Kingston Electric, Inc. v. Wal-Mart Properties, Inc.

901 S.W.2d 260
CourtMissouri Court of Appeals
DecidedMay 16, 1995
DocketNos. 67068, 67100
StatusPublished
Cited by4 cases

This text of 901 S.W.2d 260 (Kingston Electric, Inc. v. Wal-Mart Properties, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingston Electric, Inc. v. Wal-Mart Properties, Inc., 901 S.W.2d 260 (Mo. Ct. App. 1995).

Opinion

GRIMM, Chief Judge.

On November 12, 1987, Max Barken Construction Company, Inc.,1 entered into a contract with Wal-Mart Properties, Inc. Under the agreement, Barken was the general contractor for the construction of a Wal-Mart Store in St. Louis County.

On that same day, Barken entered into several subcontracts. This appeal concerns two. One was with Kingston Electric, Inc.; it required Kingston to furnish labor, materials, and equipment to complete certain electrical work. A dispute arose as to whether Kingston was obligated to complete the parking lot lighting system. The trial court held that Kingston was not and granted Kingston a mechanic’s lien for other sums due. We affirm that judgment.

Barken’s other subcontract was with Economy Door and Glass Company. Economy was to provide and install certain window glass and frames. Economy, in turn, contracted with PPG Industries, Inc. to have PPG supply the glass and frames. PPG furnished the materials, Economy performed its contract, and Barken paid Economy. However, Economy failed to pay PPG. The trial court granted PPG a mechanic’s lien. We reverse that judgment.

I. Kingston’s Mechanic’s Lien

A. Sufficiency of Notice

In their first point, Barken and Wal-Mart allege the trial court erred in granting a mechanic’s lien for Kingston because “Kingston failed to prove proper service of notice of its mechanic’s lien claim on Wal-Mart, as required under section 429.100.”2

Section 429.100 requires that persons other than the original contractor must give the owner ten days notice before filing a mechanic’s lien. The notice must set forth the amount and from whom it is due. The statute states that “[s]ueh notice may be served by any officer authorized by law to serve process in civil actions, or by any person who would be a competent witness.” Id.

When the notice is served by an officer, his official, endorsed return is sufficient proof. When it is served by another person, “the fact of such service shall be verified by affidavit of the person so serving.” Id.

Under a strict construction of the statute, the fact of service here would be insufficient. However, the mechanic’s lien law is highly remedial. In order to “advance its equitable object, a liberal construction should be given to all of its provisions.” The Fruin-Bambrick Constr. Co. v. Jones, 60 Mo.App. 1 (Mo.App.St.L.1894); Sentinel Woodtreating, Inc. v. Cascade Dev. Corp., 599 S.W.2d 268, 270 (Mo.App.S.D.1980).

[263]*263As a result, our courts have held that the manner of service is immaterial where it clearly appears that the owner actually received adequate written notice not less than ten days prior to the filing of the lien claim. Id,.; Fruin-Bambrick, 60 Mo.App. at 4. If the manner of service is immaterial when timely actual notice is received, it follows that the same rule should apply concerning the proof of service.

In the case before us, Kingston did not prove service by either an official return or affidavit. Rather, Kingston submitted records from Wal-Mart’s registered agent, C T Corporation System.

C T’s records reflect that on November 22, 1988, a “Notice by Contractor to Owner of Building of claim of Mechanic’s Lien” was served on C T. Also, on November 22, C T sent a “Service of Process Transmittal Form” to Wal-Mart. This form also contains the notation: “This confirms our telephone call to your office.” C T’s records contain a carbon copy of the Service of Process Transmittal Form. The signed carbon copy shows that the original was received on November 23, 1988. C T’s records were authenticated by its supervisor of service of process.

Here, the purpose of the notice, to give an owner time to investigate the merits before deciding whether to pay or contest the claim, was met. See Miller v. Hoffman, 26 Mo.App. 199, 202 (Mo.App.St.L.1887). Thus, although Kingston did not prove timely notice by one of the statutory methods, the proof given was sufficient to show that Wal-Mart received actual notice of Kingston’s intent to file a mechanic’s lien. Point denied.

B. Subcontract Provisions

In their second point, Barken and Wal-Mart allege the trial court erred in finding in favor of Kingston for $19,840.00, the cost of the parking lot lighting system. They argue that they properly set off this amount from what Kingston was paid because Kingston’s subcontract required it to do this work. They contend that when Kingston refused to do the work, they had to pay that sum to another contractor.

The opening section of the printed American Institute of Architects Subcontract form used by the parties incorporates by reference the agreement between the owner and contractor, the drawings, and the specifications. The second section of the printed form says that “The Subcontractor shall perform all the Work required by the Contract Documents for....” Among the listed, typed items is section “16530 — Site Lighting.”

Section 16530, as set forth in the project manual, consists of certain specifications for a parking lot lighting plan. “It is well settled that matters incorporated into a contract by reference are as much a part of the contract as if set out in haec verba.” Trantham v. Old Republic Ins. Co., 797 S.W.2d 771, 774 (Mo.App.E.D.1990). These sections would require Kingston to complete the parking lot lighting system.

However, another section of the form subcontract, which appears to conflict with the second section, must be considered. The last provision in the last section of the subcontract says: "... the documents which are applicable to this Subcontract, except for Addenda and Modifications issued after execution of this Subcontract, are enumerated as follows:.” A typed list of certain drawings, specifications, and addenda follows.

The pertinent drawing containing the plans for the parking lot system is Sheet Number E-l dated October 8, 1987. Sheet Number E-l dated October 8, 1987 is not included in the typed list.

Here, the subcontract contains contradictory provisions and is ambiguous on its face. The second section appears to include the parking lot lighting, while the last section does not.

A contract is ambiguous when its terms are susceptible of more than one meaning so that reasonable persons may fairly and honestly differ in their construction of the terms. J.S. DeWeese Co. v. Hughes-Treitler Mfg. Corp., 881 S.W.2d 638, 644 (Mo.App.E.D.1994). When a contract is ambiguous, extrinsic evidence may be used to resolve the ambiguity. Id.

[264]*264At trial, Kingston presented evidence that it did not see or receive Sheet Number E-l dated October 8, 1987 until after the subcontract was signed and work begun. Without that sheet, witnesses said it would be impossible to bid the lighting system.

Further, after the work began, Barken asked Kingston to bid the parking lot lighting. Kingston then was furnished Sheet Number E-l dated October 8, 1987.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bray v. Sexton
534 S.W.3d 418 (Missouri Court of Appeals, 2017)
Fru-Con Construction Corp. v. KFX, Inc.
153 F.3d 1150 (Tenth Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
901 S.W.2d 260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-electric-inc-v-wal-mart-properties-inc-moctapp-1995.