Kingston v. Markward & Karafilis, Inc

350 N.W.2d 842, 134 Mich. App. 164
CourtMichigan Court of Appeals
DecidedApril 30, 1984
DocketDocket 59944, 62538
StatusPublished
Cited by7 cases

This text of 350 N.W.2d 842 (Kingston v. Markward & Karafilis, Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingston v. Markward & Karafilis, Inc, 350 N.W.2d 842, 134 Mich. App. 164 (Mich. Ct. App. 1984).

Opinion

Shepherd, J.

Following a jury trial, a verdict in plaintiffs favor in the amount of $3,000,000 was entered jointly against defendant cross-defendant appellant, W.J.C. Kaufmann Construction Co. (Kaufmann) and defendant cross-plaintiff appellee Markward & Karafilis, Inc. (Markward). The jury awarded total indemnity in favor of Markward. *167 Kaufmann now appeals as of right from the trial court’s order denying its motion for judgment notwithstanding the verdict on the issue of indemnity. Markward also appeals, claiming that it should have been granted a directed verdict in favor of indemnity. The appeals have been consolidated by order of this Court. We find Kaufmann’s claim to be meritorious since we find that Kaufmann owed no obligation of indemnity to Mark-ward.

On December 11, 1976, plaintiffs decedent, Charles G. Kingston, who was employed by defendant Chrysler Corporation, was assisting another employee in replacing metal plate covers on top of an oil reservoir. The plate cover on which Kingston was standing slipped and he fell into the reservoir and died.

The reservoir and metal plate covers had been constructed in 1969 and 1970 when the plant at which Kingston worked was renovated. The metal plates were constructed by Kaufmann pursuant to an agreement with Chrysler that was embodied in a purchase order and related documents dated February 27, 1969. By reference in the purchase agreement, the parties’ contract was to be governed by Chrysler’s General Conditions, apparently standard conditions included by Chrysler in its contracts. Included in the General Conditions was a clause indemnifying Chrysler against property damage and personal injury related to the contractor’s (Kaufmann’s) work.

On March 19, 1969, Chrysler and Markward entered into an agreement for the construction of an addition to the same building. That purchase letter was issued on April 17, 1969. The metal plates constructed by Kaufmann were considered a substructure of the building; the addition con *168 structed by Markward was labeled a superstructure which was added to the building.

On April 3, 1969, Chrysler Corporation sent Kaufmann a letter, informing Kaufmann that its contract was "assigned” to Markward. The letter also said:

"We will be issuing a Purchase Order Change shortly officially effecting this assignment. At that time the above noted contractor will assume the responsibility for overall administration and coordination, but Chrysler will continue to make direct payments to you under the terms of our present contract.”

Kaufmann acknowledged the letter on April 8, 1969:

"This will acknowledge receipt of your letter of April 3, 1969, advising that our Purchase Order for the above subject work is being assigned to Markward & Karafilis, Inc.

"We have no objection to this assignment as long as our retention money is not held until completion of the Marward contract.”

Kaufmann finished work on the reservoir plates in May, 1969. The purchase order change was issued on June 16, 1969, and said:

"Add to Order:

"The coordination and responsibility of this contract is now assigned to the General Contractor, Markward & Karafilis, Inc., with payment being made direct by Chrysler Corporation.”

On July 7, 1969, Markward sent a letter to the architect associated with the renovation, John G. Hoad & Associates, advising Hoad that gratings (covers) on the oil reservoir tanks were not an *169 chored and therefore posed a danger to property and people. Markward asked Hoad to inspect the gratings. Markward was not advised of any subsequent changes to be made, nor was Kaufmann ever informed by Markward of the slippage problem or of Markward’s concern. Under the terms of Kaufmann’s contract with Chrysler, construction of "stops” on the plates would have been considered extra and additional work, according to Hoad, since they were not included in the plans and specifications issued to Kaufmann.

In November, 1969, Hoad notified Chrysler by letter that Kaufmann had completed the substructure work in acceptable condition. Markward concurred and final payment was recommended. In January, 1970, construction meetings were held at which Chrysler, Hoad, and Markward, among others, were present, and at which the loose fit of the gratings was noted. Kaufmann was not represented at the meeting. Protective stops apparently were never added to the gratings.

Decedent’s estate ultimately brought an action against Markward, which plaintiff claimed was the general contractor; Kaufmann, which plaintiff identified as a subcontractor; and Hoad Associates, the architect. Third-party complaints for common-law indemnity were filed against Chrysler by Markward and Kaufmann. Markward cross-claimed for indemnity against Kaufmann on the basis of the assignment of the contract by Chrysler. Chrysler tendered its defense to the third-party complaint to Kaufmann, claiming that it had a right to indemnity under its contract with Kaufmann.

At trial, upon the close of proofs, Markward moved for a "conditional” directed verdict on its cross-claim: if the jury found "active” negligence *170 by Markward or Kaufmann or found that Mark-ward was liable for failing to point out Kaufmann’s negligence, then Markward would be totally indemnified by Kaufmann. The trial judge denied the motion, stating:

"I don’t think there is anything in the testimony or anything in the way the parties have described their conduct that indicates that the — that there was, indeed, intended to be the broad indemnification moving to Markward and Karafilis from Kaufmann that is referred to in the body of that indemnification paragraph.”

However, the court eventually charged the jury:

"I charge you that the evidence indicates that Mark-ward and Karafilis pursuant to the assignment of the purchase order in question had a contract with W.J.C. Kaufmann Construction Company and, therefore, W.J.C. Kaufmann Construction Company is bound by the applicable terms of said contract. The existence of the indemnity agreement in the contract language between Markward and Karafilis and W.J.C. Kaufmann Construction Company is undisputed. Because of this, I charge you that the indemnity agreement is presumed to be understood by both parties.

"You are instructed that the Markward and Karafilis Company is entitled to a verdict in its favor on the cross-claim for indemnity under the language of the purchase order under any one of the following circumstances:

"One. That the W.J.C. Kaufmann Construction Company was negligent and its negligence was the full proximate cause of the plaintiffs decedent’s death, or:

"Number two. That both Markward and Karafilis and W.J.C. Kaufmann Construction Company were negligent and this negligence was a proximate cause of plaintiffs decedent’s death.”

Kaufmann noted its objections to the charge.

*171 The jury returned a verdict in the amount of $3,000,000 in favor of plaintiff, jointly against Markward and Kaufmann.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ab Petro Mart, Inc v. Ali T Beydoun Insurance Agency, Inc
317 Mich. App. 290 (Michigan Court of Appeals, 2016)
ISRA VISION, AG v. Burton Industries, Inc.
654 F. Supp. 2d 638 (E.D. Michigan, 2009)
Butt v. Giammariner
433 N.W.2d 360 (Michigan Court of Appeals, 1988)
People v. Ranson
395 N.W.2d 271 (Michigan Court of Appeals, 1986)
Dundee v. Puerto Rico Marine Management, Inc
383 N.W.2d 176 (Michigan Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
350 N.W.2d 842, 134 Mich. App. 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-v-markward-karafilis-inc-michctapp-1984.