Kirkpatrick v. City of Binghamton

256 A.D. 19, 9 N.Y.S.2d 713, 1939 N.Y. App. Div. LEXIS 4634

This text of 256 A.D. 19 (Kirkpatrick v. City of Binghamton) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirkpatrick v. City of Binghamton, 256 A.D. 19, 9 N.Y.S.2d 713, 1939 N.Y. App. Div. LEXIS 4634 (N.Y. Ct. App. 1939).

Opinion

Hill, P. J.

Cross-appeals have been taken from a judgment entered in Broome county clerk’s office on May 6, 1938, in favor of plaintiffs, who have also appealed from an order entered in the same clerk’s office on August 1, 1938, which struck out each item of their costs and disbursements except those for referee’s and stenographer’s fees.

The plaintiffs, contractors and builders, in January, 1923, agreed in writing with the defendant in consideration of $320,085, to furnish the necessary labor and materials to construct The Daniel S. Dickinson School.” Work progressed until the 11th day of September, 1923, when a large part of said building collapsed and fell in ruins.” Immediately following this catastrophe there were negotiations and correspondence between the parties. The commissioner of public works of the city, by letter, directed plaintiffs to discontinue work on the building, “ except such work as you may do by my request in cleaning away the debris and work of that character.” It contained the following paragraph: Your compliance with this letter will not be considered as an abandonment of the work on your part. Until the cause of the collapse of the building is definitely ascertained I do not think it is wise [21]*21or prudent to continue with the construction.” Another communication from the same official stated, “ I would request that you clear away the debris so as to make such inspection possible. You have an organization on the ground and are in a better position to do this than any other party interested.” This letter directed that the work be done in a manner to give opportunity for inspection and study as to the cause of the collapse. The plaintiffs replied, We will endeavor to clear away the debris in The Daniel S. Dickinson School building in such a manner as to make a more thorough inspection possible, it being understood, however, that this work by us will be done without any prejudice whatsoever to any rights or claims which we may have. And in the event that it is ultimately found that we are not to blame for the collapse, we shall, of course, expect to be compensated for every expense to which we have been or shall be put by reason thereof.” Following this, a portion of the debris was cleared away. Numerous photographs were taken and full opportunity given for inspection. Certain items of the expenses were submitted by plaintiffs to the department of public works, approved by the commissioner and paid by a draft of the city treasurer.

On April 15, 1924, a second contract in connection with continuing the construction was made between the plaintiffs and the defendant. The original architects had employed a consultant who had devised changes. The portion of the contract concerning compensation and work to be done is as follows:

“ 4. The party of the first part shall pay to the parties of the second part, as their entire compensation for such additional work and materials as are required in and by the said supplemental plans and for carrying the twelve inch wall indicated at D on said supplemental plans up through * * * to the underside of the roof, and for the premium on the additional bond required by the said party of the first part which was specified in the estimate bearing date March 17, 1924, which was furnished to the said party of the first part by the said parties of the second part, the sum of Twenty-eight thousand three hundred and fifteen dollars ($28,315.00), the times and amounts of such payments to be determined in all respects by, and pursuant to, the general provisions applicable to the payments to the Contractors contained in said contract of January 10, 1923.”

The estimate of March 17, 1924, mentioned in the above-quoted section of the contract, was in form a letter to the board of contract and supply and is attached to the contract. In it is Usted the work which was to be performed thereunder: Walls #1, Floors of collapsed area #2, Piers at A #3, Main entrance walls, West walls at [22]*22D.” For these five items the total was $26,795. In arriving at the amount named in the contract, $510 was added for the additional bond. The letter contained a further paragraph: “ If the 12" wall at D is carried up through the second and third stories to underside of roof, add to the above One thousand ten dollars ($1010).” On the day following the writing of the above letter, which was some weeks prior to the making of the contract, plaintiffs wrote to the bureau of contract and supply in part as follows:

“ Below is a list of miscellaneous items not covered in the original plans and specifications nor covered by quotations of $26,795 for specific items recommended in Report of A. F. Gilbert, viz:
“ Beam support for low ceilings of corridors in place of suspension rods which incumber duct spaces.
“ Beams required over opening for air intake shaft in basement.
“ Support for walls over wardrobes in class rooms.
“ Columns necessary to support comer of corridor floorslab at stairs.
“ Improvement of exterior wall bond and construction of brick walls which prevented a greater collapse (see previous quotation of $2,160 dated February 22, 1923).
“ Expense due to collapse including removal of rubbish.
“ The above items will probably not exceed a total of $13,600. This total does not cover any future changes in construction which was done under the original contract control. It is, however, a probable maximum for the above items which are not included in the specific quotation of $26,795 presented to the Board of Contract and Supply on March 17, 1924.”

The referee in his report states: “Upon the evidence before me, I find that the cause of the collapse was the insufficiency of the walls as designed to bear the load, together with the cutting of chases in the walls and piers by the contractor who was in privity with the City, but not with the plaintiffs.” The city, after the collapse, obtained the services of a consulting architect and engineer. His reports are voluminous and largely given to detail, but I quote portions which are in the nature of conclusions supported by the detailed facts recited by him:

“ Upon the failure of the pier in the basement the girder in question over the main entrance sagged to the south, dragging •with it the floors and roof, causing the conditions as found.
“ In addition to the foregoing conditions of faulty design of this structure the plans show the wall of the auditorium and the westerly wall of the second story corridor * * * designed to be supported on some form of steel cantilever constmction, but in the structural steel plans and at the building this wall is shown as sup[23]*23ported from the corridor floor. The structural steel drawings show concrete haunches under this wall, with reinforcing steel; in the remaining portion of the building this construction has been omitted, and it is assumed this condition also existed in the collapsed portion as there is no evidence of reinforcing bars as shown on plans as continuous.
“ The added loading of this wall and the eccentric influence of this design assisted in the failure of the structure.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
256 A.D. 19, 9 N.Y.S.2d 713, 1939 N.Y. App. Div. LEXIS 4634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirkpatrick-v-city-of-binghamton-nyappdiv-1939.