Kirkner Elec., Inc. v. Rydarowicz

2020 Ohio 3362
CourtOhio Court of Appeals
DecidedJune 12, 2020
Docket19 CO 0041
StatusPublished

This text of 2020 Ohio 3362 (Kirkner Elec., Inc. v. Rydarowicz) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirkner Elec., Inc. v. Rydarowicz, 2020 Ohio 3362 (Ohio Ct. App. 2020).

Opinion

[Cite as Kirkner Elec., Inc. v. Rydarowicz, 2020-Ohio-3362.]

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT COLUMBIANA COUNTY

KIRKNER ELECTRIC INC.,

Plaintiff-Appellee,

v.

JOHN RYDAROWICZ, JENNIFER RYDAROWICZ

Defendants-Appellants.

OPINION AND JUDGMENT ENTRY Case No. 19 CO 0041

Civil Appeal from the Columbiana County Municipal Court of Columbiana County, Ohio Case No. 2018 CV F 000420

BEFORE: Gene Donofrio, Cheryl L. Waite, Carol Ann Robb, Judges.

JUDGMENT: Affirmed

Atty. Fredric Kannensohn, Atty. Samuel Jordan, 4531 Belmont Avenue, Suite 2C, Youngstown, Ohio 44505, for Plaintiff-Appellee and

Atty. Mark Lavelle, 940 Windham Court, Suite 7, Youngstown, Ohio 44512, for Defendants-Appellants. –2–

Dated: June 12, 2020

Donofrio, J.

{¶1} Defendants-appellants, John and Jennifer Rydarowicz, appeal from a Columbiana County Municipal Court judgment in favor of plaintiff-appellee, Kirkner Electric, Inc., on appellee’s claim for unjust enrichment, following a bench trial. {¶2} Appellants began construction of their new home in 2016. Appellants hired Digger Quality Homes (Digger) to frame the house. On Digger’s recommendation, appellants contacted appellee to handle the electrical work. {¶3} In March 2016, appellants met with Brant Griffith. Griffith has worked as an electrician for appellee for over 18 years and was in charge of this project. The parties agreed that appellee would do the electrical work for the new home. But they never entered into a written contract. {¶4} According to Griffith, appellant John Rydarowicz initially told him the house was going to be approximately 2,000 square feet. Griffith estimated the project at $5 per square foot and gave appellants an estimate of $10,000 to complete the electrical work. When Griffith later went to the site of the new house, after it had been framed, he saw that the house was actually closer to 3,000 square feet. Griffith then told appellants that the project was going to cost more than the $10,000 he initially quoted them. {¶5} According to John, when he and his wife met with Griffith, Griffith told him the price would be $10,000 “give or take.” He stated that Griffith never told him a price per square foot. John also stated he gave every contractor who worked on his house a set of blueprints, which listed the square footage of the house as 2,912 square feet. {¶6} In October 2016, appellee sent appellants the first bill in the amount of $7,452.42. Appellants paid the first bill in full. At that point, the project was not yet complete and appellants knew they still owed more for the electrical work. {¶7} In March 2017, the project was complete. Appellee sent appellants the second bill in the amount of $9,633.09. According to John, they were surprised at the amount appellee said they owed. John stated that he contacted Griffith, who told him they would work something out. John further stated that he contacted appellee’s owner

Case No. 19 CO 0041 –3–

who told him to pay what he thought was fair. Appellants made payments of $2,500 and $3,000 on the second bill. {¶8} Appellee then filed a complaint against appellants asserting a claim for unjust enrichment and seeking judgment in the amount of $4,133.09, the balance remaining on the second bill, plus interest. {¶9} The matter proceeded to a bench trial where the court heard testimony from Griffith, John, and Jenna. The court found that appellee competently performed the electrical work and billed appellants in accordance with industry standards. The court determined it would be unjust to permit appellant to benefit from the work without payment. Therefore, the court awarded judgment in favor of appellee in the amount of $4,133.09 with interest. {¶10} Appellants filed a timely notice of appeal on October 15, 2019. They now raise a single assignment of error for this court’s review. {¶11} Appellants’ assignment of error states:

THE TRIAL COURT ERRED IN FINDING THE MANIFEST WEIGHT OF PLAINTIFF-APPELLEES [sic.] EVIDENCE PROVED ALL THE ELEMENTS OF UNJUST ENRICHMENT.

{¶12} Appellants agree that appellee conferred a benefit on them and that they knew of the benefit. But they argue that the trial court’s finding that it would be unjust for them not to make an additional $4,133.09 payment to appellee was against the manifest weight of the evidence. Appellants contend the court accepted Griffith’s testimony as truthful and disregarded John’s testimony. They assert the court accepted John’s testimony that the work was completed as expected but that it disregarded John’s testimony that appellee’s owner told him to pay what was fair. Moreover, appellants argue the trial court rewarded appellee for “sloppy business practices” by awarding it a 70- percent increase beyond the initial quote when there was no written contract for the job. {¶13} When reviewing civil appeals from bench trials, an appellate court applies a manifest weight standard of review. Revilo Tyluka, L.L.C. v. Simon Roofing & Sheet Metal Corp., 193 Ohio App.3d 535, 2011-Ohio-1922, 952 N.E.2d 1181 (8th Dist.), citing App.R. 12(C), Seasons Coal v. Cleveland, 10 Ohio St.3d 77, 461 N.E.2d 1273 (1984).

Case No. 19 CO 0041 –4–

Judgments supported by some competent, credible evidence going to all the material elements of the case must not be reversed as being against the manifest weight of the evidence. C.E. Morris Co. v. Foley Constr. Co., 54 Ohio St.2d 279, 376 N.E.2d 578, syllabus (1978). See, also, Gerijo, Inc. v. Fairfield, 70 Ohio St.3d 223, 226, 638 N.E.2d 533 (1994). Reviewing courts must oblige every reasonable presumption in favor of the lower court's judgment and finding of facts. Gerijo, 70 Ohio St.3d at 226 (citing Seasons Coal Co., supra). In the event the evidence is susceptible to more than one interpretation, we must construe it consistently with the lower court's judgment. Id. In addition, the weight to be given the evidence and the credibility of the witnesses are primarily for the trier of the facts. Kalain v. Smith, 25 Ohio St.3d 157, 162, 495 N.E.2d 572 (1986). {¶14} We must examine the evidence presented at trial in examining whether the trial court’s judgment was against the manifest weight of the evidence. {¶15} Griffith was appellee’s sole witness. Griffith testified that he first met with appellants in March 2016. (Tr. 9). He stated that there was no general contractor on the job. (Tr. 10). Instead, he simply met with appellants and they told him what they wanted in their new home. (Tr. 10). Griffith guesstimated that he met with appellants on three occasions before he started work at their new house. (Tr. 11). Griffith testified that he never saw a set of plans for the house during these meetings. (Tr. 11). {¶16} Griffith testified that the parties never entered into a written contract. (Tr. 12). He stated that appellants told him the house was going to be 2,000 square feet. (Tr. 12). Believing the house would be approximately 2,000 square feet, Griffith estimated a cost of $10,000 to $12,000 based on $5 per square foot. (Tr. 12, 29). {¶17} Griffith stated that he realized the house was more than 2,000 square feet when he went to the house to start the “rough in.” (Tr. 14). This occurred in June 2016. (Tr. 15). At that point, Griffith stated he told appellants the project was going to cost more than he had originally quoted but he did not tell them how much more at that time. (Tr. 15, 30). He stated that appellants did not voice any complaints to him at that time. (Tr. 17).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Revilo Tyluka, L.L.C. v. Simon Roofing & Sheet Metal Corp.
2011 Ohio 1922 (Ohio Court of Appeals, 2011)
State v. Nichols
619 N.E.2d 80 (Ohio Court of Appeals, 1993)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Hambleton v. R.G. Barry Corp.
465 N.E.2d 1298 (Ohio Supreme Court, 1984)
Kalain v. Smith
495 N.E.2d 572 (Ohio Supreme Court, 1986)
Gerijo, Inc. v. City of Fairfield
70 Ohio St. 3d 223 (Ohio Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
2020 Ohio 3362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirkner-elec-inc-v-rydarowicz-ohioctapp-2020.