Kingsley Arms Inc. v. Kirchhoff-Consigli Constr. Mgt., LLC

CourtNew York Supreme Court
DecidedApril 18, 2018
Docket2018 NYSlipOp 50611(U)
StatusPublished

This text of Kingsley Arms Inc. v. Kirchhoff-Consigli Constr. Mgt., LLC (Kingsley Arms Inc. v. Kirchhoff-Consigli Constr. Mgt., LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingsley Arms Inc. v. Kirchhoff-Consigli Constr. Mgt., LLC, (N.Y. Super. Ct. 2018).

Opinion



Kingsley Arms Inc., Plaintiff,

against

Kirchhoff-Consigli Construction Management, LLC and FEDERAL INSURANCE COMPANY, Defendants.




900117-15

APPEARANCES:
Mastropietro Law Group, PLLC
Attorneys for Plaintiff
(John Mastropietro and Eric W. Gentino, of counsel)
63 Franklin Street
Saratoga Springs, New York 12866

Hinckley, Allen & Snyder LLP
Attorneys for Defendants
(James J. Barriere and Nathan R. Sabourin, of counsel)
30 South Pearl Street, Suite 901
Albany, New York 12207
Richard M. Platkin, J.

Plaintiff Kingsley Arms Inc. ("Kingsley") commenced this commercial construction action in February 2015, seeking to recover $208,000 from defendant Kirchhoff-Consigli Construction Management, LLC ("Consigli") and Federal Insurance Company ("Federal").[FN1] The claim arises from remediation work that Consigli, the general contractor, directed Kingsley, a sub-contractor, to perform in or about September 2014.

Following the completion of extensive fact discovery, a trial was held before the undersigned on November 8, 9 and 13, 2017. The Court heard the testimony of nine witnesses and received about 50 documents into evidence. Post-trial briefing was completed on February 16, 2018. Based on the credible testimony and evidence adduced at trial, the Court hereby makes [*2]the following findings of fact and conclusions of law.



BACKGROUND

In December 2010, Consigli was awarded a contract with the State University Construction Fund ("SUCF") for the general construction services required to build a new business school at the SUNY Albany uptown campus ("Project") (Ex. A). As required by its prime contract, Consigli procured a payment bond for the protection of its subcontractors and suppliers (Ex. 7).

On March 28, 2011, Kingsley entered into a written subcontract with Consigli to perform the site work for the Project, including the installation of about 920 feet of underground stormwater drainage piping (see Ex. 4 ["Subcontract"]). All work, labor and materials furnished by Kingsley pursuant to the Subcontract were to be "in complete accordance with the General Construction Documents" (id., article 1[A]), including the specifications prepared by SUCF's design consultant, Watts Architecture & Engineering ("Watts") (see Ex. 1). Kingsley guaranteed its work from defects in materials or workmanship for a period of one year from final acceptance (Subcontract, article 10).

In or about Spring 2013, flooding was discovered in one of the buildings adjacent to the Project site. SUCF investigated and discovered that a section of the new pipe had become deformed. After a series of discussions between the parties, Consigli directed Kingsley to repair the damaged pipe, and Kingsley complied ("2013 Repair").[FN2]

In the Summer of 2014, after the Project was completed, a routine video inspection of the drainage system revealed that a different segment of pipe was not installed at the specified slope and that another portion of the pipe had failed. SUCF's engineer notified Consigli of the problems on July 29, 2014 (Ex. 13); SUCF directed Consigli to replace the failed pipe on August 12, 2014 (Ex. 14); and Consigli issued the same directive to Kingsley on August 25, 2014 (Ex. 15).

Kingsley took the position, with support from Consigli, that the defects observed on video inspection were caused by the over-pressurization of the drainage system, which resulted from the designer's failure to properly account for the volume of stormwater draining through the system (Exs. 20-21). To preserve its rights and remedies against SUCF, Consigli submitted a notice of claim and verified statement on August 18, 2014 (Exs. 17 and 18).

SUCF was unconvinced by Kingsley and Consigli's over-pressurization theory and, instead, believed that the drainage system had not been properly installed. Representatives of SUCF, Consigli and Kingsley met to discuss the issue, and they ultimately agreed that the damaged section of pipe would be excavated and inspected, and a determination as to responsibility for the remediation costs would be made based on the results of the inspection.

The defective pipe was excavated and replaced in September 2014 ("2014 Repair"). SUCF hired MJ Engineering and Land Surveying, P.C. ("MJ Engineering") to observe this work and report on the condition of the existing system (see Ex. 25 ["MJ Report"]). The system's designer, Watts, also observed the remediation work and issued a report to SUCF (Ex. K ["Watts [*3]Report"]).

In total, seven sections of 15-inch diameter drainage pipe were replaced. Each section was a continuous 20-foot pipe, except for the seventh section, which had been field spliced by Kingsley. Thomas Bayly, a founder and vice-president of Kingsley who served as its Project superintendent, testified that this section of pipe had been struck by an excavator during installation, and Kingsley made a field splice to replace the damaged portion.

After reviewing the reports of its consultants, SUCF determined that the damaged pipe had not been installed in accordance with the plans and specifications and, therefore, refused to pay for the remedial work. Consigli adopted a similar position, while preserving its rights against SUCF in the event that the design of the system were determined to be defective (see Exs. 15, 19; see generally Transcript, pp. 337-342).



ANALYSIS

Kingsley contends that the remedial work performed in September 2014 resulted from a defective design of the drainage system and was not attributable to any deficiencies in its installation of the system. Consigli disagrees, arguing that Kingsley did not install the stormwater drainage system in accordance with applicable specifications and that Kingsley failed to prove that the design of the drainage system was defective.

For the reasons that follow, the Court concludes that Kingsley has neither demonstrated its own compliance with the Subcontract (including the design specifications) nor proven its claim of a defective design by a preponderance of the credible evidence.[FN3]



A. Kingsley's Performance of the Work

The Court finds that Kingsley has failed to demonstrate its own compliance with the Subcontract as to at least three issues highly pertinent to its claim.



1. The Field Splice

The proof at trial establishes that Kingsley did not comply with the Subcontract in responding to the accidental damage of a 20-foot section of pipe during the sewer installation.

Thomas Bayly testified that Kingsley cut out the damaged segment of pipe and "spliced" in a new segment. However, the specifications clearly required Kingsley to "[r]eplace defective piping using new materials" (Ex. 1, Section 33 41 00 [Storm Utility Drainage Piping], § 3.10 [A] [3]). Further, Thomas Bayly acknowledged that he did not consult the pipe manufacturer's recommendations before deciding to perform the field splice rather than replace the damaged pipe.

With respect to the manner in which the splice was performed, Kingsley emphasizes that visual inspection of the pipe following excavation showed that the splice appeared to be intact with the metal bands still in place (see Exs. 27B, 27C).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Village of Endicott v. Parlor City Contracting Co.
51 A.D.2d 370 (Appellate Division of the Supreme Court of New York, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Kingsley Arms Inc. v. Kirchhoff-Consigli Constr. Mgt., LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingsley-arms-inc-v-kirchhoff-consigli-constr-mgt-llc-nysupct-2018.