Kinser Construction Co. v. State

145 A.D. 41, 129 N.Y.S. 567, 1911 N.Y. App. Div. LEXIS 1734
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 3, 1911
StatusPublished
Cited by5 cases

This text of 145 A.D. 41 (Kinser Construction Co. v. State) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinser Construction Co. v. State, 145 A.D. 41, 129 N.Y.S. 567, 1911 N.Y. App. Div. LEXIS 1734 (N.Y. Ct. App. 1911).

Opinion

Betts,-J.:

November 23, 19Ó6, the above-named construction company and the defendant made a written contract, known as contract No. 27, for the improvement of the Champlain canal between Dunham’s Basin road and the Hudson river at Fort Edward in accordance with plans and specifications which formed a part of the contract; The Kinser Construction Company agreed' to build thr¿e and seventy-six one-hundredths miles of the Champlain canal, and was to be paid therefor by the State as the work progressed in installments according to the amount of work done and materials furnished, and a certain percentage was to be retained until the completion of the entire contract.

The construction. Company began the work under its contract, and completed quite a portion thereof, and payments were made thereunder by the State; Included in the work agreed .to be done was the erection of a lock No. 7, concerning the erection or non-erection of which there was trouble later Various alteration orders were made -under the provisions of the contract, and the work was done or partly done under such orders by the construction company, the parties thus giving practical construction to that part of the'contract. In November occurred a cave-in or slide of quite a large portion of the bank -of the canal at lock No. 7, whereupon the slope at the location of lock No. 7 was changed from one on one as it was to one on three. On December 15, 1908, while the construction [43]*43company was excavating for said lock No. 7, another and an immense slide occurred, which let down -into' the excavation material approximating from 500 to 600 feet long, and from 90 to 100 feet wide, which ran very nearly to the middle of the old Champlain canal,- which was eastward of the proposed new canal. It was then found that the material at this lock No. 7 was a slippery, greasy clay, and extended a depth of 40 feet or more below the excavation, whereupon the State on December 18, 1908, halted the construction south of station 1217 by the following letter:

“Albany, December 18, 1908.
“Kinser Construction Co.,
“Fort Edward, N. Y.:
. “ Gentlemen. — Owing to the fact that we have under consideration the matter of changing location of lock 7, which may be thrown either to the north or south, which might affect the plans of all work south of station 1217, I deem it for the best interest of the State, and hereby direct you to discontinue all work south of station 1217 until such time as we have new plans perfected.
“Yours very truly,
“(Signed) W. R. HILL,
Special Deputy State Engineer

The stations included' in. this contract ran from a little past station 1041 to station 1245, and the discontinuance of the work directed was from station 1217 south, which would take in about from station 12l7«to station 1245, a distance a little over one-half a mile. No interference was made by the State with the prosecution of the work north of station 1217, some of which was uncompleted. The construction company stopped work at about the date of this letter, or on or about December 24, 1908, as was claimed in a subsequent letter by the construction company. On May 21, 1909, the construction company .-wrote remonstrating against the long delay and announcing that they were suffering damages by not being permitted to proceed. On or about June 12, 1909, the State officials issued alteration or change orders, known as change orders No. 7 and No. 6, making substantial changes in the contract originally made and discontinuing or eliminating the construction of lock ‘No. 7, [44]*44originally contracted for, as that was to be constructed entirely outside of the part of the canal covered by the construction company’s contract. 'This was followed by the letter of June 24, 1909, which is as follows:

“Albany, N. June 24, 1909.
“Kinser Construction Co.,
“Fort Edward, N. Y.:
• “Gentlemen. — On December 24, 1908, you were ordered by former Special Deputy State Engineer Wm. R. Hill to discontinue all work on your contract No. 27,. south of sta. 1217, until such time as new plans might he perfected. The order of December 24 is hereby rescinded.
“Very truly yours,
“(Signed) WM. B. LANDRETH,
Special Deputy State Engineer.”

This letter rescinded the previous stop order. Upon- receipt of this letter and on or about July 1, 1909, the construction company notified the Superintendent of Public Works by letter that it declined to comply with the said order and would cease all work under said contract and bold the State of New York hable for all damages occasioned by the action of the State and for breaches of said contract. . The. letter is as follows:

July 1st, 1909.
“ Hon. Frederick 0. Stevens,
Superintendent of Public Works, .
“Albany, N. Y.: .
“ Dear Sir, — We are in receipt of a letter. from'Mr. Wiiliam B. Landretb, Special Deputy State Engineer, dated June 24th, 1909, making certain fundamental changes in the plan covering the work embraced in our contract No. 27, and also eliminating therefrom and taking from us large portions thereof.
“In answer thereto we have forwarded tó him a letter of which the inclosed is a copy.
“We hereby notify you that we decline to comply with said' order, and as we have been verbally informed by those in authority that the same will be insisted upon, we hereby notify you that we elect to treat the said order and insistence thereon as in violation of the terms of said contract and as a breach [45]*45thereof. We shall accordingly cease all work under said contract, and shall hold the State of. New York and its officers liable for all damages occasioned by the said action on the part of said State, and the breaches of said contract above referred to, as well as all other breaches in connection therewith. We are,
“ Yours very respectfully,
“THE KINSER CONSTRUCTION-COMPANY,
“By T. W. Kinser, President.”

Thereafter this claim, was filed and tried in the Court of Claims, the construction company, claiming damages of $370,525.41 for various items alleged in its claim. A trial was had and resulted in a judgment against the State for $70,679.25, with interest on a portion thereof, amounting all together to $77,425.46, from which determination this construction company appeals on the ground that it is insufficient.

It appears from an examination of the evidence here that after the second and large cave-in, where this lock No. 7 was to be constructed;, the State made an examination of the soil there and concluded that it was neither prudent nor safe to •attempt to erect a lock in that location. The soil was a slippery, greasy clay there from forty to seventy feet down in the ground. It was decided by the State that it was not possible to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of New York v. Local 333, Marine Division, International Longshoremen's Ass'n
79 A.D.2d 410 (Appellate Division of the Supreme Court of New York, 1981)
City of New York v. Local 333
106 Misc. 2d 888 (New York Supreme Court, 1980)
Bissell v. L. W. Edison Co.
156 N.W.2d 623 (Michigan Court of Appeals, 1967)
Matter of Kramer Uchitelle, Inc.
43 N.E.2d 493 (New York Court of Appeals, 1942)
Sokoloff v. National City Bank
120 Misc. 252 (New York Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
145 A.D. 41, 129 N.Y.S. 567, 1911 N.Y. App. Div. LEXIS 1734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinser-construction-co-v-state-nyappdiv-1911.