/ Fl LE IN CLERKS OFFICE lllJI'R9&E COURT, STATE OF WASHINQ10N DATE JUN 2 7 2013 "Ykt.t. PREME COURT OF THE STATE OF WASHINGTON
KING COUNTY, DEPARTMENT ) OF DEVELOPMENT AND ) No. 87514-6 ENVIRONMENTAL SERVICES, ) an executive agency, ) EnBanc ) Petitioner, ) ) v. ) ) KING COUNTY, a Washington ) municipal corporation, JEFFREY L. ) SPENCER, a single man, and ) RONALD A. SHEAR, a single man, ) ) Respondents. ) ) Filed JUN 272013
C. JOHNSON, J.-This land use case requires us to determine how the King
County Code provisions allow uses to vest as nonconforming uses. This case began
as a challenge to an agency order declaring the use of the property was not
compliant with King County zoning ordinances. The applicants' challenge was
based on the assertion that the use was established before revisions to the zoning
ordinances characterized the use as nonconforming and, thus, requiring a permit.
This case also presents the issue of what effect a nonpermitted activity has
on a later claim to a preexisting use when a permit was required for the activity No. 87514-6
asserted as support for a preexisting use. The hearing examiner found for the
landowner on all relevant issues, but the decision was reversed by the superior
court. The Court of Appeals reversed the superior court, and we now reverse the
Court of Appeals and hold that the landowner's use was not established within the
meaning of the King County Code.
FACTS AND PROCEDURAL HISTORY
The 10-acre parcel of land at issue in this appeal lies in the Green River
Valley and is zoned agricultural. The landowner, Jeffrey Spencer, allowed Ronald
Shear, who operates a business (BRC), which processes organic materials into
animal bedding and fuel, to rent the property. 1
In 2003, Shear was operating a similar processing facility on a one-acre
parcel near Spencer's parcel. In October, the two entered into an oral "lease"
agreement whereby Shear began bringing equipment and materials onto Spencer's
parcel for later processing. This operation fit under the definition of an "interim
recycling facility" under the then-existing King County Code and required no use-
specific permitting. Shear's activities on the parcel increased throughout 2004,
although no actual grinding or processing had begun. Then, in September 2004,
1 For ease of reference, these parties will all be referred to as Shear unless otherwise noted.
2 No. 87514-6
King County amended its code to require permitting for operations such as Shear's,
classifying them as "materials processing facilities." 2 There is no dispute that
Shear's current operations constitute a materials processing facility under the code.
Nor is it disputed that actual grinding of the organic materials had not commenced
before the code revisions. However, the hearing examiner did find that Shear's
operations were continually expanding during the time leading up to the zoning
revisions and that the business required three stages for full implementation: site
preparation, grinding of raw materials, and transfer of those materials off site. The
hearing examiner also found that prior to the zoning change, "all of the essential
first-stage site preparation activities were underway." Clerk's Papers (CP) at 31.
Shortly after the zoning change, in late 2004 or early 2005, Shear began
actual grinding of organic materials. In response to complaints from a nearby
landowner, the Department of Development and Environmental Services (DDES)
began to investigate Sheaes operations. Apparently, DDES made multiple
informal contacts before ultimately filing an administrative notice and order on
October 9, 2006. The administrative order found two violations: the operation of a
2 The King County Code defines a "[m]aterials processing facility" as "[a] site or establishment, not accessory to a mineral extraction or sawmill use, that is primarily engaged in crushing, grinding, pulverizing or otherwise preparing earth materials, vegetation, organic waste, construction and demolition materials or source separated organic materials and that is not the final disposal site." King County Code (KCC) 21A.06.742.
3 No. 87514-6
materials processing facility in a critical area without permit and grading in critical
areas (flood hazard area and wetlands) without proper permitting.
Shear appealed the administrative order, setting off long and contentious
proceedings not relevant here. On January 28, 2010, the hearing examiner filed his
report and decision, which was largely (but not completely) in favor of Shear. In
relevant part, the hearing examiner interpreted the following language of the King
County Code as expressly recognizing that preexisting uses could vest even if not
in full operation:
21A.06.800 Nonconformance. Nonconformance: any use, improvement or structure established in conformance with King County rules and regulations in effect at the time of establishment that no longer conforms to the range of uses permitted in the site's current zone or to the current development standards of the code due to changes in the code or its application to the subject property.
21A.08.010 Establishment of uses. The use of a property is defined by the activity for which the building or lot is intended, designed, arranged, occupied, or maintained. The use is considered permanently established when that use will or has been in continuous operation for a period exceeding sixty days. A use which will operate for less than sixty days is considered a temporary use, and subject to the requirements ofK.C.C. 21A.32 of this title. All applicable . requirements of this code, or other applicable state or federal requirements, shall govern a use located in unincorporated King County.
KING COUNTY CODE (KCC) 21A.06.800; KCC 21A.08.010. Thus, the hearing
examiner reasoned, Shear's use as a materials processing facility could be a
4 No. 87514-6
preexisting use despite the fact that actual grinding had not begun prior to the
zoning change. The hearing examiner also found that the King County Code
required further actions by the county to designate flood hazard areas, and because
it had yet to complete the process, the code contained an unenforceable flood
hazard standard. Finally, the hearing examiner found that Shear had engaged in
unlawful grading, albeit not in a critical area. 3
Importantly, the hearing examiner recognized that Shear's use had and
would likely continue to expand and required Shear to obtain a conditional use
permit for any expansion. He determined that Shear's use as of September 2004
(the month King County amended its code) was the baseline level of permitted use.
Any expansion after that date would require a conditional use permit. However,
given the contentious nature of the proceedings, the hearing examiner also
recognized that DDES might abuse the conditional use permit process and imposed
several restrictions applicable to the permitting process. He ruled that DDES was
not allowed to use the permit process to directly or indirectly prohibit a viable
materials processing facility. Moreover, subject to small exceptions, it could not
require any further studies on the wetland or flood hazard area issues.
----------------- 3 There were also findings related to a wetlands issue, but that issue is not part of the current appeal.
5 No. 87514-6
Free access — add to your briefcase to read the full text and ask questions with AI
/ Fl LE IN CLERKS OFFICE lllJI'R9&E COURT, STATE OF WASHINQ10N DATE JUN 2 7 2013 "Ykt.t. PREME COURT OF THE STATE OF WASHINGTON
KING COUNTY, DEPARTMENT ) OF DEVELOPMENT AND ) No. 87514-6 ENVIRONMENTAL SERVICES, ) an executive agency, ) EnBanc ) Petitioner, ) ) v. ) ) KING COUNTY, a Washington ) municipal corporation, JEFFREY L. ) SPENCER, a single man, and ) RONALD A. SHEAR, a single man, ) ) Respondents. ) ) Filed JUN 272013
C. JOHNSON, J.-This land use case requires us to determine how the King
County Code provisions allow uses to vest as nonconforming uses. This case began
as a challenge to an agency order declaring the use of the property was not
compliant with King County zoning ordinances. The applicants' challenge was
based on the assertion that the use was established before revisions to the zoning
ordinances characterized the use as nonconforming and, thus, requiring a permit.
This case also presents the issue of what effect a nonpermitted activity has
on a later claim to a preexisting use when a permit was required for the activity No. 87514-6
asserted as support for a preexisting use. The hearing examiner found for the
landowner on all relevant issues, but the decision was reversed by the superior
court. The Court of Appeals reversed the superior court, and we now reverse the
Court of Appeals and hold that the landowner's use was not established within the
meaning of the King County Code.
FACTS AND PROCEDURAL HISTORY
The 10-acre parcel of land at issue in this appeal lies in the Green River
Valley and is zoned agricultural. The landowner, Jeffrey Spencer, allowed Ronald
Shear, who operates a business (BRC), which processes organic materials into
animal bedding and fuel, to rent the property. 1
In 2003, Shear was operating a similar processing facility on a one-acre
parcel near Spencer's parcel. In October, the two entered into an oral "lease"
agreement whereby Shear began bringing equipment and materials onto Spencer's
parcel for later processing. This operation fit under the definition of an "interim
recycling facility" under the then-existing King County Code and required no use-
specific permitting. Shear's activities on the parcel increased throughout 2004,
although no actual grinding or processing had begun. Then, in September 2004,
1 For ease of reference, these parties will all be referred to as Shear unless otherwise noted.
2 No. 87514-6
King County amended its code to require permitting for operations such as Shear's,
classifying them as "materials processing facilities." 2 There is no dispute that
Shear's current operations constitute a materials processing facility under the code.
Nor is it disputed that actual grinding of the organic materials had not commenced
before the code revisions. However, the hearing examiner did find that Shear's
operations were continually expanding during the time leading up to the zoning
revisions and that the business required three stages for full implementation: site
preparation, grinding of raw materials, and transfer of those materials off site. The
hearing examiner also found that prior to the zoning change, "all of the essential
first-stage site preparation activities were underway." Clerk's Papers (CP) at 31.
Shortly after the zoning change, in late 2004 or early 2005, Shear began
actual grinding of organic materials. In response to complaints from a nearby
landowner, the Department of Development and Environmental Services (DDES)
began to investigate Sheaes operations. Apparently, DDES made multiple
informal contacts before ultimately filing an administrative notice and order on
October 9, 2006. The administrative order found two violations: the operation of a
2 The King County Code defines a "[m]aterials processing facility" as "[a] site or establishment, not accessory to a mineral extraction or sawmill use, that is primarily engaged in crushing, grinding, pulverizing or otherwise preparing earth materials, vegetation, organic waste, construction and demolition materials or source separated organic materials and that is not the final disposal site." King County Code (KCC) 21A.06.742.
3 No. 87514-6
materials processing facility in a critical area without permit and grading in critical
areas (flood hazard area and wetlands) without proper permitting.
Shear appealed the administrative order, setting off long and contentious
proceedings not relevant here. On January 28, 2010, the hearing examiner filed his
report and decision, which was largely (but not completely) in favor of Shear. In
relevant part, the hearing examiner interpreted the following language of the King
County Code as expressly recognizing that preexisting uses could vest even if not
in full operation:
21A.06.800 Nonconformance. Nonconformance: any use, improvement or structure established in conformance with King County rules and regulations in effect at the time of establishment that no longer conforms to the range of uses permitted in the site's current zone or to the current development standards of the code due to changes in the code or its application to the subject property.
21A.08.010 Establishment of uses. The use of a property is defined by the activity for which the building or lot is intended, designed, arranged, occupied, or maintained. The use is considered permanently established when that use will or has been in continuous operation for a period exceeding sixty days. A use which will operate for less than sixty days is considered a temporary use, and subject to the requirements ofK.C.C. 21A.32 of this title. All applicable . requirements of this code, or other applicable state or federal requirements, shall govern a use located in unincorporated King County.
KING COUNTY CODE (KCC) 21A.06.800; KCC 21A.08.010. Thus, the hearing
examiner reasoned, Shear's use as a materials processing facility could be a
4 No. 87514-6
preexisting use despite the fact that actual grinding had not begun prior to the
zoning change. The hearing examiner also found that the King County Code
required further actions by the county to designate flood hazard areas, and because
it had yet to complete the process, the code contained an unenforceable flood
hazard standard. Finally, the hearing examiner found that Shear had engaged in
unlawful grading, albeit not in a critical area. 3
Importantly, the hearing examiner recognized that Shear's use had and
would likely continue to expand and required Shear to obtain a conditional use
permit for any expansion. He determined that Shear's use as of September 2004
(the month King County amended its code) was the baseline level of permitted use.
Any expansion after that date would require a conditional use permit. However,
given the contentious nature of the proceedings, the hearing examiner also
recognized that DDES might abuse the conditional use permit process and imposed
several restrictions applicable to the permitting process. He ruled that DDES was
not allowed to use the permit process to directly or indirectly prohibit a viable
materials processing facility. Moreover, subject to small exceptions, it could not
require any further studies on the wetland or flood hazard area issues.
----------------- 3 There were also findings related to a wetlands issue, but that issue is not part of the current appeal.
5 No. 87514-6
DDES filed a timely appeal under the Land Use Petition Act (LUP A),
chapter 36.70C RCW. The King County Superior Court reversed the hearing
examiner on all issues. The court held that the hearing officer's determination that
actual grinding had not occurred "preclude[ d]" his finding of a nonconforming use
because the code required a use to be "'in operation'" for 60 days in order to be
established. CP at 664. It also held that the code did contain an enforceable flood
hazard area standard and that the hearing examiner acted outside of his jurisdiction
in imposing conditions. Shear timely appealed this decision, and in a published
decision, the Court of Appeals, Division One reversed the superior court and
reinstated the hearing examiner's decision. King County Dep 't ofDev. & Envtl.
Servs. v. King County, 167 Wn. App. 561, 273 P.3d 490 (2012). We granted
discretionary review. King County Dep 't ofDev. & Envtl. Servs. v. King County,
175 Wn.2d 1009,287 P.3d 594 (2012).
ANALYSIS
LUP A sets forth six standards for relief from an administrative land use
decision. RCW 36.70C.130. As relevant here, relief will be granted if the hearing
examiner's decision was "an erroneous interpretation of the law, after allowing for
such deference as is due the construction of a law by a local jurisdiction with
expertise." RCW 36.70C.130(1)(b). An appellate court stands in the same shoes as
6 No. 87514-6
the superior court and reviews the administrative record. Isla Verde Int 'l Holdings,
Inc. v. City of Camas, 146 Wn.2d 740, 751,49 P.3d 867 (2002). Alleged errors of
law are reviewed de novo and questions of fact are reviewed for substantial
evidence. City of University Place v. McGuire, 144 Wn.2d 640, 647, 30 P.3d 453
(2001).
Nonconforming Use
Generally, a nonconforming use is a use that "lawfully existed" prior to a
change in regulation. Despite that the use may no longer be permitted, it is allowed
to continue due to the fairness and due process concerns of the landowner. Rhod-A-
Zalea & 35th, Inc. v. Snohomish County, 136 Wn.2d 1, 6, 959 P.2d 1024 (1998).
The doctrine is "intended to protect only those uses which were legally established
before" the change in regulation. 1 ROBERT M. ANDERSON, AMERICAN LAW OF
ZONING § 6.11 (Kenneth H. Young ed., 4th ed. 1996). The landowner has the
burden to prove that (1) the use existed prior to the contrary zoning ordinance, (2)
the use was lawful at the time, and (3) the applicant did not abandon or discontinue
the use for over a year prior to the relevant change. McMilian v. King County, 161
Wn. App. 581, 591, 255 P.3d 739 (2011).
The analytical focus of the dispute here centers on the provisions and
language of the King County Code, which regulates zoning and the allowable uses
7 No. 87514-6
of land. The parties disagree over the interpretation of several sections of the King
County Code.
The first disputed section of the code defines a nonconforming use as "any
use, improvement or structure established in conformance with King County rules
and regulations in effect at the time of establishment that no longer conforms to the
range of uses permitted in the site's current zone." KCC 21A.06.800 (emphasis
added). Importantly, the past-tense form of the word "establish" is used twice in
this provision in reference to the use, which shows that the use must already be
established in order to be considered a nonconforming use. As discussed below,
this approach tracts the analysis employed by our cases discussing preexisting
uses. See, e.g., Anderson v. Island County, 81 Wn.2d 312, 501 P.2d 594 (1972)
(finding no nonconforming use where landowner had intent to operate cement
hatching plant but had not actually begun operations).
Shear's argument, which the Court of Appeals found convincing, focuses on
another section ofthe code that provides, "The use of a property is defined by the
activity for which the building or lot is intended, designed, arranged, occupied, or
maintained." KCC 21A.08.010. Although these words, especially "'intended,"'
arguably suggest that prospective uses are allowed, this sentence is about
"'defin[ing]"' uses, not selecting a point in time at which they vest. Here, for
8 No. 87514~6
example, the hearing examiner found that Shear "intended, designed, arranged,
occupied, or maintained" the property in a manner that falls under the code's
definition of a "materials processing facility." Thus, because Shear intended to
operate a materials processing facility, that is the use he must prove was
established. However, this sentence in the code provides little guidance because it
says nothing about when a use is established but instead provides guidance as to
how to define a use in relation to activities occurring on the land, especially where
some activities might be unregulated for one use but regulated for another.
This interpretation is further confirmed by the next two sentences of the
code, which provide further guidance on defining the use-specifically, whether it
is temporary or permanent. These sentences state that a "use is considered
permanently established when that use will or has been in continuous operation for
a period exceeding sixty days. A use which will operate for less than sixty days is
considered a temporary use." KCC 21A.08.010. Shear focuses on the word "will"
to argue that prospective uses can be "established" within the meaning of the code.
As discussed above, however, this section is about defining uses, not about when
they are established. 4 As a condition precedent to determining whether a use is
------------- 4 We recognize that the section is entitled "Establishment of uses" but is in a separate chapter of the code than the definition of a "nonconforming use." In context, we read this section
9 No. 87514-6
permanent or temporary, that use must exist. A use exists when it is "established"
within the meaning ofKCC 21A.06.800. In this context, "will" speaks to existing
established uses that have not been in operation for 60 days but are expected to
continue for more than 60 days.
For example, suppose a landowner wanted to open a hotel and obtained
approval for all the necessary permitting before that use is subsequently prohibited.
The permit approval would "establish" the use even though occupation of the
facility may not have started, and the use would be a permanent use because it
"will" be in operation for more than 60 days. Similarly, in Shear's case, if he had
been fully processing the materials for 15 days, his use would have been
established within the meaning of the code and would have been permanent
because it eventually would have been in continuous operation for 60 days. But,
again, the code requires establishment as a' condition precedent to the creation of a
nonconforming use. Thus, we conclude that the "will" in KCC 21A.08.010 does
not have any bearing on when a nonconforming use is "established" but instead
refers to whether uses that are already "established" in accordance with KCC
21A.06.800 are considered "permanent" or "temporary." Because Shear had not
as related to establishing what the use is, not the point in time in which the use is "established" within the meaning ofKCC 21A.06.800.
10 No. 87514-6 ·
completed all three stages as determined by the hearing examiner, his use was not
established within the meaning of the code prior to the zoning change.
This interpretation of the code is also consistent with our case law applying
the nonconforming use doctrine. Nonconforming uses are disfavored, and we have
repeatedly held that the doctrine is a narrow exception to the State's nearly plenary
power to regulate land through its police powers. Consistent with the narrowness
of this doctrine, we held in Rhod-A-Zalea that a landowner does not "vest" the
entire code at the time the use is established, but that only the use itself is vested
and a landowner must still comply with subsequent changes to the land use code
not involving that specific use. Rhod-A-Zalea, 136 Wn.2d at 6-7. Thus, even where
a nonconforming use was lawfully established, the rights of a landowner may still
be limited to only what is required to protect the landowner's due process interests.
Nonetheless, the use must actually exist before it can be termed a "preexisting use"
and a due process right attaches to a landowner.
In another case, the landowner moved its gravel operations to a newly
purchased track of land with the intent of also moving its cement batching plant to
the same location. Several months later, the county amended the zoning code to
designate the land as residential. Soon thereafter, the landowner began construction
of a cement hatching plant. This court held that a nonconforming use did not exist
11 No. 87514-6
for the cement batching plant because that use did not precede the zoning change.
We stated that "mere purchase of property and occupation thereof are not sufficient
factors, either severally or jointly, to establish an existing nonconforming use" and
that the use '"must exist somewhere outside the property owner's mind."'
Anderson, 81 Wn.2d at 321 (quoting Cook v. Bensalem Twp. Zoning Bd. of
Adjustment, 413 Pa. 175, 196 A.2d 327, 330 (1963)). The landowner might have
established the gravel operation as a preexisting use because it "existed" prior to
the zoning change. He could not, however, prove that the intended cement batching
plant was established so as to be a nonconforming use. That same reasoning
applies in this case.
Here, Shear took similar actions to that of the landowner in Anderson. He
obtained rights to the land (although not a fee interest), stored some materials on
the property, and expressed an intent to take further action to commence a
recycling operation but had not commenced actual recycling. When the regulations
changed, the "processing" component of his materials processing facility had not
begun. Allowing some contemplated future use to be considered a "preexisting"
use would be contrary to the requirements of the preexisting use doctrine as
defined by our cases, and we find no language in the King County Code that would
allow a landowner to create a preexisting use merely by undertaking preparatory
12 No. 87514-6
steps with a plan to take action at some unknown time in the future. Neither the
King County Code nor our cases recognize such activities as sufficient to establish
a vested nonconforming use. Shear has not met his burden to show his use was
established.
As further support for this conclusion, this case also presents the situation
where Shear's preparatory work was performed without the required permits.
Importantly, Shear did not appeal the hearing examiner's conclusion that permits
were required for the grading performed before the code revisions. The hearing
examiner recognized this failure and ordered Shear to apply for and secure those
permits, albeit, after the fact. That ruling, however, has the analysis somewhat
backward. A component of establishing a preexisting use is that the use be lawfully
established. This rule has been consistently recognized by our cases. Rhod-A-
Zalea, 136 Wn.2d at 6 (stating rule that use must have "lawfully existed" prior to
becoming a nonconforming use); McMilian, 161 Wn. App. at 590-91 (holding that
petitioner's status as a trespasser precluded a finding that the use lawfully existed,
and therefore the use could not be a nonconforming use); First Pioneer Trading
Co. v. Pierce County,l46 Wn. App. 606, 614, 191 P.3d 928 (2008) (discussing
petitioner's failure to obtain proper permitting and finding that petitioner had not
established a nonconforming use). What these cases recognize is that when a
13 No. 87514-6
landowner utilizes unlawful methods to establish a nonconforming use, that
unlawfulness precludes a subsequent finding of a lawful nonconforming use.
Because Shear has not appealed the ruling that permits were required, he cannot
meet the required showing that his use lawfully existed. 5
CONCLUSION
We reverse the Court of Appeals' reinstatement of the hearing examiner's
decision and hold that Shear's use was not established within the provisions of the
King County Code as a lawful preexisting use.
5 Because we hold that the materials processing facility was not a lawful nonconforming use, we do not need to resolve the issues regarding the hearing examiner's imposition of conditions. The hearing examiner's conditions were imposed as part of the conditional use permit process, which was necessarily predicated on Shear having a nonconforming use. Thus, we need not address whether the hearing examiner exceeded his authority or whether the code contains an enforceable flood hazard zone standard.
14 No. 87514-6
WE CONCUR:
5~¥ fflcfr-'(j·