Kingston Trap Rock Co. v. Eastern Engineering Co.

39 A.2d 422, 132 N.J.L. 254, 1944 N.J. LEXIS 248
CourtSupreme Court of New Jersey
DecidedOctober 17, 1944
StatusPublished
Cited by9 cases

This text of 39 A.2d 422 (Kingston Trap Rock Co. v. Eastern Engineering Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingston Trap Rock Co. v. Eastern Engineering Co., 39 A.2d 422, 132 N.J.L. 254, 1944 N.J. LEXIS 248 (N.J. 1944).

Opinion

The opinion of the court was delivered by

Perskie, J.

The question for decision is whether the trial judge misconstrued, as urged, the contract in issue.

Appellants, Kingston Trap Rock Co. and Lambertville Quarry Co., corporations of this state, the former shall be hereafter referred to as Kingston and the latter as Lambert-ville, sued defendant, Eastern Engineering Company, also a corporation of this state, which shall be hereafter referred to as Eastern, to recover the contract price for stone they allegedly furnished Eastern under a contract between Kingston and Eastern dated August 6th, 1942. The complaint consists of two counts.

The first count relates to the claims of Kingston. It alleges that pursuant to its contract Kingston furnished Eastern with 32,598.62 tons of stone, which Eastern accepted and for which it agreed to pay at the rate of $1.50 a ton; that of this total tonnage, 20,900.51 tons were furnished to and accepted by Eastern on or before December 31st, 1942, and Eastern paid for same; that the remaining 11,698.11 tons were furnished between January 1st, 1943, and March 9th, 1943, and as so furnished were accepted but not paid for by *255 Eastern; and thus that there was due and owing to Kingston the sum of $17,547.16 plus interest.

The second count relates to the claim of Lambertville. It-alleges that pursuant to the stated contract (August 6th, 1942) Lambertville furnished Eastern, at its request, 14,003.22 tons of stone at the agreed rate of $1.38 a ton, the difference of twelve cents on each ton being the allowed difference in the freight rates as provided by the contract; that of this total, 9,275.2 tons were furnished to and accepted by Eastern on or before December 31st, 1942, and Eastern paid for same; that the remaining 4,728.02 tons were furnished between January 1st, 1943, and March 9th, 1943, and were accepted but, as with Kingston’s claim, were not paid for by Eastern; and that thus there was due and owing to Lambertville $6,524.66 plus interest. Kingston joined in this count as plaintiff, in the alternative, in the event it would be determined that the claim of Lambertville resides in Kingston under the contract.

Eastern denied liability. Additionally, it sought to recover from Kingston, by way of counter-claim, the damages it allegedly suffered because of Kingston’s breach of the contract. More specifically stated, the alleged breach was that Kingston did not furnish between 500 to 700 tons of stone a day as it had contracted to do notwithstanding that it had been advised that such daily supply was vitally necessary in order for Eastern to complete its contract with the United States of America for the construction of two parallel rubble jetties at the Delaware Bay entrance to the Gape May County Canal, and notwithstanding that frequent demands were made upon Kingston to comply with its contract with Eastern, and notwithstanding that Kingston was advised that its failure to do so was causing it (Eastern) delay in completing the construction of the jetties with resultant money loss which Kingston would be called upon to satisfy. The alleged money loss of $32,128 is made up as follows: (1) $22,718 expended for additional equipment and labor, (2) $7,410 increased costs for hauling and trucking, and (3) $2,000 excess costs for general office overhead.

Kingston denied liability on the counter-claim. Of its *256 additional six separate defenses but three (first, fifth and sixth) are admittedly embraced in the like numbered grounds of appeal here argued.

The first separate defense concedes its contractual obligation to furnish approximately 500 to 700 tons of stone a day during the months of August, September, October and November, 1942, but asserts that Eastern refused to order or accept such supply and hence waived any right or claim for damages for the non-delivery in the specified quantities; the fifth is that it was not obliged under the provisions of the contract (“Contingencies”) to furnish stone in any specified quantities after December 1st, 1942; and the sixth is that under the further contingent provisions of the contract it was unable to obtain cars from the railroads to furnish the specified daily quantities of stone.

At the end of the proofs offered by Kingston and Lambert-ville in support of their alleged claims, the trial judge granted Eastern’s motion for a nonsuit as to Lambertville. Judgment of nonsuit was entered accordingly. Pursuant to the directions of the trial judge on the motion to nonsuit, the trial proceeded on the basis that the claims embraced in both counts constituted a single claim of Kingston against Eastern. The case was so tried. Notwithstanding its pleaded denial of liability, Eastern in the course of the trial admitted, but without'prejudice to its counter-claim, that it owed Kingston the sum of $25,293.11 under both counts. Accordingly, the jury, as directed, returned a verdict in the admitted amount in favor of Kingston and against Eastern. Prom the judgment entered upon that verdict, no appeal is taken. On the conflicting proofs as to which of the parties was at fault on Eastern’s counter-claim, the jury returned a verdict of $20,000 in favor of Eastern and against Kingston. Judgment was entered accordingly. Hence Kingston in case No. 10 and Lambertville in case No. 14, appeal.

As to Kingston’s appeal. The contract in issue has for its source a public invitation, issued in July of 1942, by the United States of America (Engineering Office of the War Department) for the furnishing of the necessaiy equipment, materials, &c., and for the construction of the Stated *257 jetties. (Italics supplied.) To the end of submitting a bid on the day set (July 29th, 1942) Eastern communicated with Kingston. It was advised that Kingston was tlioroughly familiar with the specifications, the three classes of stone and the quantities thereof required, and that it had given quotations thereon. It quoted Eastern the price of $1.50 a ton plus freight. Eastern was the successful bidder. It further negotiated with the government, as it was obliged to do under the advertised form of “Negotiated Contract,” with results satisfactory to each. Eastern, however, did not sign the contract with the government until it further assured itself of Kingston’s ability to supply the stone in the time and in the quantities specified. Accordingly, the vice-president of Eastern called upon the president of Kingston and informed him that Eastern did not want to sign the government contract unless it could be assured of deliveries of stone of 500 to 600 tons a day. The president of Kingston called in its foreman, all three discussed the situation in detail. Kingston was advised of the beginning date (August 20th, 1942) and completion date (December 28th, 1942) and that Eastern would require a few weeks to make preparatory arrangements such as building roads, &c. The result reached was that Kingston could with the purchase of an additional crane meet the requirements. Thus it was that the conceded confirmation, under date of August 4th, 1912, of the oral quotations, was accepted for Eastern on August 6th, 1942. The contract between the government and Eastern, although dated July 29th, 1942, pursuant to the prescribed government practice, was in fact signed by the parties some two or three weeks thereafter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruenn v. Switlik
447 A.2d 583 (New Jersey Superior Court App Division, 1982)
American Express Co. v. Rona Travel Service, Inc.
187 A.2d 206 (New Jersey Superior Court App Division, 1962)
MacFadden v. MacFadden
139 A.2d 774 (New Jersey Superior Court App Division, 1958)
Journeymen Barbers' International Union, Local 687 v. Pollino
126 A.2d 194 (Supreme Court of New Jersey, 1956)
William Berland Realty Co. v. Hahne & Co.
98 A.2d 124 (New Jersey Superior Court App Division, 1953)
Balsham v. Koffler
73 A.2d 272 (New Jersey Superior Court App Division, 1950)
Rolle Mfg. Co. v. Marco Chemicals, Inc.
92 F. Supp. 218 (D. New Jersey, 1950)
Mayer v. Sulzberger
71 A.2d 233 (New Jersey Superior Court App Division, 1950)
Independent Directory Corp. v. Sherman Ind., Etc.
69 A.2d 746 (New Jersey Superior Court App Division, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
39 A.2d 422, 132 N.J.L. 254, 1944 N.J. LEXIS 248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-trap-rock-co-v-eastern-engineering-co-nj-1944.