Kinney v. Williams

1917 OK 466, 168 P. 196, 66 Okla. 167, 1917 Okla. LEXIS 165
CourtSupreme Court of Oklahoma
DecidedOctober 9, 1917
Docket7964
StatusPublished
Cited by13 cases

This text of 1917 OK 466 (Kinney v. Williams) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinney v. Williams, 1917 OK 466, 168 P. 196, 66 Okla. 167, 1917 Okla. LEXIS 165 (Okla. 1917).

Opinion

Opinion by

GALBRAITH, C.

This was an action for damages alleged to have accrued by reason of the breach of warranty in the sale of two oil tanks. The plaintiff in error was the vendor and the defendant, and the defendant in error was the vendee and plaintiff in the trial court. There was a trial to the court and a jury and a verdict returned in favor of the plaintiff in the sum of $230. Upon the overruling of the motion for a new trial judgment was rendered for the amount of the verdict and for the costs. To review which this appeal has been per-feeted. The facts, briefly stated, are as followsi:

Kinney, the plaintiff in error, was a sheet metal worker, living at McAlester, Pitts-burg county. In December, 1913, Williams, who desired to go into the oil distributing business at Lehigh, in Coal county, entered into a contract with Kinney to build him two metal tanks, of the capacity of 65 barrels each; these when completed were to be conveyed to Lehigh and erected for use there. The contract price of the tanks was $130. They were completed, paid for, and accepted by the purchaser, but before accepting the tanks the purchaser received from the vendor a written guarantee, reading as follows:

“This certifies that P. W. Kinney has guaranteed two oil tanks to G. W. Williams that was made by P. W. Kinney to be in good service and condition, and furthermore guarantees the tanks not to leak, and if so will fix them without extra charge to the owner, G. W. Williams.”

It was charged in the petition, and supported by the evidence, that the tanks, shortly after they were erected and placed in use, developed leaks from which oil was wasted, and one of them, after the vendor had been notified and a helper had been sent to stop the leaks, broke open and oil ran down to the ground in a large stream, and 1,000 or 1,200 gallons were lost. Again it is contended on behalf of the plaintiff that owing to the defective construction of ■the top of the tanks water entered the tanks and mingled with the oil, and rendered much of it unsalable, and he was forced to throw it away, and that because of the water being in the oil it became un-merchantable, and he lost his trade, and his business was injured and ruined. It is contended on behalf of the defendant that the tanks were constructed from good material, and were built in a workmanlike manner, and that' they were the perfect products of workmanship, and that if they leaked after being placed in use, it was due entirely to the fault of the purchaser by reason of the faulty construction of the platform upon which they were placed for use.

The assignments of error set out in the petition in error are two, namely:

“First. The court committed error in overruling the motion for a new trial filed by plaintiff in error.
“Second. The court committed error in giving that part of his instruction to the jury contained on page 60 of the transcript, *168 and to -which exceptions of plaintiff in enror were noted at the time.’!

"We find by reference to the motion fop new trial that one ground only is set out therein, namely, that “the verdict is not sustained by sufficient evidence, and is contrary to law.”

An examination of the testimony discloses that there is testimony to support the verdict of the jury. It is true that all of the testimony as to the amount of damage sustained is controverted, but this testimony raised issues of fact that were for the determination of the jury, and. its finding being supported by the evidence, .in the absence of prejudicial errors of law, is conclusive upon this appeal. The record fails to disclose that any proper exception was saved to the instructions of the court referred to by the second assignment of error, as required by section 5003, Rev. Laws 1910 (A. B. Farquhar Co., Limited, v. Sherman et al., 22 Okla. 17, 97 Pac. 565), and therefore this assignment presents no question for review.

This leaves but one assignment for consideration ; that is, the one set out in the motion for a new trial, and in the first paragraph of the petition in error, namely, that the verdict is not sustained by sufficient evidence, and Is contrary -to law. There is evidence tending to support the verdict, and the same does not seem to be contrary to law. The guaranty given by the vendor to the vendee was that the tanks were “to be in good service and condition.” If the tanks leaked there was a breach of this guaranty. The fact that the tanks did leak is not denied by any witness. There was a sharp conflict in the testimony as to what caused the leak, whether it was due to defects in the construction of the tanks or a faulty construction of the platform on which they were placed by the vendee. This was an issue of fact that was properly submitted to the jury, and its finding being supported by the evidence and the law is binding on this appeal.

The rule for the measure of damages for breach of an obligation arising from contract is prescribed 'by statute, and is set out in section 2852, Rev. Laws 1910, as follows:

“For the breach of an obligation arising from contract, the measure of damages,’except where otherwise expressly provided by this chapter, is the amount, which will compensate the party aggrieved for all the detriment proximately caused thereby, or which, in the ordinary course of things, would be 'likely to result therefrom. No damages can be recovered for a breach of contract, which are not clearly ascertainable in both their nature and origin.”

A late case in which this court made application of the above rule, and approved the amount of damages recovered in an action arising out of the breach of an obligation of a contract, is Dickerson et al. v. Incorporated Town of Eldorado, 64 Okla. 142, 166 Pac. 708.

The application of the rule to the instant case sustains the judgment entered in the court below. It therefore follows that the same should be affirmed.

By 'the .Court: It is so ordered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittman v. Oklahoma Natural Gas Co.
1951 OK 331 (Supreme Court of Oklahoma, 1951)
Kansas, O. & G. Ry. Co. v. Dillon
1942 OK 174 (Supreme Court of Oklahoma, 1942)
Pure Oil Co. v. Chisholm
1936 OK 252 (Supreme Court of Oklahoma, 1936)
State Guaranty Bank v. Doerfler
1924 OK 598 (Supreme Court of Oklahoma, 1924)
Chortney v. Curry
1924 OK 497 (Supreme Court of Oklahoma, 1924)
Rock Island Coal Mining Co. v. Allen
1924 OK 508 (Supreme Court of Oklahoma, 1924)
Hemme v. Stein
1923 OK 686 (Supreme Court of Oklahoma, 1923)
Missouri Pacific Ry. Co. v. Horn
1923 OK 640 (Supreme Court of Oklahoma, 1923)
Hapgood v. Vickery
1923 OK 535 (Supreme Court of Oklahoma, 1923)
Sand Springs Railway Co. v. Westhafer
1923 OK 513 (Supreme Court of Oklahoma, 1923)
Young v. Cole
1923 OK 408 (Supreme Court of Oklahoma, 1923)
Carson v. Harrod
1923 OK 330 (Supreme Court of Oklahoma, 1923)
Dague v. McCaslin
196 P. 696 (Supreme Court of Oklahoma, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
1917 OK 466, 168 P. 196, 66 Okla. 167, 1917 Okla. LEXIS 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinney-v-williams-okla-1917.