KiewitPhelps

CourtArmed Services Board of Contract Appeals
DecidedMarch 24, 2025
Docket62980
StatusPublished

This text of KiewitPhelps (KiewitPhelps) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KiewitPhelps, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) KiewitPhelps ) ASBCA No. 62980 ) Under Contract No. W9128F-12-C-0023 )

APPEARANCES FOR THE APPELLANT: Vivian Katsantonis, Esq. Christopher M. Harris, Esq. John F. Finnegan, III, Esq. Watt, Tieder, Hoffar & Fitzgerald, LLP McLean, VA

Michael A. Branca, Esq. Peckar & Abramson, P.C. Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney James M. Pakiz, Esq. William G. Latka, Esq. James J. Irvine, Esq. Jacob W. Harberg, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Omaha

OPINION BY ADMINISTRATIVE JUDGE EYESTER ON THE GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION

The Army Corps of Engineers (Corps or government) moves to dismiss this appeal for lack of jurisdiction. Specifically, the Corps argues appellant KiewitPhelps (KP) submitted an unsigned, and therefore uncertified, claim to the contracting officer. KP disagrees and argues it did submit a certified claim to the contracting officer and then submitted another certification in response to a request from the Defense Contract Audit Agency (DCAA). The Corps argues the submission to DCAA is essentially irrelevant as it was never provided to the contracting officer. For the reasons set forth below, we deny the government’s motion to dismiss.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On August 16, 2012, the Corps awarded Contract No. W9128F-12-C-0023 to KP for the construction of a new facility to serve the U.S. Strategic Command (R4, tabs 2.01, 2.02). 1 The contract included the full text of Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002), which stated the contract was subject to the Contract Disputes Act (CDA) (R4, tab 2.01 at 1510-11). Accordingly, any claim over $100,000 had to provide a certification which “may be” executed by a representative authorized to bind the contractor with respect to the claim. The required certification was to state that the claim was made in good faith; supporting data was accurate and complete; the amount requested accurately reflected the contract adjustment for which the contractor believed the government was liable; and the signatory was authorized to certify the claim on behalf of the contractor. (Id.) FAR 52.233-1(d)(2)(iii), (d)(3)); see also 41 U.S.C. § 7103(b).

2. Ultimately, KP filed several claims with the Corps, many resulting in appeals with the Board. For example, on October 5, 2018, KP submitted a certified claim to the contracting officer seeking money and a time extension (R4, tab 27.01.02 at 165, 187, 199-200). The claim, in addition to including a signed certification, also included a signed proposed change order setting forth the claimed amounts, which also included the Defense Federal Acquisition Regulation Supplement (DFARS) 252.243-7002 certification (R4, tab 27.01.01 at 1). KP appealed a deemed denial of that claim to the Board, which was docketed as ASBCA No. 62119.

3. Two years later, on July 10, 2020, KP submitted the claim at issue here. Specifically, KP submitted Serial Letter No. H-2100 to the contracting officer seeking a contracting officer’s final decision (COFD) pursuant to FAR 52.233-1. (R4, tab 29.01 at 1) According to the serial letter, titled in part “Delay & Disruption #3 (01 JAN 2018 – 19 FEB, 2019),” KP was submitting a two-part claim in the amount of $13,702,363 (id. at 1-2).

4. In part one, KP sought $8,803,026 for alleged government caused delays and inefficiencies for the period January 1, 2018 through February 19, 2019 (R4, tab 29.01 at 1). KP titled this part of the claim “Delay and Disruption #3.” In part two, KP sought $4,899,337, arguing these were additional costs associated with its October 5, 2018 certified claim. KP titled this part of the claim “Additional Costs associated with Oct. 5th claim.” (Id. at 1-2)

5. KP’s project director signed the serial letter above his typewritten name and title (R4, tab 29.01 at 2). The serial letter did not include any certification language (see R4, tab 29.01).

1 Pursuant to an Order dated September 15, 2021, the government’s Rule 4 consists of tabs 1-20 from ASBCA No. 61184, tabs 21-28 from ASBCA No. 62119, and tabs 29-30 from ASBCA No. 62980. In addition, the decision uses the PDF page numbers in a tab for citations to the record.

2 6. KP’s serial letter specifically referenced and attached several supporting documents, including a narrative titled “Request for Contracting Officer’s Final Decision [for] Delay and Disruption Impacts After December 2017”; proposed change order 02102; and proposed change order 02103. As relevant here, the serial letter noted that proposed change order No. 02102 supported part one of the claim and proposed change order No. 02103 supported part two of the claim. (R4, tab 29.01 at 1- 2) The attachment titled Request for a Contracting Officer’s Final Decision, dated July 9, 2020, was over 500 pages of information relating to both parts one and two of the claim; both proposed change orders were part of this document (see R4, tab 29.02).

7. Attached proposed change order No. 02102, addressing part one of the claim, included itemized amounts for each alleged cost incurred as well as general and administrative expenses, profit and bond costs; the amounts totaled $8,803,027 2 (R4, tab 29.02 at 21-22). The proposed change order included the following language:

For costs incurred due to delay and disruption inefficiencies as outlined in the attached claim narrative (Attachment A). Window 1-Window 3 (January 1, 2018 - February 19, 2019).

Reference the claim narrative for all corresponding exhibits and schedules.

In accordance with DFARS 252.243-7002, I certify that the request is made in good faith and that the supporting data are accurate and complete to the best of my knowledge and belief.

(Id. at 21). The certification included the name of KP’s “Authorized Negotiator,” phone number and title of KP’s “Project Director,” and was dated July 11, 2020. The signature block, however, was blank. (Id. at 21-22) The KP authorized negotiator listed (i.e., KP’s project director) was the same person that signed Serial Letter No. H 2100 (compare R4, tabs 29.02 at 21-22, with 29.01 at 2).

8. Likewise, attached proposed change order No. 02103, addressing part two of the claim, included itemized amounts for each alleged additional costs incurred as well as general and administrative expenses, profit, bond costs, and builder’s risk insurance; the amounts totaled $4,899,338. The proposed change order also included the same certification language as proposed change order No. 02102, quoted above. The

2 On the page following proposed change order No. 02102 is an Excel worksheet providing detail about the claim amount; the total set forth for the claim is $8,803,026 (R4, tab 29.02 at 23).

3 certification included the name of KP’s “Authorized Negotiator,” phone number and title of KP’s “Project Director,” and was dated July 7, 2020. Again, the signature block was blank. (R4, tab 29.02 at 503) And, again, the KP authorized negotiator listed (i.e., KP’s project director) was the same person that signed Serial Letter No. H-2100 (compare R4, tabs 29.02 at 503, with 29.01 at 2).

9. On August 21, 2020, the contracting officer notified KP she received Serial Letter No. H-2100 with the attached 528-page narrative that included supporting data regarding the claim and stated she would issue a decision by April 16, 2021 (R4, tab 30.01 at 1-2). The contracting officer explained she would seek outside expert assistance to perform a critical path schedule analysis and “intends to exercise [the government’s] contractual rights to have the [DCAA] audit the claimed costs” (id. at 1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
KiewitPhelps, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiewitphelps-asbca-2025.