Khoshabe v. Grand Traditions, LLC

2026 IL App (1st) 250772-U
CourtAppellate Court of Illinois
DecidedMarch 25, 2026
Docket1-25-0772
StatusUnpublished

This text of 2026 IL App (1st) 250772-U (Khoshabe v. Grand Traditions, LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Khoshabe v. Grand Traditions, LLC, 2026 IL App (1st) 250772-U (Ill. Ct. App. 2026).

Opinion

2026 IL App (1st) 250772-U Order filed: March 25, 2026

FIRST DISTRICT THIRD DIVISION

No. 1-25-0772

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT ______________________________________________________________________________

JOSEPH KHOSHABE, ) Appeal from the ) Circuit Court of Plaintiff and Counterdefendant-Appellant, ) Cook County. ) v. ) No. 2021 L 63052 ) GRAND TRADITIONS, LLC, ) Honorable ) John Curry, Defendant, Counterplaintiff, and Third-Party ) Judge, presiding. Plaintiff-Appellee. ) ) (Sima Khoshabe Trust, dated September 22, 1995, and ) Owners and Non-Record Claimants, ) ) Third-Party Defendants). ) ______________________________________________________________________________

JUSTICE ROCHFORD delivered the judgment of the court. Justices Lampkin and Reyes concurred in the judgment.

ORDER

¶1 Held: Judgment in favor of appellee affirmed, where appellant forfeited issue of purported inconsistency between the general verdict and special interrogatory answers returned by the jury and appellant’s other arguments are without merit.

¶2 Plaintiff and counterdefendant-appellant, Joseph Khoshabe, appeals from a final judgment

and an award of attorney fees and costs entered in favor of defendant, counterplaintiff, and third-

party plaintiff-appellee, Grand Traditions, LLC (“GT”). On appeal, Khoshabe primarily relies No. 1-25-0772

upon a purported inconsistency between the general verdict and special interrogatory answers

returned by the jury. For the following reasons, we affirm.

¶3 Khoshabe filed his initial seven-count complaint against GT on June 28, 2021, seeking

damages purportedly arising out of a contract between the parties executed on or about October 7,

2019, for the remodeling and construction of an addition to a residential property located in South

Barrington, Illinois.

¶4 In August 2021, GT responded by filing an answer denying the material allegations of the

complaint and affirmative defenses of setoff, failure to mitigate damages, and application of the

“acts of god” provision of the contract considering the impact of the COVID-19 pandemic. GT

also filed a three-count counterclaim and third-party complaint for foreclosure of a mechanic’s

lien, breach of contract, and quantum meruit. While these counterclaims were also addressed to

third-party defendant and purported legal owner of the property at issue, Sima Khoshabe Trust,

dated September 22, 1995, this party was never served and claims against it were not further

pursued below.

¶5 In January 2022, Khoshabe filed the operative amended complaint and answers to GT’s

affirmative defenses. In the amended complaint, Khoshabe pleaded claims for breach of contract,

fraud, violation of the Illinois Home Repair Act (815 ILCS 515/1 (West 2022)), violation of the

Illinois Uniform Deceptive Trade Practices Act (815 ILCS 510/2 (West 2022)), violation of the

Illinois Consumer Fraud and Deceptive Practices Act (815 ILCS 505/1 (West 2022)), accounting,

and negligence. All but the breach of contract and negligence claims were either dismissed or

voluntarily withdrawn by Khoshabe prior to trial.

¶6 As relevant to this appeal, the amended complaint alleged that the original 2019 contract

for the remodel of and addition to the property was for $667,120, with the construction expected

-2- No. 1-25-0772

to be completed five to six months after permits for the work were obtained. The contract also

required GT to provide Khoshabe with lien waivers “from each and every subcontractor and/or

supplier or laborer for any and all of the work and materials provided by them.” The amended

complaint specifically alleged, inter alia, that GT failed to comply with this provision of the

contract, and that Khoshabe was damaged as a result and should have been excused from further

performance under the contract due to this breach.

¶7 GT filed an answer to the amended complaint in July 2022. GT refiled its affirmative

defenses and stood on its previously filed counterclaims. The parties thereafter conducted

discovery, and this matter proceeded to a jury trial in December 2024.

¶8 As relevant to the issues presented on appeal, the parties presented evidence that between

December 2019 and August 2020, the parties executed multiple written change orders for

additional or modified work on the project, increasing the contract price to $774,826.81. Khoshabe

approved of these changes in writing, and Khoshabe paid GT approximately $703,000.00, leaving

an unpaid balance of $71,826.81. One of the central issues at trial was exactly what occurred when

GT sought a final payment of that amount and Khoshabe refused to pay. The dispute centered

around the requirements of section 7(d) of the contract. That section specifically provided:

“Progress Payments. The Contract Sum shall be payable to the Builder in staged

periodic progress payments ("Progress Payments"), as follows:

***

“(d) The aforementioned Construction Payments shall be paid by Owner directly to

the Builder. Builder shall submit periodic Payment requests to Owner (each a "Payment

Request"). Each Payment Request from the Builder to the Owner shall be based upon the

progress of construction of the Home, subject to change as mutually agreed to by Builder

-3- No. 1-25-0772

and Owner in a writing signed by Builder and Owner. Each Payment Request shall include

(i) work and materials completed as of the date the Payment Request is made and (ii) any

deposits required to secure materials. Payment shall be made to Builder from the Owner

within five (5) days after receipt by Owner of a Payment Request provided that the Builder

shall: (i) have met with the Owner at the site to review improvements constructed in

accordance with such Payment Request: and (ii) have provided Owner with lien waivers

from each and every subcontractor and/or supplier or laborer for any and all of the work

and materials provided by them which relate to any portion of said Payment Request, which

lien waiver(s) shall acknowledge a waiver, release and relinquishment of any and all liens

or claims, or right of lien or claim fur any labor, work or materials furnished by them

through the date of the Payment Request.”

¶9 Khoshabe presented evidence at trial, primarily through his own testimony, that GT refused

to provide the lien waivers applicable to the final work on the project and that it was for that reason

he refused to make the final payment. In turn, GT presented evidence—through testimony of

Khoshabe, employees of GT, and GT’s subcontractors, as well as various written communications

between Khoshabe and GT entered into evidence—that it had been the parties’ practice throughout

the project to meet at the home to review work and then exchange lien waivers and payment.

However, when it came to the final payment request, Khoshabe repeatedly refused to meet at the

home with GT or make any payment.

¶ 10 After the parties finished presenting the evidence, Khoshabe made an oral motion for a

directed verdict on GT’s breach of contract counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas D. Cundiff v. Virginia Lee Washburn
393 F.2d 505 (Seventh Circuit, 1968)
Isidore Strauss v. Stratojac Corporation
810 F.2d 679 (Seventh Circuit, 1987)
Lawlor v. North American Corporation of Illinois
2012 IL 112530 (Illinois Supreme Court, 2013)
Erlenbush v. Largent
819 N.E.2d 1186 (Appellate Court of Illinois, 2004)
Van Der Molen v. Washington Mutual Finance, Inc.
835 N.E.2d 61 (Appellate Court of Illinois, 2005)
In Re Marriage of Auriemma
648 N.E.2d 118 (Appellate Court of Illinois, 1995)
Bright Horizons Children's Centers, LLC v. Riverway Midwest II, LLC
931 N.E.2d 780 (Appellate Court of Illinois, 2010)
Pedrick v. Peoria & Eastern Railroad
229 N.E.2d 504 (Illinois Supreme Court, 1967)
Donaldson v. Central Illinois Public Service Co.
767 N.E.2d 314 (Illinois Supreme Court, 2002)
Powers v. Rockford Stop-N-Go, Inc.
761 N.E.2d 237 (Appellate Court of Illinois, 2001)
Wade v. Rich
618 N.E.2d 1314 (Appellate Court of Illinois, 1993)
Maple v. Gustafson
603 N.E.2d 508 (Illinois Supreme Court, 1992)
Gandy v. Kimbrough
941 N.E.2d 329 (Appellate Court of Illinois, 2010)
Sandholm v. Kuecker
2012 IL 111443 (Illinois Supreme Court, 2012)
Walters v. Rodriguez
2011 IL App (1st) 103488 (Appellate Court of Illinois, 2011)
PML Development LLC v. Village of Hawthorn Woods
2023 IL 128770 (Illinois Supreme Court, 2023)
Ris v. Advocate Health and Hospitals Corp.
2023 IL App (3d) 220221-U (Appellate Court of Illinois, 2023)
Kulhanek v. Casper
2023 IL App (1st) 221454 (Appellate Court of Illinois, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2026 IL App (1st) 250772-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/khoshabe-v-grand-traditions-llc-illappct-2026.