Kimberly v. Aldridge

357 S.W.2d 558, 1962 Mo. App. LEXIS 756
CourtMissouri Court of Appeals
DecidedApril 2, 1962
DocketNo. 23444
StatusPublished
Cited by1 cases

This text of 357 S.W.2d 558 (Kimberly v. Aldridge) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kimberly v. Aldridge, 357 S.W.2d 558, 1962 Mo. App. LEXIS 756 (Mo. Ct. App. 1962).

Opinion

CROSS, Judge.

This is an equity action in the nature of an interpleader. Plaintiff holds funds in escrow as a disinterested stake holder. Both defendants interplead their respective claims to the fund. Defendant Paul Ber-man, a Trustee in Bankruptcy, appeals from the trial court’s judgment awarding the fund to defendant R. G. Aldridge.

The controversy stems from the construction of the Grandview Bank Building, and involves inter-related transactions between the principal contractor, a subcontractor and a sub-subcontractor.

In September, 1958, the Bennett Construction Company entered into the principal contract with the Grandview Bank to construct the building. Bennett then entered into a subcontract with one Stanley C. Dugan, which provided that Dugan would perform the excavation work on the project. In turn, Dugan entered into a sub-subcontract with defendant Aldridge entitled “Equipment Rental Agreement”, which obligated Aldridge to furnish dirt moving machinery and operators for the excavation work, and bound Dugan to pay for the use of such machinery and the labor required for its operation on the basis of an hourly rate.

.During October, 1958, Aldridge furnished the required machinery and labor and performed and completed the excavation work called for by his contract with Dugan. In so doing he incurred actual cost expense, including labor hire paid out of pocket, in the sum of $5,867.22, but exclusive of wear and depreciation of his machinery. Aldridge completed performance of the contract on October 3, 1958. Under its terms he was entitled to full payment from Dugan on November 15, 1958. On November 20, 1958, Aldridge invoiced Dugan for the payment of $8,217.50 — the contract price for all services rendered under the contract, as calculated by its terms and specified rates. Dugan admits that Al-dridge fully performed the contract. He testified Aldridge did “every bit”' of the work shown on the statement, and that “the prices charged (the total of $8,217.50) are the contract prices”. Dugan made no response to the invoice, and has never paid Aldridge.

After Dugan’s default Aldridge looked to Bennett for payment. Aldridge took the position that it was then Bennett’s direct obligation, arising by contract, to pay for the labor and materials he had furnished. The contract provisions relied upon by Aldridge are contained in the principal contract between Grandview and Bennett — as affirmed and incorporated in Bennett’s subcontract with Dugan.

The Grandview-Bennett contract includes several documents going to make up the entire agreement, one of which is a performance bond executed by Bennett as principal and by the Aetna Casualty and Surety Company as his surety. Pertinent provisions of the bond read as follows:

“NOW, THEREFORE, if Principal shall faithfully perform such contract and pay all persons who have furnished [560]*560labor or material for use in or about the improvement and shall indemnify and save harmless the Owner from all cost and damage by reason of Principal’s default or failure so to do, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
“All persons who have furnished labor or material for use in or about the improvement shall have a direct right of action under the bond, subject to the Owner’s priority”.

The subcontract between Bennett and Du-gan provides, in part:

“2. The sub-contractor * * * agrees to comply with the general conditions of the contract between the owner and the general contractor
“4. The purchaser (Bennett) agrees to pay the sub-contractor * * * in accordance with terms of his contract with the owner * * * ”,

Aldridge first demanded payment from Bennett by a letter and statement of account mailed December 23, 1958, followed by a second letter and statement mailed January 14, 1959, which reads in part as follows: “We would appreciate your check for the above rental as soon as possible, otherwise we will have to take other means to collect this money”. Testimony on behalf of Aldridge discloses that the “other means” intended by him were to file a mechanic’s lien on the property and to file a suit on Bennett’s bond. During these negotiations Aldridge’s consulting attorney was Mr. Clifford B. Kimberly — nominal plaintiff in this suit. Mr. Kimberly notified both Bennett and the bonding company of “a potential claim under the bond”. He made demand upon Aetna for a copy of the bond and notified that company of Al-dridge’s claim. The attorney had advised Aldridge that he had a right to file a mechanic’s lien against “the job”. It was then in contemplation that such lien would be filed if payment was not received before the lien filing period expired.

The record does not show that Bennett made any response to Aldridge’s letters. However, it is shown by the testimony of W. W. Bennett, President of the Bennett Company, that he “ran into” Aldridge while on an out state business trip and had a discussion with him about the claim. Mr. Bennett testified, “I assured him if he would come to our office, why we would close the matter because we felt obligated to pay him for it”. Bennett also stated that he had in mind, in dealing with Aldridge, the fact that Aldridge had a right to file a mechanic’s lien; that he and Aldridge’s attorney had discussed that subject several times; that as the original prime contractor he was concerned that a mechanic’s lien not be filed on the job and that Al-dridge be paid; also that he was familiar with the provision of the bond that anyone who furnished labor on the job had a right to sue directly on the bond for payment and that he recognize Aldridge’s right to do so.

The time within which Aldridge could file a statutory lien against the property expired March 1, 1959. Approximately two weeks before that date Aldridge went to the Bennett Company’s office and there conferred with W. W. Bennett. Dugan was not present. The conference resulted in a settlement of Aldridge’s account by an agreement that Aldridge would reduce his claim to $7500.00 and that Bennett would issue the company’s check in the amount of $7500.00 as payment of the claim in full. On February 16, 1959, Bennett issued the check in the agreed amount, payable to Al-dridge and Dugan, and delivered it to. Aldridge.

Aldridge testified that he accepted the check “as payment for the job” and that as a result of receiving the check he refrained from filing a mechanic’s lien and from filing a suit on Bennett’s bond. W. W. Ben-[561]*561nett testified that he intended the check to be in payment to Aldridge for the work he had done and that it was specifically for that purpose; that he was actuated in making the payment by the fact that Aldridge had "the potential lien right and the potential right to sue on the bond”; that “Du-gan never did any work on the site that we know of * * * ”; that he (Bennett) took over the job from Dugan and caused it to be completed; that there is a balance due Bennett from Dugan; that Bennett is not indebted to Dugan in any amount; that in view of that situation Bennett would not have paid Dugan any money at all, did not intend to pay him, and did not intend the check to include any payment to Dugan.

After receiving the check from Bennett, Aldridge attempted to locate Dugan and secure his endorsement. Failing to do so, Aldridge endorsed the check and deposited it for payment. The bank on which the check was drawn refused payment because it lacked Dugan’s signature.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson Savings & Loan Ass'n v. Seabaugh
395 S.W.2d 260 (Missouri Court of Appeals, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
357 S.W.2d 558, 1962 Mo. App. LEXIS 756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kimberly-v-aldridge-moctapp-1962.