KINGSTON PIPE INDUSTRIES, INC. v. Champlain Sprinkler, Inc.

2004 VT 59, 857 A.2d 767, 177 Vt. 484, 54 U.C.C. Rep. Serv. 2d (West) 109, 2004 Vt. LEXIS 181
CourtSupreme Court of Vermont
DecidedJune 15, 2004
Docket03-271
StatusPublished
Cited by1 cases

This text of 2004 VT 59 (KINGSTON PIPE INDUSTRIES, INC. v. Champlain Sprinkler, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KINGSTON PIPE INDUSTRIES, INC. v. Champlain Sprinkler, Inc., 2004 VT 59, 857 A.2d 767, 177 Vt. 484, 54 U.C.C. Rep. Serv. 2d (West) 109, 2004 Vt. LEXIS 181 (Vt. 2004).

Opinion

¶ 1. Champlain Sprinkler, Inc., and company president Bruce Pelkey (together Champlain) appeal a summary judgment decision of the Franklin Superior Court granting Kingston Pipe Industries, Inc. (Kingston) damages in the amount of $14,093.28, attorney’s fees, and court costs. Champlain contends that summary judgment was improper because there is a genuine issue of material fact about whether Kingston was in breach of warranty for defects in its pipe and, if so, whether Champlain’s costs to cure the defects should offset the damages. We reverse.

¶ 2. In reviewing a summary judgment decision, we use “the same standard as the trial court, and affirm the granting of a motion for summary judgment if there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law.” Springfield Hydroelectric Co. v. Copp, 172 Vt. 311, 313, 779 A.2d 67, 70 (2001) (internal quotations and citation omitted); V.R.C.P. 56(c)(3). Additionally, we regard all allegations made in opposition to the motion as true if supported by affidavit or other evidence, LaShay v. Dep’t of Social & Rehabilitation Servs., 160 Vt. 60, 62, 625 A.2d 224, 225-26 (1993), and thus summarize the facts as advanced by appellant.

¶ 3. Champlain installs fire protection sprinkler systems. Kingston is a specialty pipe supplier that offei’s prefabricated, ready-to-install sprinkler systems. In the fall of 2000, Pelkey ordered custom pipe from Kingston to install in the Vermont Agency of Transportation’s Colchester garage. Champlain admits that it accepted but never paid for the pipe order.

¶ 4. On July 10, 2002, Kingston filed a complaint against Champlain and a motion for trustee process in Franklin Superior Court to collect payment for the pipe. In its complaint, Kingston claimed, inter alia, that Champlain breached its contract with Kingston by refusing to pay for the pipe it received. In its answer Champlain raised, as affirmative defenses, failure of consideration and that “[t]he materials were defective.”

¶ 5. The court (Judge Teachout) heard Kingston’s motion for trustee process on August 22, 2002. At the hearing, the court explained that “the purpose of the [trustee] hearing is to determine whether or not there is a reasonable likelihood of recovery” and asked Champlain whether there were “any defenses to the issuance of the trustee process.” Champlain’s counsel responded that his client had “received defective products and the offset [of accommodating those defects] outweighs any monies that [Kingston] would be receiving.”

¶ 6. At the hearing, Pelkey testified regarding the pipe’s defects and Champlain’s costs to remedy those defects. He testified that the general contractor at the Colchester job site notified him that the pipe was rejected by the State of Vermont because it was “full of rust inside and out.” Pelkey then notified Kingston Pipe. However, Kingston had no replacement pipe available, nor could Pelkey find another supplier in time to complete the job. So instead, Champlain attempted to fix the pipe by removing the rust. After Champlain cleaned and installed the pipe, some of the prethreaded joints began to leak. Champlain ultimately had to reinstall the pipe four times, and replace leaking joints by cutting off threaded fittings and installing welded pipe joints. Pelkey also pro *485 vided an itemized list showing that the total cost to fix the defects exceeded the purchase price of the pipe. Based on the facts presented, the court held that Kingston did not have a reasonable likelihood of success on the merits and denied Kingston’s motion for trustee process.

¶ 7. Four months later, Kingston filed a motion for summary judgment arguing that Champlain could not avoid payment because it accepted the pipe, knowing it was rusty. In support of the motion, Kingston submitted a portion of Pelkey’s testimony from the trustee process hearing, but omitted the five pages of his testimony detailing Champlain’s costs to cure defects in the pipe. Champlain answered by citing to the Uniform Commercial Code, 9A V.S.A. § 2-714 (buyer’s damages for breach caused by nonconformity of tender) and § 2-717 (deduction of buyer’s damages from purchase price). Champlain also submitted an affidavit from Pelkey swearing to the factual allegations contained in its response to summary judgment, but did not submit the missing five pages of Pelkey’s testimony.

¶ 8. The court (Judge Pearson) awarded summary judgment to Kingston, concluding that under Brown’s Auto Salvage v. Piche, 145 Vt. 485, 491 A.2d 1041 (1985), Champlain accepted the rusty pipe when it installed it and, therefore, as a matter of law could not later complain about the rust or raise an offset defense. Additionally, the court held that since the allegedly defective threading was not discovered until after installation, Champlain could only claim incidental or consequential damages, and then only as a counterclaim. Having failed to mount such a compulsory counterclaim, see V.R.C.P. 13(a), the court refused to consider damages caused by the allegedly defective threading. This appeal followed.

¶ 9. The parties first dispute whether Champlain met its burden, as the non-moving party under Rule 56(e), to submit credible documentary evidence or affidavits sufficient to rebut the evidence of the moving party. See Boulton v. CLD Consulting Eng’rs, Inc., 2003 VT 72, ¶ 5, 175 Vt. 413, 834 A.2d 37 (in summary judgment nonmoving party may not rest on allegations in pleadings, but must persuade court, based on evidence in record, that there is a triable issue of fact). Clearly Pelkey’s testimony from the trustee process hearing regarding defects in the pipe, and Champlain’s cost to cure those defects, raises a genuine issue of material fact regarding damages incurred by Champlain. Kingston Pipe argues that Champlain is precluded from using that testimony since it failed to resubmit the relevant portions in support of its answer to summary judgment.

¶ 10. We long ago determined, however, that the date evidence is submitted to the court is “immaterial” for purposes of summary judgment. Pierce v. Riggs, 149 Vt. 136, 138, 540 A.2d 655, 657 (1987).

[W]hen entertaining' a Rule 56 motion for summary judgment, the trial court is required to consider the entire setting of the case, including the affidavits, depositions, admissions, answers to interrogatories and similar material on file to determine the existence of a genuine issue of material fact...! Therefore, the entire record is to be considered.

Id. As we decide summary judgment motions under the same standard as the trial court, the Court will consider the full evidentiary record, including all of Pelkey’s testimony in the initial trustee process hearing.

¶ 11. The remaining issue is whether Champlain is precluded from claiming those damages as a defense to Kingston’s collection action, either because Champlain accepted the pipe knowing of the rust nonconformity or because it failed to *486

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Appeal of Cowan
2005 VT 126 (Supreme Court of Vermont, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 VT 59, 857 A.2d 767, 177 Vt. 484, 54 U.C.C. Rep. Serv. 2d (West) 109, 2004 Vt. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-pipe-industries-inc-v-champlain-sprinkler-inc-vt-2004.