Kimball v. United States

24 Ct. Cl. 35, 1888 U.S. Ct. Cl. LEXIS 1, 1800 WL 1611
CourtUnited States Court of Claims
DecidedDecember 31, 1888
DocketNo. 14687
StatusPublished
Cited by2 cases

This text of 24 Ct. Cl. 35 (Kimball v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kimball v. United States, 24 Ct. Cl. 35, 1888 U.S. Ct. Cl. LEXIS 1, 1800 WL 1611 (cc 1888).

Opinion

Sooeield, J.,

delivered the opinion of the court:

By authority of an act of Congress approved June 18,1878, a survey of Pearl River, in Mississippi, with a view to improve its navigation, was made under the direction of the War Department. The survey extended from Carthage, which is 105 miles above the city of Jackson, to the mouth of the river, a distance of about 500 miles. A chart was prepared, on which were noted the obstructions to navigation found in the river at that time.

In 1879 and again in 1880 small appropriations were made for the improvement above Jackson, and the work was commenced and prosecuted on that part of the river lor several years'.

June 14, 1880, Congress appropriated $30,000 to commence the improvement below Jackson.

The Department advertised for proposals. The claimant became the lowest bidder, and the work, beginning at Jackson and extending down the river 195 miles, was allotted to him.

[53]*53October 7,1880, a formal contract was executed, in which, this claimant agreed—

“ In accordance with advertisement and specifications, and in accordance with his proposal, to faithfully perform the work of improving the navigation of Pearl River for a continuous distance of 195 miles to a point about three-quarters of a mile below Harrison’s Ferry, as exhibited on a chart on file in the United States engineer office at New Orleans.”

The contract provided that the work should be completed by January 1, 1882, but the time was afterwards extended to January 1, 1883. The work was not to be accepted until it had undergone a rigid inspection by % Government officer.

The claimant was furnished with a copy of the chart referred to in the contract and advertisement, and soon after began the improvement.

In the autumn of 1881 the claimant notified the engineer that he had cleared the river for 104 miles, and requested an inspection. The request was refused.

In September, 1882, he notified that officer that, his work was complete for the whole 195 miles, and requested an inspection. To this request the engineer replied that Mr. Collins,, the assistant engineer who had made the original survey, had already passed down the river and found many obstructions, and therefore a more formal inspection at that time would be useless, as he would not accept the work in that condition. The claimant contended that the obstructions observed by Mr. Collins had come into the stream after he had once cleared it out and that he was not required by his contract to remove new obstructions which were being deposited by every flood. Nevertheless, he obtained Mr. Collins’s notes, went over his work again, and removed all the instructions so noted.

December 12, 1882, he again notified the engineer that he had completed his contract and requested inspection and payment. December 25, 1882, Assistant Engineer Buchanan was sent to make the inspection, but he found the river too high.

Thereupon a.supplementary contract was made, whereby it was agreed that $25,000 should be then paid and the balance left until after an inspection could be made the next summer.

Although no official inspection was then made, the court has found that the claimant had, in fact, prior to December 12, [54]*541882, removed all the obstructions to navigation in the river which were noted in the chart of the original survey; all that he had found in the river as he progressed with the work, whether noted on the chart or not, and all that were pointed out on the notes of Mr. Collins furnished him in September, 1882.

In August, 1883, Mr. Buchanan made an inspection of the work and reported to the engineer in charge September 11, 1883. The latter officer, in reply to the claimant’s inquiry as to the result of the inspection, informed him that Mr. Buchanan had reported that “ he did not believe that the river had been cleaned out according to contract,” and that “he (the engineer in charge) could not accept the work.” He did not inform him • of any specific obstructions found in the river by Mr. Buchanan, nor of any further work which he was expected to perform.

If the question of performance or non-performance were in issue here the court would be compelled to decide that on December 12,1882, when the claimant called for final inspection, his work was complete, and only awaited a formal inspection and acceptance to entitle him to his pay; and further, that he was not bound by the terms of his contract to clear the river of obstructions deposited by the floods of 1883.

The claimant, however, had agreed to submit that question to the decision of the defendants or their engineer in charge. The advertisement provides that—

“ No payment will be made until the work contracted for is completed to the satisfaction of the United States.”

The specifications further provide that—

“When the contractor reports his work finished an inspection will be made to satisfy the United States before settlement.”

The contract itself provides that—

“ The decision of the engineer officer in charge as to conformity [of the work to the contract] shall be final.”

The supplemental contract again provides that the claimant shall—

“ Make no claim or demand for said balance until after such inspection and acceptance.”

The engineer decided against the claimant, and that decision must stand unless impeached for fraud or mistake other than an error of judgment.

[55]*55If that were all, the claimant would be without remedy in this court. But it is not all. After an unfavorable inspection and non-acceptance the claimant was to be informed of the alleged defects in his work and given an opportunity to perfect it.

The original contract provides that—

“ All work done under this contract shall, before being accepted, be subject to rigid inspection by an inspector appointed on the part of the Government, and such as does not conform to the specifications set forth in this contract shall be made to conform before settlement of the contract.”

The supplemental contract further provides that the claimant shall—

“ Make no claim or demand for said balance until after such inspection and acceptance and to duly perform any and all such other or further work as may, under the terms and conditions of said original contract, be required of him by the inspecting officer, and to leave all his plant on the work until after final and accepted completion of said work by the United States.”

The purpose in retaining the $3,736 and requiring the plant to be left on the work was, undoubtedly, to secure the performance of further work, if, on inspection, any deficiency should be found.

The claimant was never thereafter notified of any specific deficiency nor required to perform any specific work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parish v. United States
98 F. Supp. 347 (Court of Claims, 1951)
John Thomson Press, & Manufacturing Co v. United States
57 Ct. Cl. 200 (Court of Claims, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
24 Ct. Cl. 35, 1888 U.S. Ct. Cl. LEXIS 1, 1800 WL 1611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kimball-v-united-states-cc-1888.