Kimberly Lighting LLC v. Refresco Beverages US Inc.

CourtDistrict Court, E.D. Michigan
DecidedJuly 20, 2021
Docket2:21-cv-10089
StatusUnknown

This text of Kimberly Lighting LLC v. Refresco Beverages US Inc. (Kimberly Lighting LLC v. Refresco Beverages US Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kimberly Lighting LLC v. Refresco Beverages US Inc., (E.D. Mich. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION KIMBERLY LIGHTING, LLC,

Plaintiff and Counter-defendant, Case Number 21-10089 v. Honorable David M. Lawson

REFRESCO BEVERAGES US, INC.,

Defendant and Counter-plaintiff. __________________________________________/

OPINION AND ORDER DENYING MOTION TO TRANSFER VENUE

In this commercial sales dispute, defendant Refresco Beverages US asks the Court to transfer the case to the District of New Jersey. The defendant, a Florida company, does not challenge personal jurisdiction or argue that venue is improperly laid in this district. Instead, it argues that the dispute primarily concerns the installation of industrial lighting at one of its warehouses in New Jersey, and the federal court in that state would be more convenient for the parties and witnesses who have knowledge about the work done there. But according to the plaintiff, the dispute also deals with installations at two locations in Pennsylvania, there also is a settlement agreement negotiated between lawyers in Florida and Michigan it seeks to enforce, and witnesses must travel some distance to testify no matter where the trial takes place. Perhaps New Jersey may be a marginally more convenient place to try certain aspects of this lawsuit, but the defendant has not made a compelling case for transfer sufficient to upset the plaintiff’s initial choice of forum. The motion will be denied. I. Plaintiff Kimberly Lighting LLC is a Michigan company that installs, recycles, leases, evaluates, and makes recommendations on new lighting products and services. Defendant Refresco is a national bottler of branded beverages, incorporated in Georgia with its principal place of business in Florida. Sometime last year, the parties entered into several contracts to install upgraded lighting at eight Refresco facilities which are located in Oklahoma, Florida, New Jersey, South Carolina, California, and two cities (Glen Mills and Aston) in Pennsylvania. According to the amended

complaint, Refresco still owes Kimberly money for the work done at the New Jersey and the two Pennsylvania locations. Kimberly alleges that the work was completed at the three locations toward the end of 2020. Refresco allegedly signed off on the completed work but refused to pay Kimberly. Refresco says it has not paid because Kimberly failed to complete all the work and did not install the proper equipment. The dispute prompted negotiations between the parties’ representatives located in Michigan and Florida, communicating via email. Kimberly alleges that the parties reached a settlement agreement in December 2020 for the work performed at the three locations. The agreement called for Kimberly to perform the

necessary work at the facilities and to conduct a walkthrough at the New Jersey facility to address whether any additional work needed to be performed, and Refresco would pay for the completed work. It appears that a walkthrough inspection was performed in New Jersey by Kimberly’s Michigan-based representative Doug Jenkins. In an email dated December 9, 2020, counsel for Refresco confirmed that payment would be made per the resolution agreed upon. However, Refresco denies that a formal settlement agreement ever took place. Jenkins earlier had visited New Jersey to bid on the project. On March 2, 2020, Kimberly quoted $122,621 to replace various lighting fixtures at that facility. The work was completed by an installer, Wachter, Inc., which has a presence in New Jersey. During the walkthrough of the facility, Kimberly discovered that 57 high bay lights that it delivered to Refresco (which Refresco confirmed it had received) were missing and could not be installed. Kimberly issued Refresco a credit of $24,080 for those items. Although all of the other work was completed, Refresco still has not paid Kimberly. Kimberly asserts that Refresco owes $74,020.40 for the services and products provided. Additionally, it contends that Refresco

“accepted delivery, and took possession and control of, 112 high bay lights and 440 tubes valued at $37,096,” but never paid for them and refuses to return them or to allow Kimberly to install them. Finally, Kimberly alleges that Refresco owes at least $16,300 for the profit and lost rebates that Kimberly did not receive as a result of Refresco’s refusal to allow Kimberly to install the products. Refresco, however, believes that Kimberly is not entitled to any payment until it fully completes the work; it also determined that “some or all” of the high bay lights that Kimberly supplied were the incorrect wattage (165 watts instead of 180 watts), and the high bay lights that were the correct wattage failed to meet separate illumination requirements specified in Refresco’s

purchase order. On January 29, 2021, Jenkins signed a document reflecting Kimberly’s understanding of the scope of the uncompleted work for the high bay light installations in New Jersey. After the parties attempted to negotiate the completion of the outstanding work, Kimberly indicated that it no longer agreed to complete the work on the project and issued a “credit memo” in the amount of $18,019 on March 5, 2021. On March 18, 2021, Refresco issued a notice of default to Kimberly, declaring that Kimberly defaulted on the contract and demanding that it complete the project to avoid termination and the hiring of backup contractors. Kimberly allegedly refused, and Refresco terminated the contract on March 23, 2021. It appears that a dispute also arose over the separate contracts to install lighting at two of Refresco’s Pennsylvania facilities. That dispute also was the subject of negotiations. According to the purported settlement agreement, Kimberly would perform the additional work at the Pennsylvania facilities by December 23, 2020 and upon completion, Refresco would make the outstanding payments by December 31, 2020.

Kimberly completed the work at Refresco’s Pennsylvania facilities on December 26, 2020 (the three-day delay was due to a snowstorm, which prevented workers from getting to the site). In an email, Refresco expressed satisfaction with the completion of the work and indicated that it would forward payment to Kimberly. Refresco’s response to the initial complaint reflects its belief that this aspect of the dispute was resolved and any related claims were moot. But Kimberly asserts in its amended complaint that, although it completed the project, Refresco only made partial payment and additional amounts remain outstanding. Kimberly also contends that because of its reliance on Refresco’s promises, it incurred an additional $5,862.96 in materials, costs, and expenses, and it seeks to recoup discounts that were conditioned on Refresco’s timely payment

under the parties’ settlement agreement. Kimberly filed its complaint in this Court on January 12, 2021, alleging fraudulent inducement, breach of contract, and unjust enrichment in separate counts for the New Jersey and Pennsylvania installations. On March 30, 2021, Refresco filed a counterclaim alleging that Kimberly breached the parties’ contract with respect to the work performed at the New Jersey facility and seeking a declaratory judgment that it need not pay Kimberly anything until Kimberly completes the project adequately. Kimberly then amended its complaint, adding one count of conversion for the defendant’s refusal to pay for the New Jersey lighting. Refresco filed an amended counterclaim, which added an allegation that Kimberly breached the parties’ contract by failing to ensure that the lighting met the project’s illumination requirements. Refresco filed its motion to transfer venue on the same day it filed its counterclaim. II. The defendant asks the Court to transfer this case to the District of New Jersey under 28

U.S.C. § 1404(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Piper Aircraft Co. v. Reyno
454 U.S. 235 (Supreme Court, 1982)
Stewart Organization, Inc. v. Ricoh Corp.
487 U.S. 22 (Supreme Court, 1988)
Nicol v. Koscinski, U.S. Dist. Judge
188 F.2d 537 (Sixth Circuit, 1951)
Actmedia, Inc. v. Ferrante
623 F. Supp. 42 (S.D. New York, 1985)
Audi AG & Volkswagen of America, Inc. v. Izumi
204 F. Supp. 2d 1014 (E.D. Michigan, 2002)
Lewis v. Grote Industries, Inc.
841 F. Supp. 2d 1049 (N.D. Illinois, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Kimberly Lighting LLC v. Refresco Beverages US Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kimberly-lighting-llc-v-refresco-beverages-us-inc-mied-2021.