called a third person named Patrick who installs
Rheems in Dayton. He came out and he found that the heat pump had a wire - - one of the
two wires was too small. And he used the word this bigger one is a thirty-five, the smaller
one’s only a thirty; it’s overheating, throwing the two breakers. And he said that’s been
your problem the whole time.”
{¶ 6} Kirn asserted that “the first tank of propane had a leaky valve and [the
renters] lost a lot of propane and the dealer supposedly compensated them. I think he
undercompensated.” She stated that the renters “sneaked out owing me January, February, 4
March, April’s rent. They couldn’t pay their bills.”
{¶ 7} Kirn submitted two bills from “Lowe’s HVAC,” one of which is dated March 7,
2013, in the amount of $140.00, and provides, “Checked refrigerant charge, adjusted charge and
tstat,” and indicates a charge of $70.00 for labor and $70.00 for a service call, and another which
indicates it was paid on March 5, 2013, in the amount of $370.00, and provides, “rewired
control wiring on heat pump and LP gas furnace. Set thermostat for dual fuel and heat pump,”
and indicates a charge of $300 for three hours of labor by two men, and a $70.00 service call
charge. Kirn also submitted “Dale’s Bill,” dated May, 2013, which contains multiple unrelated
charges but includes a highlighted charge of $80.00 for “heat pump re-wire-extra,” and Kirn
stated that it was from Dale Peckham “for installing the wire” for the heat pump. Kirn stated
that the system has worked since Dale Peckham installed the new wire. Finally, Kirn submitted
a receipt, dated April 12, 2013, from “Lowe’s Home Centers, Inc.,” in the amount of $112.70, “to
buy the new breakers and the wire.”
{¶ 8} Kirn asserted that “Lowe’s told me that * * * I was really overcharged for the
thermostat and kit * * *. So I got on the internet this week and first thing under the Honeywell,
they gave FocusPRO thermostats, no need for external kits, no need for wires, reduces the backup
heat needed.” Kirn stated that she “found one on line for a hundred and eighty five dollars plus
eleven to ship it. So it was two hundred. * * * .” The following exchange occurred:
MS. KIRN: And I had also asked - -said that he had overcharged on the
thermostat according to Lowe’s.
THE COURT: Well, I don’t have anything from Lowe’s that tells me that,
do I? 5
MS. KIRN. No. That was personal, yes.
THE COURT: And I’m not going to take anything off the internet.
MS. KIRN. Okay. All I’ve got is the cost of the Honeywell, three copies
of it. I don’t know if she wants these or not.
THE COURT: * * * That’s total of seven hundred and two dollars. * * *
What do you have that you don’t know if I want?
MS. KIRN: Lowe’s said I was terribly overcharged so I got what it - - the
thermostat, the Honeywell recommended thermostat.
THE COURT: Off the internet?
MS. KIRN: Off the internet.
THE COURT: I don’t want those.
{¶ 9} The following exchange occurred in the course of Heifner’s testimony:
MR. HEIFNER: * * * Ma’am, on the thing of the thermostat, she got the
cost of the thermostat, not of running the twenty-five feet of two different types of
wire, the modem to make a fossil fuel, dual fuel, where you have a heat pump and
a propane furnace running together because usually it’s an electric furnace. Well,
when you run a fuel, they cannot run together at the same time so you have to buy
a fossil fuel kit which is what it’s called. And it alone is over a hundred dollars
just for the module.
THE COURT: So you’re saying that the four hundred dollars that you
charged her was - -
MR. HEIFNER: For the installation - - 6
THE COURT: For the thermostat - -
MR. HEIFNER: - - of the thermostat, the thermostat, the module, and the
outdoor sensor.
{¶ 10} Heifner stated that when he “got the job done, there was a lot of gas, propane
usage. He called me * * * and told me the gas was using too much after three weeks - - after it
was done and working * * * .” The following exchange occurred:
MR. HEIFNER: And [the tenant] told me how much gas he was using.
And I said that’s not right, that’s too much. So I went over there, and I checked
bubbles on all the fittings. I couldn’t find any in the basement that I did because I
ran all new gas line, pipe, black pipe. So I proceeded on the way outside and
doing the propane company’s work. And I found out right at the shutoff valve on
the tank itself that there was bubbles; there was a leak, pretty good leak. So I told
him; we called them, they came out and replaced a new tank and gave him some
credit back. * * * I did that on my own. I could have charged her for that because
it wasn’t my fault, but I did not charge her. That was free.
Then I went back again and somehow the thermostat had gotten reset,
maybe power outage or whatever. It’s a programmable. So I had to go in there,
reprogram it and get it back to where it was going to fossil fuel, using the outdoor
sensor and all this stuff. * * * I reset it, I put it back to the setting and everything
went really - - was fine. I called him a couple days later, he said it’s running fine.
So she proceeded - - I sent her a bill after - - December 5, somewhere
around there, that’s when I was finished; and she paid it so it must have been - - I 7
don’t understand it. * * * So but she finally sent me the check and that’s the last I
heard of it until she called me on a Tuesday. I had the flu last winter bad, all
week long. * * * I called him on a Friday morning.
THE COURT: Him who?
MR. HEIFNER: Scott, who lives right next door. Because that’s who I
got to call to get in to have someone there so I have access to the thermostat and
everything so I can run the system and see what’s going on. So I called him
Friday morning and he said he came home that night before, Thursday, and she
had had Bobby Lowes there. She called me one time, Tuesday morning; and then
she called someone else. She didn’t give me a chance. And it says right there in
the letter that he called me and I told him as soon as I can, I will. And she went
with someone else and then all this stuff happened, it didn’t work right after that.
So that’s - -that’s all I’ve got.
{¶ 11} Heifner submitted a handwritten statement, dated, July 15, 2013 that appears to
be signed by Scott Overturf, Kirn’s tenant. It provides that Heifner installed a new furnace and
that, “Yes there was bugs in the system, I called Brian whenever there was a problem with
furnace he did come to house to fix problem. After about the fourth time the system was
working fine. Then one day Kathern (sic) and I was outside of house and noticed that the heat
pump and propane was on same time.” The statement provides that Overturf called Heifner who
“came out and noticed on Honeywell thermostat that there was a system reset happen it started
working fine, then furnace messed up again I called Brian he said he had the flu and would be
there as soon he felt better and in the meantime Kathern (sic) had Lowe’s from Cedarville come 8
out to look at system.” Overturf’s statement provides that subsequently “the system was worse
than before, then called Brian again he came out noticed the system was set wrong from Lowe’s
it was set for warmer climates. Brian Kathern (sic) and I was there and Brian told Kathern (sic)
that the electric panel need updated so he was going to run a subpanel to run furnace. Also Brian
lives next door approx. 1/8 mile away.”
{¶ 12} At the conclusion of Heifner’s testimony, Kirn referred to a letter from her
addressed to Heifner, dated March 22, 2013, in which she stated that she requested that he pay
her Lowe’s bills. Kirn stated, “You had the propane set at twenty-five. This is five degrees
below the point that a heat pump can extract heat from air. So it comes on as electric and it’s
very inefficient pulling it up. And Lowe’s told me this. They set all the settings back at factory
settings because this is not approved setting that he put things on. They never told me that he
came back again and worked on anything.” The letter was not admitted as an exhibit.
{¶ 13} The following exchange occurred:
THE COURT: Any way, go ahead and finish - - wrap it up.
MS. KIRN: * * * it was not working and there was a fault in a line that
caused overheating and threw breakers.
THE COURT: But Lowe’s didn’t end up fixing it, did they?
MS. KIRN: * * * they thought they had.
THE COURT: They tried. So I’m not sure why you expect Mr. Heifner to
pay for someone to come out and not fix your furnace.
MS. KIRN: They thought they had. They made corrections. They came
out twice. And it’s this third man who finally found the problem. But these two 9
men worked three hours. * * *
***
MS. KIRN: I called Lowe’s because they said Brian couldn’t fix it. And
he was standing there, Scott was standing there saying look at this, the propane,
you know, is on. And he said it’s costing me a fortune, I can’t afford it. And
they knew I called Lowe’s and they were there when Lowe’s came.
{¶ 14} The trial court’s decision merely provides that the court ruled in favor of
Heifner, and we note that Kirn did not request in writing that the court issue written findings of
fact and conclusions of law, pursuant to Civ. R. 52. We also note that the rules of evidence do
not apply to proceedings in the small claims division of a municipal court. Evid.R. 101(C)(8).
{¶ 15} Kirn’s brief does not comply with App.R. 16(A). She has failed to set forth
specific assignments of error. Her brief provides in part that she “requests that the four service
call/repair bills be paid by defendant, as well as court costs, and that he install the proper 2 stage /
1 stage cooling thermostat with proper outdoor sensor, if a sensor is needed with the particular
dual heat stage / single cooling stage thermostat being installed.” Attached to Kirn’s brief are
copies of the bills she submitted to the trial court, as well as product information regarding a
Wireless FocusPRO Thermostat, model number TH811OU1003.
{¶ 16} We infer from Kirn’s brief that she is asserting as an assignment of error that
the judgment of the trial court is against the manifest weight of the evidence.
{¶ 17} As this Court recently noted:
The standard set forth for manifest-weight-of-the-evidence appellate
review in State v. Thompkins, 78 Ohio St.3d 380, 678 N.E.2d 541 (1997), applies 10
also in civil cases. Eastley v. Volkman, 132 Ohio St.3d 328, 2012-Ohio-2179, 972
N.E.2d 517, ¶ 17. In applying this standard, the appellate court, reviewing the
entire record, weighs the evidence and all reasonable inferences, considers the
credibility of witnesses and determines whether in resolving conflicts in the
evidence, the factfinder clearly lost its way and created such a manifest
miscarriage of justice that the judgment must be reversed and a new trial ordered.
The discretionary power to grant a new trial should be exercised only in the
exceptional case in which the evidence weighs heavily against the judgment. State
v. Martin, 20 Ohio App.3d 172, 175, 485 N.E.2d 717 (1st Dist.1983), cited
approvingly in Thompkins at 387. Folck v. Redman, 2d Dist. Clark No.
2013-CA-35, 2013-Ohio-3646, ¶ 8.
{¶ 18} Regarding the two “Lowe’s HVAC” bills, in the total amount of $510.00, as the
trial court noted, it is clear that the heat pump was not successfully repaired by the “Lowe’s
HVAC” repairmen. Kirn testified that the repairmen “checked it out as much as they could,”
and that they “thought” they had fixed it, but it “still wasn’t working.” Heifner stated that after
the system was working, and a problem arose when he was ill, Kirn “went with someone else and
then all this stuff happened, it didn’t work right after that.” Scott Overturf’s letter provides that
“the system was worse than before” after the “Lowe’s HVAC” repairmen were there. We
conclude that the trial court’s decision in favor of Heifner regarding the “Lowe’s HVAC” bills is
not against the manifest weight of the evidence.
{¶ 19} Regarding the $80.00 charge on “Dale’s Bill,” as well as the receipt from Lowe’s
Home Centers, Inc., in the amount of $112.70, both of which Kirn submitted as evidence of the 11
cost of replacing the wire that Kirn alleged was wrongly installed by Heifner, we note that the
$370.00 “Lowe’s HVAC” bill provides in part, “Rewired control wiring on heat pump and LP
Gas Furnace.” As noted above, according to Heifner and Overturf, the system did not work
properly after two visits from “Lowe’s HVAC.” Kirn contacted “Patrick,” who allegedly found
the faulty wire, and Dale Peckham replaced the wire, after the “Lowe’s HVAC” repairmen had
rewired the heat pump. It is not clear which wire Peckham replaced, and given the intervening
actions of “Lowe’s HVAC,” we cannot conclude that the trial court’s decision in favor of Heifner
regarding the costs of replacing the wire is against the manifest weight of the evidence.
{¶ 20} Finally, regarding the cost of the thermostat, we note that Heifner and Kirn
provided conflicting testimony. Kirn asserted that “Lowe’s” advised her that Heifner overcharged
her, and that she found an adequate thermostat on the internet for two hundred dollars. We note
that the trial court did not admit her exhibit regarding the thermostat, and the promotional
information attached to her brief is not part of the record on appeal. App.R. 9. Heifner asserted
that his charge of $400.00 did not just cover the cost of the thermostat but also its installation,
including the cost of “running the twenty-five feet of two different types of wire,” a modem that
costs over $100.00, an outdoor sensor, and a fossil fuel kit. The trial court was free to credit
Heifner’s testimony over Kirn’s, and we cannot conclude that the court lost its way in resolving
the conflicting testimony regarding the cost of the thermostat.
{¶ 21} Having thoroughly reviewed the entire record, we conclude that the decision of
the trial court in favor of Heifner is not against the manifest weight of the evidence. The
judgment of the trial court is affirmed.
.......... [Cite as Kirn v. Heifner, 2014-Ohio-535.] HALL, J. and WELBAUM, J., concur.
Copies mailed to:
Kathryn Kirn Brian Heifner Hon. Catherine M. Barber, Acting Judge