Kinetic Systems, Inc. v. Integrated Project Services, LLC and Lonza Biologics, Inc.
This text of 2025 DNH 002 (Kinetic Systems, Inc. v. Integrated Project Services, LLC and Lonza Biologics, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE
Kinetic Systems, Inc. Case No. 20-cv-1125-SM v. Opinion No. 2025 DNH 002
Integrated Project Services, LLC and Lonza Biologics, Inc.
O R D E R
Kinetic Systems, Inc. renews its motion for judgment
against Integrated Project Services, LLC (“IPS”) for the entire
amount back charged, notwithstanding the jury’s verdict
(awarding only part of the back charged amount). See Fed. R.
Civ. P. 50(b). IPS objects. For the reasons that follow, the
motion is denied.
Standard of Review
“If the court does not grant a motion for judgment as a
matter of law made under Rule 50(a), . . . the movant may file a
renewed motion for judgment as a matter of law.” Fed. R. Civ.
P. 50(b). To succeed on a motion under Rule 50(b), the movant
must establish that “the jury failed to reach the only result
permitted by the evidence.” Lestage v. Coloplast Corp., 982
F.3d 37, 47 (1st Cir. 2020). For purposes of a Rule 50(b)
motion, the court construes the “facts in the light most
favorable to the jury verdict, draw[s] any inferences in favor
of the non-movant and abstain[s] from evaluating the credibility of the witnesses or the weight of the evidence.” Suero-Algarín
v. CMT Hosp. Hima San Pablo Caguas, 957 F.3d 30, 37 (1st Cir.
2020) (citation omitted).
Background
IPS engaged Kinetics as a subcontractor to do piping and
mechanical work on a commercial construction project. From the
beginning, Kinetics fell behind the agreed upon schedule and was
unable to meet important deadlines. Kinetics also did not pay
many of its subcontractors in a timely manner, all of which led
to delays and unexpected additional project costs. At the end
of the project, IPS and Kinetics negotiated certain change
orders aimed at resolving outstanding claims and disputes. IPS,
however, withheld amounts from the change order payment as back
charges to cover extracontractual costs that Kinetics allegedly
caused and IPS incurred.
Kinetics brought suit against IPS and Lonza Biologics, Inc.
(the project owner), seeking recovery of the amounts withheld.
Before trial, Kinetics and IPS entered a stipulation of fact,
establishing that the parties had agreed to two change orders --
one for $1,255,587 and the other for $1,874,762, which totaled
$3,130,349. Of that agreed amount, IPS paid Kinetics only
$1,024,034.75, withholding the remainder as back charges in the
amount of $2,106,314.75. Kinetics disputed IPS’s right to
2 withhold back charges as well as the amount of the back charges
withheld.
IPS asserted that it properly withheld $2,106,314.75 under
the withholding provision in the Subcontracts, § 7.16. The
issue at trial was whether, or to what extent, IPS properly
withheld the back charged amounts from the agreed payment due
for the change orders. IPS bore the burden of proving that the
amount withheld was allowed under § 7.16. IPS introduced
testimony and other evidence regarding Kinetics’s deficient work
performance and the negative impact of that work. IPS claimed
that some $2,569,221 in additional costs caused by Kinetics were
incurred. To cover those costs (i.e. to pay third parties and
cover its own costs), IPS sought funds from Lonza in a “Capital
Project Change Request,” which Lonza approved. One of IPS’s
employees, Anthony Malvone, testified that Lonza provided the
funds to cover the extra costs that IPS incurred due to
Kinetics’s failure to perform as contractually required.
Evidence presented also supported IPS’s claim that it was
obligated to, and Lonza fully expected it to, recover those
costs through back charges against Kinetics.
The jury returned a verdict in favor of Kinetics on the
breach of contract claim as to some, but not all, of the amount
withheld from the agreed back charge amount. The jury found
that $444,875.53 of the $2,106,314.75 back charged was not
3 proper under the Subcontracts. IPS owes that amount to
Kinetics.
Discussion
Kinetics argued at trial, and argues in support of this
Rule 50(b) motion, that IPS could not, as a matter of law,
withhold any of the amount owed under the change orders,
because, among other things, § 7.16 allowed withholding only “to
such extent as IPS reasonably deems necessary to protect it from
loss as a result of [eight listed circumstances].” Doc. no. 57-
8, at 24-25 (emphasis added). Kinetics also argued at trial and
argues in this motion that IPS did not need protection from
loss, within the meaning of § 7.16, because Lonza had already
funded the additional costs IPS claimed to have incurred due to
Kinetics’s alleged failures to fully perform, when it approved
and paid IPS’s change order request. Kinetics further argues
that because Lonza paid IPS’s change order seeking reimbursement
for the extra costs, IPS would receive a windfall to the extent
it is permitted to withhold any amount from the Kinetics change
orders.
Kinetics’s theory, however, ignores the commercial reality
of the parties’ dealings, and it lacks contractual context. The
evidence at trial established that Kinetics did not perform its
work under the Subcontracts, and did not pay all of its
subcontractors, in a timely manner, which led to problems and
4 additional unanticipated costs on the project. As a result, IPS
had to provide some additional supervision and perform
additional tasks to obtain adequate performance. That extra
work was costly, but it was also necessary to keep the project
moving toward completion. Those additional incurred costs were
“covered” or “funded” by amounts provided to IPS by Lonza,
again, to keep the project going, as the jury could well have
found.
The additional costs that IPS incurred due to Kinetics’s
performance failures on the project, as found by the jury, were
not amounts owed to Kinetics, but amounts Kinetics owed to IPS,
or, in the end, to Lonza. Those additional costs were in the
nature of damages, or “losses”, incurred by IPS initially, and
by Lonza ultimately. Kinetics has not pointed to any evidence
that IPS and Lonza intended, understood, or agreed that Kinetics
would be relieved of all liability for the extra costs IPS (and
Lonza) incurred because of Kinetics’s own performance failures.
The evidence shows that IPS (and Lonza) fully intended to
recover the additional costs from Kinetics through back charges
under the Subcontracts’ provisions. The arrangement between IPS
and Lonza as to how the amounts back charged may be allocated
between them is irrelevant to IPS’s right to withhold payment
under § 7.16. To the extent IPS might now be over paid, with
respect to Lonza, as a result of the verdict, does not affect
5 Kinetics’s obligation to reimburse IPS for the additional costs
the jury found Kinetics to have caused and IPS to have incurred.
Kinetics presented its theory to the jury–that under § 7.16
of the Subcontracts IPS could not withhold payment from the
change orders on grounds that Lonza had “paid” IPS for those
extra costs. The jury properly rejected that theory and found
that IPS was within its contractual rights to withhold proper
back charges under § 7.16. Kinetics has not shown that “the
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2025 DNH 002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kinetic-systems-inc-v-integrated-project-services-llc-and-lonza-nhd-2025.