King Construction, Inc. v. Plaza Four Realty, LLC

976 A.2d 145, 2009 Del. LEXIS 360, 2009 WL 2033060
CourtSupreme Court of Delaware
DecidedJuly 15, 2009
Docket84, 2009
StatusPublished
Cited by8 cases

This text of 976 A.2d 145 (King Construction, Inc. v. Plaza Four Realty, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King Construction, Inc. v. Plaza Four Realty, LLC, 976 A.2d 145, 2009 Del. LEXIS 360, 2009 WL 2033060 (Del. 2009).

Opinion

HOLLAND, Justice:

The plaintiff-appellant, King Construction, Inc. (“King”), appeals from the final judgment of the Superior Court dismissing King’s statement of claim for a mechanics’ lien against property owned by the defendant-appellee, Plaza Four Realty, LLC (“PFR”). The Superior Court granted PFR’s motion to dismiss because the statement of claim: first, failed to allege that PFR provided prior written consent to the contract between King and PFR’s tenant; second, failed to allege the time when the provision of labor or materials was completed; and third, was filed prematurely because King had not yet completed performance of the labor or made a final delivery of materials under the contract.

In this appeal, the appellant argues that the Superior Court should not have dismissed its claim because title 25, section 2712(b) of the Delaware Code 1 does not require a statement of claim for a mechanics’ lien to allege that the property owner gave prior written consent; or the date of completion of the work, if the work is not yet completed when the statement of claim is filed. The appellant also argues that a statement of claim may be filed before the work is completed.

We conclude that where construction work is performed on leased property pursuant to a contract with the tenant, the Delaware Mechanics’ Lien Statute requires that a statement of claim allege, inter alia, that: the tenant obtained the property owner’s prior written consent; and “the date of completion of the labor performed or of the last delivery of materials furnished.” Failure to allege the property ownerfiessor’s written consent or the date of completion, or filing a statement of claim before completion, renders the statement of claim incomplete and requires dismissal of the claim. Accordingly, the final judgment of the Superior Court must be affirmed.

Facts

King is a general construction contractor based in Baltimore, Maryland. PFR is a limited liability company that owns property in Newark, Delaware. PFR leased its property at 721 E. Chestnut Hill Road in Newark to Alpha Baptist Church a/k/a Alpha Worship Center, Inc. (“AWC”), with the lease term commencing on January 1, 2007. AWC intended to renovate the building on the property to use as a church.

On December 8, 2006, before the lease term commenced, the manager of PFR sent the New Castle County Department of Land Use a notarized letter authorizing AWC to obtain a demolition permit or building permit for its renovation project. 2 On December 20, 2006, AWC entered a construction contract with King to perform the renovations for a lump sum of $1,185,000.

King began furnishing labor and materials for the AWC renovations on January 22, 2007. On March 1, 2007, AWC direct *148 ed King to focus its construction efforts on the more critical parts of the project and to stop work on the less critical portions, because AWC was experiencing financial difficulties. During the renovations, AWC also issued various change orders directing King to add certain work to and delete other work from the contract. The changes reduced the sum of the contract by $156,056.23 to a revised sum of $1,028,943.77.

King alleges that AWC refused to pay King certain amounts it owed under the contract upon proper requests for payment from King. Specifically, King claims that the value of the labor and materials it provided under the contract was $967,992.51 and that the value of the work remaining to be performed was $60,951.26. King claims that AWC has only paid $671,194.42 and still owes King $367,749.35 under the contract.

Mechanics’ Lien Claim

On August 31, 2007, King filed a statement of claim in the Superior Court, seeking a mechanics’ lien for $367,749.35 against PFR’s property at 721 E. Chestnut Hill Road. King also sought a personal judgment in the same amount against AWC. The statement of claim did not allege that PFR had given prior written consent to the construction and did not mention the December 2006 letter from PFR’s manager to the Department of Land Use. The statement of claim did not allege a date on which the performance of labor was completed or on which the last delivery of materials was supplied. Instead, it stated that King continued to perform labor and to supply materials to the property, and that the value of the work remaining to be completed was $60,951.26. The work remained uncompleted at the time this appeal was filed.

After King filed its statement of claim, King and AWC entered into a payment plan agreement in which AWC agreed to make periodic payments to King. King stated in its opening brief in this appeal that it still needs the mechanics’ lien to secure its position under the payment plan agreement.

On May 29, 2008, PFR filed an answer to King’s statement of claim. The answer included an affidavit of defense with a copy of the lease between PFR and AWC. PFR asserted that it had not given prior written consent “to the repairs and alterations to the property requested by and contracted for by the Tenant.”

Motion to Dismiss

On June 19, 2008, PFR filed a motion to dismiss the statement of claim. PFR argued that the statement of claim should be dismissed because: first, King failed to allege that PFR gave prior written consent to the construction; second, King filed its statement of claim prior to the completion of the work; and third, King failed to allege the date on which the work was completed.

On September 2, 2008, King filed its response in opposition to the motion to dismiss. King asserted that PFR had given prior written consent to the construction when it sent the letter to the Department of Land Use authorizing AWC to “obtain a demolition and/or building permit and a change of use permit” for the property. King filed a copy of the December 2006 letter as an exhibit to its response.

King also argued that section 2712(b) of the Mechanics’ Lien Statute 3 does not require that a statement of claim contain an allegation that the property owner gave prior written consent to construction con *149 tracted for by the tenant and, therefore, its failure to allege prior written consent did not render the statement of claim defective. In addition, King argued that it could not include the completion date in the statement of claim because the work to be performed under the contract was not completed. King also contended that the statement of claim for a mechanics’ lien could be filed prior to the completion of the work, as long as it was not filed more than 120 days following the completion of the work, under the applicable limitations period provided in section 2711(b).

Superior Court Judgment Motion to Dismiss Granted

On September 29, 2008, the Superior Court issued a written opinion adopting PFR’s position and dismissing the statement of claim without prejudice. 4 King sought an interlocutory appeal to this Court, which was denied. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CRE Niagara Holdings, LLC v. Resorts Group, Inc.
Superior Court of Delaware, 2021
DiFebo v. Board of Adjustment of
132 A.3d 1154 (Supreme Court of Delaware, 2016)
Christiana Mall, LLC v. Emory Hill & Co.
90 A.3d 1087 (Supreme Court of Delaware, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
976 A.2d 145, 2009 Del. LEXIS 360, 2009 WL 2033060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-construction-inc-v-plaza-four-realty-llc-del-2009.