King Hill Irrigation District v. Craster Farm & Orchard Co.

221 P. 839, 37 Idaho 89, 1923 Ida. LEXIS 216
Idaho Supreme Court·Decided April 23, 1923·Published·Cited by 4 cases

Opinions

DUNN, J.

— In this . proceeding, which was commenced in the district court af Elmore county, appellants are resisting the assessment of $65 per acre upon their lands which was levied by the directors of the King Hill Irrigation District as benefits to said lands from the expenditure of a large [93] amount of money, approximately $1,000,000, by the government of the United States in rebuilding, enlarging and improving certain portions of the canal system through which the lands of said irrigation district receive water.

King Hill Irrigation District embraces lands that were .formerly included in the King Hill Carey Act project. The reclamation of this project was undertaken pursuant to a contract made by the state of Idaho with the King Hill Irrigation and Power Campany. The estimated cost of the reclamation of the lands included in the project was $600,000, but after the expenditure of this sum and a million dollars besides it was found that the system was so imperfect that the state was unable to show that an ample supply of water had been actually furnished to reclaim the lands embraced in the project and therefore was unable to secure patents for the land claimants, including appellants herein. The King Hill Irrigation and Power Company was without further means to fulfill its contract. It had mortgaged to the Continental and Commercial Trust and Savings Bank its interest in the canal system constructed by it, its water appropriation, its contract with the state of Idaho and its lien upon the water right contracts and lands of the contract holders who had not paid up in full, for funds with which to construct the irrigation system, and having defaulted in its payment of interest the mortgage was foreclosed and all of the construction company’s interest in the mortgaged property, which was a lien thereon, was sold to the state of Idaho for $30,000. The deed conveying this interest to the state of Idaho was dated March 14, 1914. The appellants had paid in full for their water rights and thereby became the owners of such water rights and of a proportionate interest in the canal system. Their rights were therefore not affected by the foreclosure proceedings against the construction company.

In a memorial in 1915 the state legislature urged that Congress take over and complete the irrigation system because the same had not been completed in such a substantial manner as to entitle the state to patent to the land there[94] under and at the same session appropriated $26,000 to assist in the maintenance of the irrigation system and furnishing water to settlers on the project. A like appropriation was made at the succeeding session of the legislature. While these appropriations by the state gave some temporary relief there was no hope that any assistance in the way of completing the canal system so as to reclaim the lands under it and make it possible to obtain patents could come from any other source than -the federal government. The situation of the settlers was desperate in the extreme. Appellants, though their water rights were paid for, were as helpless as any other owners in the matter of obtaining water to insure crops and thus make possible title to the lands claimed by them. Appellant company was the owner of a water right at the head of the eanál system, and of 1,200 acres of arid land near the lower end of the system at least 30 miles from the water, and the owner of one-twelfth of the intervening canal system which ■ was utterly inefficient to convey the water to the land. The other -appellants, with smaller interests respectively, were in a similar situation. The colossal proportions of the undertaking necessary to save the homes of the settlers as well as appellant company’s investment of $78,600 and the investments of the other appellants may be easily understood by the sum asked and received from the federal government, $1,000,000.

In this situation the irrigation district, which is respondent in this action, was organized by appellant company and the settlers. At an election held in September, 1917, authority was given to said irrigation district to enter into a contract with the United States for the reconstruction, repair and improvement of the irrigation works for the irrigation of the lands of the district. This proposition was adopted by more than a two-thirds vote of the settlers and was approved by decree of the district court. Pursuant to this vote the contract was entered into by the irrigation district, the state of Idaho and the United States government, and ..as a result of said contract all of the interest of the state of Idaho in said, canal system, which was a lien on [95] approximately an undivided eleven-twelfths of the whole, was conveyed to the government of the United States.

Pursuant to this contract work was begun by the government about March, 1918, and prosecuted apparently with diligence. Assessments for benefits were made by the board of directors of the Irrigation District, notice given to the settlers, no objection made to such assessments and petition for confirmation thereof was filed in the district court of Elmore county, October 1, 1918; an amended petition was filed November 26, 1918. The answer of appellant company was filed May 21, 1919, and this constitutes the first objection appellant company offered to the operations of the irrigation district, when a large part of $1,000,000 had been expended for its benefit and that of the other land owners.

Manifestly the conveyance to the United States was an attempt to comply with the act of Congress of June 17, 1902 (32 Stat. 388), and the act of Congress of Feb. 21, 1911 (36 Stat. 925), both of which are referred to in the contract and require, in such contracts as this, that title to the irrigation works be vested in the federal government. While the interest of the state was only a lien, it having simply succeeded to the construction company’s interest, it fairly appears that all parties regarded the state as having title to the canal system. The contract voted on and approved by the settlers on the project, after due notice to appellant company and all others interested and without opposition from appellant company, contained the following:

Free access — add to your briefcase to read the full text and ask questions with AI

King Hill Irrigation District v. Craster Farm & Orchard Co., 221 P. 839, 37 Idaho 89, 1923 Ida. LEXIS 216 (Idaho 1923).

221 P. 839 (King Hill Irrigation District v. Craster Farm & Orchard Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McDonald v. Pritzl
93 P.2d 11 (Idaho Supreme Court, 1939)
Walker v. Hughes
13 P.2d 249 (Idaho Supreme Court, 1932)