King Philip Mills v. Samuel Slater & Sons

12 R.I. 82, 1878 R.I. LEXIS 26
CourtSupreme Court of Rhode Island
DecidedMarch 2, 1878
StatusPublished

This text of 12 R.I. 82 (King Philip Mills v. Samuel Slater & Sons) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King Philip Mills v. Samuel Slater & Sons, 12 R.I. 82, 1878 R.I. LEXIS 26 (R.I. 1878).

Opinion

Potter, J.

The declaration charges that the defendants, on the 28th January, 1873, in consideration of the promise of the plaintiffs to sell to the defendants a certain quantity of jaconets, viz.: each lot which they should produce from 400 looms before July 1 (describing the quality, &e.), each lot to be of 1,000 pieces, undertook and promised to pay therefor *83 cash 7^ cents per yard, 30 days from the delivery of each lot, and the plaintiffs aver that they proceeded to employ said 400 looms, &c., and on the 19th day of May were ready and willing, and offered to deliver 1,000 pieces, &c., conforming to agreement, which defendants refused to accept; and the plaintiffs make similar averments as to subsequent lots of 1,000 pieces each for May 21, 27, June 3, 5, 11, 14, 19, 21, 26, 30, and July 3, being the products of said 400 looms between the dates, and alleging damages ; and in another count defendants aver that on the-■ day of-A. D. 1873, the defendants gave notice to plaintiffs that they should thereafter refuse to accept said goods, &c., &c.

The contract in this case was, after some introductory verbal negotiations, concluded by letter. On January 28, 1873, Mr. Chace, a director of the plaintiff company, wrote to Samuel Slater & Sons that he was instructed by the treasurer to accept the offer of cents, 30 days from the delivery of each lot of jaconets the plaintiffs should produce on 400 looms before July 1, of specified width, weight, &c. The mill was expected to be in full operation by April 1, but they would begin to deliver sooner if they could, and they expected to do so.

The same day Samuel Slater & Sons replied to Mr. Chace, recapitulated the above, and said, “ it is also understood that the maximum production is to be reached as soon as possible, and steadily maintained, unavoidable interruptions only excepted, until the completion of the contract; . . . . and to be delivered in Providence in lots of $fl,000 pieces each ; ” and they request a confirmation of the sale from the treasurer. January 31 the treasurer acknowledged the receipt of a copy of Chace’s letter, and of the letter of Samuel Slater & Sons, and ratifying “ the above described contract,” stated, “ we will commence to deliver the goods as soon as we possibly can, and will reach the maximum production as soon as possible.”

The price agreed on was to be paid in thirty days after the delivery of each lot.

/It appears in evidence that two lots of goods of about the specified quantity of 1,000 pieces were sent to defendants on or before April 17, which, it is not disputed, were deficient in width and other particulars ; that April 17 the defendants telegraphed to the plaintiffs that the goods were deficient in width *84 and weight, and to send no more until right; that April 18 they wrote to plaintiffs to the same effect, that they needed an immediate supply, and inquiring “ what are we to expect; ” that April 19 the plaintiffs wrote that they would get new reeds, that they had measured the width with a tape, &c., &c)

And April 21 the defendants wrote to the plaintiffs that as they must have an immediate supply or stop their mill, the contract was terminated. The defendant’s agent testified that as soon as they found that the plaintiffs had such reeds and no others they gave this notice to terminate the contract.

It is not disputed that the goods were to be delivered in lots of 1,000 pieces each; but it _is contended by the plaintiffs’ counsel that it would have been a compliance with the contract if all had been delivered in June. This is not the construction which would strike the mind of an ordinary intelligent business man as being the proper one, and we do not think it is the correct view. We think it is plain that the deliveries were to be made as the goods were manufactured. By the letters, the plaintiffs were to begin to deliver as soon as possible, theirs being a new mill, and were to reach the maximum production of the 400 looms as soon as possible. The defendants were engaged in finishing _this_sort, of goods for the market, and bought these goods to supply their mills for that purpose; and two witnesses say that it was not a common style of goods, and there were but few in market. Both parties were manufacturers and in a manufacturing community, and might well be supposed to know something of each other’s business and wants.

We think the reasonable construction of the letters is that the defendants were to have the whole production of 400 looms, deliveries to commence as soon as possible, and to be continued in lots of 1,000 each as fast as produced.

The question then arises, Were the defendants justified in rescinding the contract ? We think they were. The first two lots were, without dispute, not according to the contract. The width was material. The plaintiffs had made the mistake as to the width from measuring it with a tape. They were also using a kind of reeds unsuitable for the manufacture, and there could be no reliance on the future product.

The plaintiffs having failed in the first deliveries, the defend *85 ants were„not bound to take the goods offered during the latter part of the period. To bold that where successive deliveries of goods of certain qualities and quantities are to be made at successive periods, the purchaser, while he may reject those not of the quality, is bound to take those which are of the agreed quality to the end of the time, would introduce an element of uncertainty into such matters highly injurious to the interests of a business community. The purchaser may, indeed, choose not to rescind, and to accept them; and so he may accept even those not of the quality ; and if so he must pay for them what they are worth. And the case would be very different, if in a contract to be paid for in one sum at the last delivery, the seller, having complied with all the previous deliveries, failed in some of the latter ones. In such a case the purchaser would have received a benefit from the contract, and it would be right that he should pay for the benefit received.

It is to be observed here, that the plaintiffs do not allege in their declaration that they began to deliver the jaconets as soon as possible, nor that the maximum production was reached as soon as possible ; nor do they definitely allege that the whole product of 400 looms was at any one time ever sent to the defendant. And there is no positive evidence that the whole number of 400 looms was ever put upon this contract. And passing over entirely the first two deliveries of imperfect goods, they proceed to allege a readiness to deliver under the contract on the 19th of May, and so on.

They do not allege a performance on their part of the agreement they prove.

The purchasers were not bound to take any goods not according to the contract, as the two first lots of jaconets were; and the only question is, When, after failure on the part of the vendors, have the purchasers a right to rescind and look elsewhere for their supplies ? In this respect each case must depend on its own circumstances. To hold that the purchaser must receive such lots as are of the right quality, and that for the periods when they are not so he must supply himself elsewhere, and sue for his damages, or claim to deduct them, would introduce confusion into business.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

President of the Bank of Columbia v. Hagner
26 U.S. 455 (Supreme Court, 1828)

Cite This Page — Counsel Stack

Bluebook (online)
12 R.I. 82, 1878 R.I. LEXIS 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-philip-mills-v-samuel-slater-sons-ri-1878.