Kirk Williams Co. v. Six Industries, Inc.

463 N.E.2d 1266, 11 Ohio App. 3d 152, 11 Ohio B. 233, 1983 Ohio App. LEXIS 11262
CourtOhio Court of Appeals
DecidedSeptember 8, 1983
Docket1774
StatusPublished
Cited by10 cases

This text of 463 N.E.2d 1266 (Kirk Williams Co. v. Six Industries, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirk Williams Co. v. Six Industries, Inc., 463 N.E.2d 1266, 11 Ohio App. 3d 152, 11 Ohio B. 233, 1983 Ohio App. LEXIS 11262 (Ohio Ct. App. 1983).

Opinion

Brogan, P.J.

Appellee, Six Industries, Inc., was the general contractor for the construction of the Credit Life Insurance Building in Springfield, Ohio. As general contractor, appellee entered into a subcontract with the appellant, Kirk Williams Company (“Kirk Williams”) relating to the heating, ventilating and air-conditioning portion of the project. This subcontract was in excess of $1,100,000.

As is relatively standard on projects of this magnitude, the contractual undertaking between the parties was changed by formal written change orders on several occasions. These changes represented both additions as well as deletions from the subcontract with Kirk Williams. Not all of these changes, however, were signed or agreed to by Kirk Williams.

The project admittedly was not completed on the original scheduled completion date. The reasons for this delay, whether appellant had advance knowledge of such delay and the propriety of damages for any delay, were not before the trial court and are not at issue here. It is relevant, however, that the appellant did claim substantial delay damages against Six Industries.

As the project neared completion, Six Industries submitted two last change orders to Kirk Williams for approval. The last of these change orders contained a statement that:

“This change order completes and settles all disputed items between Kirk Williams Company, Inc. and Six Industries, Inc. on this project.”

Paul Wright, manager of the appellant’s industrial division, called Thomas Cooke, Vice President of Six Industries, and informed him that he could not sign and complete the change order because Kirk Williams had a delay claim in process and it would be forthcoming.

Subsequent to these discussions, Six Industries, under date of November 10, 1981, issued a check payable to Kirk Williams in the amount of $14,850.04. On the reverse side of this check, the following language appeared:

“Endorsement and/or negotiation of this check constitutes a full and complete release of Six Industries, Inc. and acknowledges full payment of all monies due or to become due for any and all work done or materials furnished by the Payee in connection with the Credit Life Insurance project in Springfield, Ohio.”

In addition, the top half or voucher of *153 this check contained the following language:

“Payment in full — $164 The Credit Life Insurance Company, Springfield, Ohio — per restrictive endorsements.”

The above-referenced check was received by appellant in the normal course of its business and the check was deposited by its bookkeeper, who believed the restrictive endorsement had no legal significance.1 On or about November 20, after this check had cleared the bank, appellant attempted to negate the clear restriction on the check by issuing its own check payable to Six Industries for $14,850.04. The check of Kirk Williams was returned by appellee’s counsel indicating that the check previously issued by Six Industries and negotiated by Kirk Williams had, in fact, settled and resolved all of the differences between the parties.

Appellant then filed this action in the Court of Common Pleas of Clark County seeking delay damages and also seeking a declaratory judgment that the restrictive endorsement on appellee’s check was of no consequence or effect. Appellee answered the complaint raising the defense of accord and satisfaction. By agreement of the parties the declaratory judgment was tried to the court without a jury and the.trial court found that all elements of accord and satisfaction were present and judgment was awarded to ap-pellee. The trial court found that under well-settled case law in Ohio the cashing of the check under the circumstances of this case amounted to accord and satisfaction. The court found that Kirk Williams could not avoid the consequences by placing an employee (who appellant claims had no authority to settle such disputes) in the position of cashing all checks tendered to the appellant through such employee irrespective of the language contained on such checks. From the judgment, appellant timely appeals asserting two assignments of error:

“I. The trial court erred when it failed to grant plaintiff’s requested declaratory judgment. Such declaratory judgment should have held that the deposit of defendant’s check by plaintiff’s bookkeeping clerk does not constitute an accord and satisfaction, a compromise, a settlement or a release of plaintiff’s claims against defendant.
“II. The trial court erred when it concluded that a bookkeeping employee of a corporation who is not authorized to settle a disputed claim subjects' the corporation to an accord and satisfaction by depositing a check bearing a restrictive endorsement, under circumstances where persons in the corporation with the authority to settle and resolve disputes were not aware of the receipt of the check until after its deposit, and the corporation promptly returns the amount of the check and rejects any settlement.”

An accord and satisfaction is a method of discharging a contract or settling a-cause of action arising either from a contract or tort, by substituting for such contract or cause of action an agreement for the satisfaction thereof an execution of such substituted agreement. Chillicothe Hospital v. Garrett (1971), 26 Ohio App. 2d 277 [55 O.O.2d 425]. Compromise and settlement is closely related to accord and satisfaction; however, performance is necessary to a complete accord and satisfaction, while it is not essential to a valid compromise. 1 American Jurisprudence 2d (1962) 303, Accord and Satisfaction, Section 2.

“An accord is a contract under which an obligee promises to accept a stated performance in satisfaction of the obligor’s existing duty. Performance of the accord discharges the original duty.” Restatement of the Law, .Contracts 2d (1981) 381-382, Section 281(1).

An accord and satisfaction is the result of an agreement between the parties, and this agreement, like all others, must be consummated by a meeting of the minds of the parties. Warner Elevator Mfg. Co. v. Higbee (1935), 53 Ohio App. 546 [7 O.O. 355]. An effective assent can *154 not be given and a meeting of the minds cannot be achieved unless the parties have knowledge of the facts which are material to the agreement. But an agreement intended as an accord and satisfaction of certain claims may be valid as to those claims known to both parties at the time of the execution, notwithstanding that an additional claim was discovered after an accord had been made and executed by satisfaction. Brient v. Cupid Ice Cream Co. (1933), 47 Ohio App. 283.

As in the case of the other contracts, when a contract of accord and satisfaction is entered into by an alleged agent on behalf of his principal, in order to bind the principal the agent must have been duly authorized thereto, or his act must have been ratified by the principal. 1 American Jurisprudence 2d, supra, Section 8, at 307-308. See, also, Aerosonic Instrument Corp. v. NuTone, Inc. (C.P. 1958), 80 Ohio Law Abs. 289.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melnyk v. Ohio Dept. of Medicaid
2019 Ohio 5134 (Ohio Court of Appeals, 2019)
Huntington Natl. Bank v. Rizzo
2019 Ohio 3994 (Ohio Court of Appeals, 2019)
Adkinson v. Alex Bell Dental-Daniel Cobb, DDS, L.L.C.
2019 Ohio 2127 (Ohio Court of Appeals, 2019)
Smith v. E.S. Wagner Co.
2016 Ohio 8096 (Ohio Court of Appeals, 2016)
Maine v. Leonard Truck & Trailer, Inc.
2014 Ohio 5722 (Ohio Court of Appeals, 2014)
Renner v. Procter & Gamble Co.
561 N.E.2d 959 (Ohio Court of Appeals, 1988)
Thonen v. McNeil-Akron, Inc.
661 F. Supp. 1252 (N.D. Ohio, 1986)
Inger Interiors v. Peralta
506 N.E.2d 1199 (Ohio Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
463 N.E.2d 1266, 11 Ohio App. 3d 152, 11 Ohio B. 233, 1983 Ohio App. LEXIS 11262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirk-williams-co-v-six-industries-inc-ohioctapp-1983.