Killian Corp. v. Murphy

27 Mass. L. Rptr. 321
CourtMassachusetts Superior Court
DecidedAugust 6, 2010
DocketNo. 063453
StatusPublished

This text of 27 Mass. L. Rptr. 321 (Killian Corp. v. Murphy) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Killian Corp. v. Murphy, 27 Mass. L. Rptr. 321 (Mass. Ct. App. 2010).

Opinion

Fremont-Smith, Thayer, J.

Based on all of the credible evidence, the Court finds and rules as follows.

In this case, the plaintiff Killian Corp. (“Killian”) sued defendants to recover the unpaid balance ($27,000) of what was owed to plaintiff under a contract for $127,000 to remodel defendants’ home, and defendants (“Murphy”) counter-claimed for plaintiffs alleged failure to perform the contract in a workmanlike manner and within a reasonable time period, the delay allegedly resulting in rain damage to the home and its contents.1 The jury returned a verdict of $20,000 against the defendants on Killian’s claim, and of a verdict of $10,648 on defendants’ counterclaim against the plaintiff.

The Court reserved to itself the determination whether Killian violated the terms of G.L.c. 142A (the Home Improvement Act), whether the alleged, violations of G.L.c. 142A constituted a violation of c. 93A, and whether Killian otherwise violated c. 93A by additional acts and/or omissions that constituted unfair and deceptive practices.

On July 1, 2005, Murphy signed his acceptance of Killian’s “Proposal” for the construction work, which thereby became the controlling contract, which, by its terms, incorporated the architectural specifications and drawings contained in Murphy’s previous contract with his architect.

[322]*322The contract provided that Killian was

To remove existing second floor bedroom area complete to weather proof same while under construction.
To construct as per drawing new second floor and attic space.
Changes are:
Remove Master Bed Room Deck and French doors and replace with two windows matching rest of house as per drawings.
Total Price: $150,000.2
We propose hereby to furnish labor and material— complete in accordance with above specifications, for the sum of $150,000. Payments to be made as follows: One third upon commencement, one third at frame inspection and balance upon completion.
All material is guaranteed to be as specified. All work to be completed in a substantial workmanlike manner according to the specifications submitted, per standard practices. Any alteration or deviation from the above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. All agreements contingent upon strikes accidents or delays beyond our control. Owner to carry fire, tornado and other insurance. Our workers are fully covered by Workmen’s Compensation and Property Damage Insurance.
ACCEPTANCE. The above prices, specifications and conditions are satisfactory and hereby accepted. You are authorized to do the work as specified. Payment will be made as outlined above. This Agreement between the parties may only be changed or amended by a written instrument of subsequent date signed by the parties thereto.

The scope of the work on the Project, as stated in the architect’s specifications which were incorporated into the contract, was to include “[r]empv[ing] roof and exterior walls to second floor deck as shown on plans . . . Construct new stair to new attic as shown on plans.” The architect’s specifications, incorporated into the contract, further specified:

Division 1 — General Requirements
All work to conform to Massachusetts State Building Code and all applicable local laws and regulations.
Contractor to verify all dimensions and details and report all errors and/or discrepancies to architect prior to the start of construction.
Contractor to complete all work indicated in the drawings and specifications, details not shown to be completed in accordance with accepted practices.
All work to be done in a good and workmanlike manner and completed in a timely fashion . . .
All work to be guaranteed to be free of substantial defects for a period of one year after completion .. .
Division 8 — Doors and Windows
Interior doors — 6 panel pine, solid jamb
Division 10 — Specialties
Bathroom — install towel bars, medicine cabinets, paper holders, etc. furnished by owner.
Division 15 — Plumbing and HVAC
Install fixtures and fittings furnished by owner . . .
HVAC — Design/build installation. Evaluate existing systems. Provide heating and cooling to new spaces. Install new and relocate ductwork and registers as required.

The Court finds that the contract did not comply with the specific requirements of c. 142A in several respects, which are discussed below. Although Chapter 142A(17) provides that a violation of this chapter constitutes a violation of Chapter 93A, courts have generally found violations of Chapter 142A sufficient to support a Chapter 93A claim for unfair or deceptive trade practices only when a contractor has also violated a statute or ordinance independent from Chapter 142A. Harrison Construction, LLC v. Cirurgiao, No. 2006-880-C, 23 Mass. L. Rptr. 272, 2007 Mass.Super. LEXIS 582, at * 8-9, n.5 (Mass.Super.Ct., Oct. 22, 2007) (where court concluded, in allowing summary judgment, that the defendant homeowner had failed to allege anything more than de minimus deficiencies in the contract arising from violations of Chapter 142A, §2).

The Court finds that, to the extent that the Contract here did not include certain ministerial information required by c. 142A, §2(8), such omission was similarly de minimus. For example, omitting a statement that all contractors and subcontractors must be registered by the administrator and that any inquiries about a contractor or subcontractor relating to a registration should be directed to the administrator; omitting the registration number of the contractor or subcontractor; omitting a reference to an owner’s three-day right of cancellation, a reference to c. 142A or a statement that Murphy should not sign the Contract if there were any blank spaces, were all insubstantial omissions which were inconsequential here.

At trial, there was no credible evidence that Killian violated any other statute or ordinance in performing the Project. Indeed, Edward Fredericks, the Plumbing Inspector for the City of Waltham, was the only City official to perform a final inspection of the Project, and testified that Killian’s work was performed in a workmanlike manner and in compliance with the Plumbing Code. I do not credit the testimony of Peter Mortali, a former plumbing salesman who had sold the Murphys [323]*323their bathroom fixtures in or about 2004, that he believed Killian’s work and its subcontractor’s work did not comply with the Plumbing Code or the jacuzzi’s and the Grohe shower manufacturer’s instructions, as he lacked competence to render such an opinion and also indicated bias by accusing Killian of character assassination.

While Killian did violate G.L.c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitinsville Plaza, Inc. v. Kotseas
390 N.E.2d 243 (Massachusetts Supreme Judicial Court, 1979)
Madan v. Royal Indemnity Co.
532 N.E.2d 1214 (Massachusetts Appeals Court, 1989)
Gopen v. American Supply Co., Inc.
407 N.E.2d 1255 (Massachusetts Appeals Court, 1980)
Framingham Auto Sales, Inc. v. Workers' Credit Union
671 N.E.2d 963 (Massachusetts Appeals Court, 1996)
Kobayashi v. Orion Ventures, Inc.
678 N.E.2d 180 (Massachusetts Appeals Court, 1997)
Harrison Construction, LLC v. Cirurgiao
23 Mass. L. Rptr. 272 (Massachusetts Superior Court, 2007)
J.T. Haffey Builders, Inc. v. Carey
27 Mass. L. Rptr. 48 (Massachusetts Superior Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
27 Mass. L. Rptr. 321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/killian-corp-v-murphy-masssuperct-2010.