Kinney v. Massachusetts Bonding & Insurance

210 A.D. 285, 206 N.Y.S. 163, 1924 N.Y. App. Div. LEXIS 6713
CourtAppellate Division of the Supreme Court of the State of New York
DecidedSeptember 12, 1924
StatusPublished
Cited by4 cases

This text of 210 A.D. 285 (Kinney v. Massachusetts Bonding & Insurance) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinney v. Massachusetts Bonding & Insurance, 210 A.D. 285, 206 N.Y.S. 163, 1924 N.Y. App. Div. LEXIS 6713 (N.Y. Ct. App. 1924).

Opinion

H. T. Kellogg, J.:

The plaintiffs were the owners of premises in the city of Albany lying between State street on the north and Norton street on the south. A brick building, which once stood upon the premises, had been razed to the first floor, but foundation walls and a concrete basement floor remained in place. The plaintiffs determined to erect upon the premises a nine-story building of modern type. It was a necessary preliminary to remove the old foundations and the basement floor, to shore up the walls of the adjoining buildings and underpin them. General excavations to a new building level were also necessary. On the 3d day of November, 1915, the plaintiffs entered into a contract with the defendant, the W. Shelton Swallow Company, relating to the construction of the new building. The Swallow Company, for a unit price, agreed to do all shoring and underpinning, and to excavate therefor. It also agreed, for the lump sum price of $77,000, to perform all masonry, carpentry, roofing, sheet metal, painting and glazing work, specified in plans and specifications attached, to make general excavations and to furnish all specified building materials to be used in the work contracted for. It agreed fully to perform on or before April 15, 1916. The plaintiffs made a separate contract for the erection of structural steel, specified for the new building, with the Levering and Garrigues Company. This contract was dated October 14, 1915. It provided that delivery and installation of steel grillage should begin on or before December 9; 1915; that superstructura! steel should begin to be delivered on December 23, 1915; that the steel work should be substantially completed on February 3, 1916. The Swallow Company began work upon its contract on November 4, 1915, and continued to work thereunder until about February 14, 1916. On or about this date it discontinued all work and thereafter performed none. The plaintiffs brought this action, and have had a recovery, against the Swallow Company and the Massachusetts Bonding and Insurance Company, its surety, for damages resulting from the failure of the Swallow Company to complete its contract.

The premises upon which the new building was to be constructed were 168 feet in depth and 36 feet in width. This narrow space was bounded on either side by the high walls of adjoining buildings and on either end by public streets. It was necessary for the Swallow Company to start excavations paralleling the walls in [287]*287order that the earth beneath them might be removed and the spaces filled with concrete underpinning. It was then necessary to begin digging trenches alongside the walls and to pave the trenches with cement in order to receive longitudinal grillage which the steel contractors were required to place. After this grillage, consisting of steel girders, had been placed by the steel contractor and filled with concrete by the Swallow Company, it was necessary that cross trenches should be excavated and paved to receive cross grillage at intervals of about fifteen feet. The ends of the cross grillage beams were to rest on the longitudinal grillage and to be incased with cement. The steel contractors were then to erect a steel superstructure upon the grillage work. The superstructure, when erected, was to be incased with masonry work, and the building was to be roofed by the Swallow Company. It is clear that performance of the masonry contract was dependent upon performance of the steel contract, and, conversely, that performance of the latter was dependent upon performance of the former. Neither party could perform its contract and perform it on time unless the other party made timely performance. Yet neither party had the power to compel or hasten performance by the other party. It is not to be supposed that either party contracted to accomplish that which might prove to be an impossibility. Therefore, from the necessities of the case, it must be inferred that the plaintiffs, in contracting with the Swallow Company, and with the Levering and Garrigues Company, promised to each contractor timely performance by the other contractor of all work the performance of which necessarily preceded the fulfillment of its own obligation.

The Swallow Company, prior to February 14, 1916, had been engaged in underpinning walls, excavating for longitudinal and cross grillage, filling trenches with concrete to receive grillage, concreting the grillage and making general excavations for the new basement floor level. On that day the Swallow Company wrote the plaintiffs a letter inclosing a bill for extra work and for damages arising from alleged delays on the part of the steel contractor. It asserted that, in excavating the basement floor of the old building, it encountered underneath the cement, down the center line of the floor, steel grillage which had been placed to support a line of supporting columns; that this grillage was concealed from view and its existence was unknown to it when the contract was made; that disclosure of its existence should have been made to it by the plaintiffs whose architects had themselves long previously caused the grillage to be placed; that it was entitled to extra compensation for the removal of the grillage. It also asserted that the plans and specifications did not indicate that the [288]*288Swallow Company was called upon to excavate or pave for cross grillage work, or to incase cross grillage with concrete. It also asserted that the steel contractors had unnecessarily delayed the steel work, causing delay and damage to the plaintiffs. The bill inclosed itemized various charges for delay and extra work aggregating $14,700. The letter said: “ Under the circumstances we are unwilling to proceed with the work unless we can have from you a further allowance of time for completion, an agreement to pay our bill annexed hereto and a further agreement on your part to pay us all additional cost and expense arising out of or in connection with the present situation.” It also said: “ In the event of your failure to meet our demands, we will elect to consider the contract broken and hold you responsible for all damage.” The plaintiffs replied with a letter of February 17, 1916, in which they stated that the Swallow Company’s claims appeared to have no merit, and that unless that company proceeded with the work the plaintiffs would avail themselves of their contract rights. They requested the Swallow-Company to advise them whether it would continue your work under the contract.” Several letters passed between the parties, but in none of them did the Swallow Company advise the plaintiffs that they would continue work. Finally, on February twenty-fourth, the plaintiffs served a written notice upon the Swallow Company and its defendant surety. This notice recited that the Swallow Company had refused and neglected to provide a sufficiency of materials and of workmen for the due progress of the work, that it was continuing in such refusal and neglect, and that it was causing an unreasonable neglect and suspension ” of the work. It gave notice that if the Swallow Company continued in such refusal and neglect for a period of forty-eight hours the plaintiffs would take possession and provide materials and labor to finish the job in the place of the Swallow Company. On February 25, 1916, the Swallow Company, having been served with the notice, wrote a letter to the plaintiffs in which, among other things, it said that it is absolutely impossible to attempt to comply with your wishes to proceed with the work.” It also said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Fidelity Insurance v. County of Rockland
98 F. Supp. 2d 400 (S.D. New York, 2000)
BGW Development Corp. v. Mount Kisco Lodge
264 A.D.2d 433 (Appellate Division of the Supreme Court of New York, 1999)
Aero Garage Corp. v. Hirschfeld
185 A.D.2d 775 (Appellate Division of the Supreme Court of New York, 1992)
City of Elmira v. Larry Walter, Inc.
150 A.D.2d 129 (Appellate Division of the Supreme Court of New York, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
210 A.D. 285, 206 N.Y.S. 163, 1924 N.Y. App. Div. LEXIS 6713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinney-v-massachusetts-bonding-insurance-nyappdiv-1924.