Kevin Walsh v. Lend Lease (US) Construction, a/k/a Bovis Lend Lease, Inc. v. Rossi Electric Company, Inc.

155 A.3d 1201, 2017 WL 1104025, 2017 R.I. LEXIS 35
CourtSupreme Court of Rhode Island
DecidedMarch 24, 2017
Docket2016-82-Appeal. (NC 11-309)
StatusPublished
Cited by7 cases

This text of 155 A.3d 1201 (Kevin Walsh v. Lend Lease (US) Construction, a/k/a Bovis Lend Lease, Inc. v. Rossi Electric Company, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kevin Walsh v. Lend Lease (US) Construction, a/k/a Bovis Lend Lease, Inc. v. Rossi Electric Company, Inc., 155 A.3d 1201, 2017 WL 1104025, 2017 R.I. LEXIS 35 (R.I. 2017).

Opinion

OPINION

Justice Robinson,

for the Court.

The third-party plaintiff, Lend Lease (US) Construction (Lend Lease), appeals from the January 13, 2016 grant of summary judgment to the third-party defendant, Rossi Electric Company, Inc. (Rossi), in Newport County Superior Court. It further appeals from the denial of its cross-motion for summary judgment. 1 Lend Lease contends that the hearing justice erred in granting Rossi’s motion for summary judgment and denying its motion for summary judgment because Rossi was required to defend and indemnify Lend Lease under the terms of the contract between the parties. This case came before the Supreme Court for oral argument on January 25, 2017, pursuant to an order directing the parties to appear and show cause why the issues raised in this appeal should not be summarily decided. After a close review of the record and careful consideration of the parties’ arguments (both written and oral), we are satisfied that cause has not been shown and that this appeal may be decided at this time.

For the reasons set forth in this opinion, we vacate the judgment of the Superior Court.

I

Facts and Travel

The following facts are gleaned from the complaint in the instant case and the deposition of plaintiff, Kevin Walsh. In June of 2008, a construction project was ongoing at the Carnegie Abbey Tower in Portsmouth, R.I. Lend Lease was the general contractor on the project, and Rossi was a subcontractor doing electrical work. Mr. Walsh was employed by Comm-Tract Corporation, a subcontractor of Rossi. Mr. Walsh was doing “voice data, cable TV installation” on the project; he was “installing wiring throughout the building.” On June 16, 2008, Mr. Walsh was severely injured when he tripped on a can of plumber’s glue *1204 that was on the stairs between the first floor and the basement. On June 6, 2011, Mr. Walsh filed his complaint setting forth negligence claims against Lend Lease and against a subcontractor of Lend Lease doing plumbing work on the project — Delta Mechanical Contractors. Subsequently, Lend Lease filed the third-party complaint against Rossi with which we are concerned in this appeal.

In the third-party complaint, Lend Lease contended that Rossi was contractually obligated to “defend, indemnify, and hold harmless * * * Lend Lease from and against any claim, cost, expense, or liability, including costs and attorney’s fees, attributable to bodily injury caused by, arising out of, resulting from, or occurring in connection with the performance of the work at the 100 Willow Avenue project.” Lend Lease additionally alleged that Rossi breached the contract between the parties because, despite the fact that it was obligated to “procure a commercial general liability insurance policy, * * * for its work at the 100 Willow Avenue Project, which policy was to name * * * Lend Lease * * * as [an] additional insured[] under the policfy],” Rossi “has refused to afford coverage to * * * Lend Lease for Kevin Walsh’s claims * * On October 20, 2015 and November 10, 2015 respectively, Rossi and Lend Lease each filed motions for summary judgment. A hearing on the motions was held on December 7, 2015.

Subsequently, on January 13, 2016, an order entered granting Rossi’s motion for summary judgment and denying Lend Lease’s motion for summary judgment. Partial final judgment was entered on February 4, 2016, pursuant to Rule 54(b) of the Superior Court Rules of Civil Procedure. Lend Lease appealed from the decision of the Superior Court.

II

Standard of Review

When considering an appeal from cross-motions for summary judgment, we conduct a de novo review. 5750 Post Road Medical Offices, LLC v. East Greenwich Fire District, 138 A.3d 163, 166 (R.I. 2016); see also Rodrigues v. DePasquale Building and Realty Co., 926 A.2d 616, 622 (R.I. 2007). We have consistently stated that “[s]ummary judgment is appropriate when, viewing the facts and all reasonable inferences therefrom in the light most favorable to the nonmoving party, the [C]ourt determines that there are no issues of material fact in dispute, and the moving party is entitled to judgment as a matter of law.” 5750 Post Road Medical Offices, LLC, 138 A.3d at 166-67 (internal quotation marks omitted); see also Medical Malpractice Joint Underwriting Association of Rhode Island v. Charlesgate Nursing Center, L.P., 115 A.3d 998, 1002 (R.I. 2015). In conducting our review, “[w]e remain mindful of the fact that [s]ummary judgment is an extreme remedy that should be applied cautiously.” Hall v. City of Newport, 138 A.3d 814, 818 (R.I. 2016) (internal quotation marks omitted); see also Estate of Giuliano v. Giuliano, 949 A.2d 386, 390 (R.I. 2008).

III

Analysis

On appeal, Lend Lease contends that the hearing justice erred because Rossi must defend and indemnify Lend Lease “to the full extent permitted by Rhode Island law under the plain and unambiguous terms” of the contract between the parties and that, by not doing so, Rossi is in breach of that contract. Lend Lease relies on our decision in Rodrigues v. DePasquale Building and Realty Co., 926 A.2d 616 (R.I. 2007), contending that that *1205 decision is analogous to the instant case. It further posits that Mr. Walsh’s injuries are covered by the contractual provision at issue because they arose “in the course of his employment,” and it avers that Rossi’s obligation to indemnify and defend Lend Lease is not dependent on Rossi’s negligence having contributed to Mr. Walsh’s injury. Lend Lease asks this Court to vacate the judgment of the Superior Court and direct the entry of summary judgment in its favor or, in the alternative, remand the matter for further proceedings in Superior Court.

As we have stated, the “purpose of the summary judgment procedure is issue finding, not issue determination.” Estate of Giuliano, 949 A.2d at 391 (internal quotation marks omitted); see also Steinberg v. State, 427 A.2d 338, 340 (R.1.1981) (“[I]n ruling on a motion for summary judgment, the trial justice must look for factual issues, not determine them.”). After a thorough review of the record in the instant case, we have no difficulty in noting the presence of issues of material fact that remain to be determined. Accordingly, in our judgment, this case was not ripe for summary judgment.

We turn our attention, initially, to the contract provision forming the basis of this dispute:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omni Hotels Mgmt. Corp. v. Ultimate Parking
61 F.4th 215 (First Circuit, 2023)
Betty Belmore v. Cheryl Petterutti
Supreme Court of Rhode Island, 2021
Hexagon Holdings, Inc. v. Carlisle Syntec Incorporated
199 A.3d 1034 (Supreme Court of Rhode Island, 2019)
Phil Bartlett v. Dr. David Coppe.
159 A.3d 1065 (Supreme Court of Rhode Island, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
155 A.3d 1201, 2017 WL 1104025, 2017 R.I. LEXIS 35, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kevin-walsh-v-lend-lease-us-construction-aka-bovis-lend-lease-inc-ri-2017.