King v. Illinois Commerce Commission

351 N.E.2d 589, 39 Ill. App. 3d 648, 1976 Ill. App. LEXIS 2625
CourtAppellate Court of Illinois
DecidedJune 24, 1976
DocketNo. 12988
StatusPublished

This text of 351 N.E.2d 589 (King v. Illinois Commerce Commission) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King v. Illinois Commerce Commission, 351 N.E.2d 589, 39 Ill. App. 3d 648, 1976 Ill. App. LEXIS 2625 (Ill. Ct. App. 1976).

Opinion

Mr. PRESIDING JUSTICE TRAPP

delivered the opinion of the court:

Plaintiffs appeal from the order of the trial court which found that the Illinois Commerce Commission (herein Commission), had statutory authority to enter its supplemental order in Docket No. 56742 and 57247, that the Commission made adequate findings to support the supplemental order, that the findings of the Commission were supported by the evidence and not against the manifest weight of the evidence. The court further found that there was a partial rescission of a lawful certificate (of necessity and convenience) issued by the Commission, and that the order at issue was not a certificate of convenience and necessity for a new or different facility.

The record incorporates an extended sequence of pleadings and proceedings before the Commission culminating in the order on appeal. In October, 1971, pursuant to a petition of the Illinois Power Company (herein Illinois), docketed No. 56742, the Commission granted a certificate of convenience and necessity for a 345 kv electric transmission line extending from Latham in Logan County, to Rising in Champaign County and to Sidney in the same county. From the point of origin the line extended 48 miles to Rising where an appropriate station was to be constructed.

Lesser transmission lines originating at Rising were to be a source of additional power to Champaign-Urbana. From Rising the transmission line extended some 20 miles to Sidney to be connected to an existing station.

So authorized and constructed the transmission line would be a source of additional power for the Sidney station, and was planned as a facility for interconnection with other sources so that service could be maintained by switching to the associated sources upon the occurrence of outages in the Illinois system. The findings and evidence supporting such original certificate are not challenged.

Subsequently, in March 1972, pursuant to a petition filed as Docket No. 57247, an order of the Commission authorized Illinois to acquire right-of-way with authority to proceed under eminent domain and to construct the line.

Plaintiffs were granted leave to intervene in the latter petition. The issues raised by plaintiffs were an alleged failure to negotiate in good faith as to the type of pole structure and the placing of such on the lands of the respective plaintiffs. The land so concerned lies upon the Latham-Rising section of the line.

At the hearings held on the petition, Docket No. 57247, counsel for Illinois advised that the University of Illinois claimed that the Rising-Sidney segment of the line might interfere with the safety requirements of its Willard Airport, and that it would not proceed with the construction on such segment until the further order of the Commission.

Thereafter, in August, the trustees of the University filed a petition for leave to intervene and for reconsideration in both Docket No. 56742, the proceedings for a certificate of necessity, and Docket No. 57247, the order for construction. The petition set out the factor of hazard arising from the construction of the transmission lines (the Rising-Sidney source) “in the immediate vicinity" of the Willard Airport, and that such construction would unduly restrict the future growth and expansion of that facility. Such petition prayed reconsideration of the certificate of necessity in so far as it pertained to the construction of the line in such “immediate vicinity.” In January, 1973, the county board of Champaign filed a similar petition with comparable allegations. Neither are parties to this appeal.

In September, 1972, in Docket No. 57247, the Commission authorized and directed Illinois to proceed and acquire right-of-way and to construct the Latham-Rising, but directed that no construction in any part of the Rising-Sidney segment be commenced without further approval of the Commission. Such order further directed that as to Docket No. 56742, “[A]s it relates to the Rising-Sidney segment of the electric transmission line be reopened for further consideration.”

As to Docket No. 57247, plaintiff, King, filed a motion to reconsider such order. That motion was directed to the sufficiency of showing the necessity for eminent domain. The motion was denied. We find no similar motion as to plaintiffs, Timmons.

In January 1973, Illinois filed its petition in the reconsolidated proceedings reciting the procedural development and status of the case, and that in Docket No. 57247, the Commission had found inter alia that Illinois could defer construction of the Rising segment until further approval of the Commission. Such petition alleged that the construction of the Latham-Rising segment will enable the supply of immediate electrical needs and that interconnection with other systems through the Rising-Sidney segment could be delayed temporarily while a new route or interconnection was designed and obtained. The petition alleged that Illinois would seek a new route for a transmission line to serve the purposes of interconnection with other sources.

The petition prayed that upon such record that the Commission find that the public convenience and necessity does not require the immediate construction and operation of the Rising-Sidney segment as originally proposed and order:

“[T]hat the Commission’s Order and Certificate of Public Convenience and Necessity granted on October 20, 1971, in Docket No. 56742, be altered and modified by rescinding that portion of said Order and Certificate authorizing, ordering and directing petitioner to construct, operate and maintain the Rising to Sidney portion of the proposed line and providing that such Order and Certificate, as so altered and modified, shall continue in full force and effect."

It further prayed that the entry of such order is without prejudice to the right of Illinois to make such subsequent application for an Order and Certificate of Convenience and Necessity to operate and maintain a transmission line on and over a route other than that originally certificated between Rising and Sidney for interconnection purposes with the Eastern United States.

The supplemental order and certificate at issue entered in the consolidated proceedings recited that the evidence show that the interconnection function served by the Rising-Sidney segment can be temporarily deferred, that action was being taken to discover alternate routes for such interconnection and that there was a continuing need for the electric power traversing the Latham-Sidney segment which remains the feasible and practical route, and that the evidence supports such determinations which are adopted as finding of fact.

The order further finds that the Rising-Sidney segment over the route heretofore proposed is not presently required for public convenience and necessity as previously ordered in Docket No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagle Bus Lines, Inc. v. Illinois Commerce Commission
119 N.E.2d 915 (Illinois Supreme Court, 1954)
Brinker Trucking Co. v. Illinois Commerce Commission
166 N.E.2d 18 (Illinois Supreme Court, 1960)
Union Electric Co. v. Illinois Commerce Commission
235 N.E.2d 604 (Illinois Supreme Court, 1968)
Black Hawk Motor Transit Co. v. Illinois Commerce Commission
76 N.E.2d 478 (Illinois Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
351 N.E.2d 589, 39 Ill. App. 3d 648, 1976 Ill. App. LEXIS 2625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-v-illinois-commerce-commission-illappct-1976.