Kinney v. Massachusetts Bonding & Insurance

210 A.D. 285, 206 N.Y.S. 163, 1924 N.Y. App. Div. LEXIS 6713
Appellate Division of the Supreme Court of the State of New York·Decided September 12, 1924·Published·Cited by 4 cases

Opinion

H. T. Kellogg, J.:

The plaintiffs were the owners of premises in the city of Albany lying between State street on the north and Norton street on the south. A brick building, which once stood upon the premises, had been razed to the first floor, but foundation walls and a concrete basement floor remained in place. The plaintiffs determined to erect upon the premises a nine-story building of modern type. It was a necessary preliminary to remove the old foundations and the basement floor, to shore up the walls of the adjoining buildings and underpin them. General excavations to a new building level were also necessary. On the 3d day of November, 1915, the plaintiffs entered into a contract with the defendant, the W. Shelton Swallow Company, relating to the construction of the new building. The Swallow Company, for a unit price, agreed to do all shoring and underpinning, and to excavate therefor. It also agreed, for the lump sum price of $77,000, to perform all masonry, carpentry, roofing, sheet metal, painting and glazing work, specified in plans and specifications attached, to make general excavations and to furnish all specified building materials to be used in the work contracted for. It agreed fully to perform on or before April 15, 1916. The plaintiffs made a separate contract for the erection of structural steel, specified for the new building, with the Levering and Garrigues Company. This contract was dated October 14, 1915. It provided that delivery and installation of steel grillage should begin on or before December 9; 1915; that superstructura! steel should begin to be delivered on December 23, 1915; that the steel work should be substantially completed on February 3, 1916. The Swallow Company began work upon its contract on November 4, 1915, and continued to work thereunder until about February 14, 1916. On or about this date it discontinued all work and thereafter performed none. The plaintiffs brought this action, and have had a recovery, against the Swallow Company and the Massachusetts Bonding and Insurance Company, its surety, for damages resulting from the failure of the Swallow Company to complete its contract.

The premises upon which the new building was to be constructed were 168 feet in depth and 36 feet in width. This narrow space was bounded on either side by the high walls of adjoining buildings and on either end by public streets. It was necessary for the Swallow Company to start excavations paralleling the walls in [287] order that the earth beneath them might be removed and the spaces filled with concrete underpinning. It was then necessary to begin digging trenches alongside the walls and to pave the trenches with cement in order to receive longitudinal grillage which the steel contractors were required to place. After this grillage, consisting of steel girders, had been placed by the steel contractor and filled with concrete by the Swallow Company, it was necessary that cross trenches should be excavated and paved to receive cross grillage at intervals of about fifteen feet. The ends of the cross grillage beams were to rest on the longitudinal grillage and to be incased with cement. The steel contractors were then to erect a steel superstructure upon the grillage work. The superstructure, when erected, was to be incased with masonry work, and the building was to be roofed by the Swallow Company. It is clear that performance of the masonry contract was dependent upon performance of the steel contract, and, conversely, that performance of the latter was dependent upon performance of the former. Neither party could perform its contract and perform it on time unless the other party made timely performance. Yet neither party had the power to compel or hasten performance by the other party. It is not to be supposed that either party contracted to accomplish that which might prove to be an impossibility. Therefore, from the necessities of the case, it must be inferred that the plaintiffs, in contracting with the Swallow Company, and with the Levering and Garrigues Company, promised to each contractor timely performance by the other contractor of all work the performance of which necessarily preceded the fulfillment of its own obligation.

Free access — add to your briefcase to read the full text and ask questions with AI

Kinney v. Massachusetts Bonding & Insurance, 210 A.D. 285, 206 N.Y.S. 163, 1924 N.Y. App. Div. LEXIS 6713 (N.Y. Ct. App. 1924).

210 A.D. 285 (Kinney v. Massachusetts Bonding & Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
BGW Development Corp. v. Mount Kisco Lodge
264 A.D.2d 433 (Appellate Division of the Supreme Court of New York, 1999)
Aero Garage Corp. v. Hirschfeld
185 A.D.2d 775 (Appellate Division of the Supreme Court of New York, 1992)
City of Elmira v. Larry Walter, Inc.
150 A.D.2d 129 (Appellate Division of the Supreme Court of New York, 1989)