Kevin M. Higgins and Sue E. Higgins v. Abigail J. Ferrari and Emmitt F. Smith

474 S.W.3d 630, 2015 Mo. App. LEXIS 1188
CourtMissouri Court of Appeals
DecidedNovember 17, 2015
DocketWD78327
StatusPublished
Cited by30 cases

This text of 474 S.W.3d 630 (Kevin M. Higgins and Sue E. Higgins v. Abigail J. Ferrari and Emmitt F. Smith) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kevin M. Higgins and Sue E. Higgins v. Abigail J. Ferrari and Emmitt F. Smith, 474 S.W.3d 630, 2015 Mo. App. LEXIS 1188 (Mo. Ct. App. 2015).

Opinion

Gary D. Witt, Judge

Appellants Kevin Higgins (“Kevin") 1 and Sue Higgins (collectively “the Higgins-es”) appeal the trial court’s entry of judgment on all counts in favor of Respondents Abigail Ferrari (“Abigail”) and Emmitt Smith (“Smith” and collectively the “Respondents”). The Higginses claim that the Respondents conspired with Tony Ferrari (“Tony”) to fraudulently transfer money received from the Higginses to a bank account controlled by Respondents, thereby placing those assets out of the reach of the Higginses in their attempts to satisfy their claims against Tony.

The Higginses raise three points on appeal. The Higginses argue that the trial court’s judgment erroneously declared and applied the law and was against the weight of the evidence regarding their claims for fraudulent transfer and civil conspiracy to commit fraud. We affirm.

FACTUAL BACKGROUND 2

This case arises out of the failed construction of an out building by Tony for the Higginses. Sometime in 2000 or 2001, Kevin was driving near his home and saw a steel building that was similar to one that he! wanted constructed on his property. Kevin received a referral from the owner of that building to Tony, who had constructed it. Tony began erecting steel buildings in 1982 and started his own business in 1989. By the time of these events, he‘had erected approximately two hundred steel buildings.

Plans to construct the Higginses’ building did not begin, in earnest until the Summer of 2002. Kevin initially .wanted to construct a building that was three hundred feet long, in which he could board and train horses. However, Tony’s estimate for the cost of a building this size was toó expensive for the Higginses, so Tony was asked to reconfigure the bid for a smaller building. Tony normally purchased the materials for the buildings he would 1 erect from a company called' Worldwide Buildings (‘Worldwide”), but' even the reconfigured smaller building was larg *633 er than those .manufactured- by Worldwide. 3

Tony, therefore, sought bids from another company, Colonial Buildings (“Colonial”), and contacted his stepfather, Smith, who was also in the construction trade, to obtain a bid from Alliance Steel Building Systems (“Alliance”).- The bid from Alliance was significantly lower than the bid Tony received from Colonial. Tony could not directly order a building from Alliance because he was not an Alliance dealer. Smith, however, was able to obtain the building due to a previous business relationship with Alliance. Up to the time of trial, this was the only, building Tony ever purchased through Smith in all the years he had been working to erect steel buildings. ■ ..

Tony cpntacted Kevin and informed him of the estimate for a 168 foot long building from Alliance. Higgins agreed to provide a $10,000.00 deposit to hold the price, for the building. - Kevin gave Tony a $10,000.00 check for the deposit, payable to Tony Ferrari, which was' endorsed by Tony and his wife, Tammy, and deposited into Tammy’s bank account. Although it is unclear from the record, there appears to have been a transfer of $5,000 from this payment into Respondents’ Account from which Alliance was paid a $4,000 deposit on the building. This issue does not need to be resolved for purposes of this opinion.

In early August of 2002, Tony provided Kevin a written contract for the construction of the building. According to the terms of the contract, the total pnce of the building was $182,163.00. , Less the $10,000.00 deposit previously conveyed,- the remaining balance on the contract was $172,163.00 to be paid in three installments. The first payment of $60,257.00 would;be paid as a down payment. The second payment of $86,081.55 would be due at the time of delivery of the building materials and would, be paid in two installments of $78,340.00 and $7,741.55. .-Finally, the last payment of $25,824.45 would be made when, the budding was completed.

-Tony received two checks from the Hig-ginses at issue in this litigation; the first check he received on September 3, 2002 in the, amount, of $60,257.00 and the second check on October 9, 2002 in the amount of $78,340.00. Rather than deposit these checks into -his wife’s account, as he had done with the original $10,000.00 deposit, these two checks were deposited into a bank account owned by Abigail, Tony’s mother. This account was an account previously used by Abigail and Smith as a business account (“Respondents’ Ac- ’ count”) 4 .

Tony testified that he deposited the 'funds into Respondents’ Account because he was having marital issues, and Tony and the Respondents wanted to make sure that the building being purchased from Alliance would bé paid for, as Smith was the person ordering the building from Alliance and would be. liable for the costs. The total amount actually deposited into Respondents’ Account was $135,597.00. 5

Abigail drafted a check out of Respondents’ Account for $76,630.00 and delivered *634 it to Alliance, at which time the remaining balance owed to Alliance on the building was paid in full. There is no dispute that Alliance was paid in full and there is no dispute that all the building materials for the project were delivered to the Higgins-es’ property. The dispute between the Higginses and the Respondents pertains to the funds remaining in the Respondents’ account, which totaled $58,987.00. Apart from payment to Alliance for the building, the evidence shows that the following sums were subsequently withdrawn from the Respondents’ Account:

• $6,000.00 paid to Colonial for doors for the building that were purchased from Colonial rather than Alliance;
• $2,500.00 paid to Tony with a note indicating it was used for payroll; 6
• $17,000.00 paid to Tony with a note indicating it was used for building ma- ■ terials;
• $660.32 paid to United Rentals;
• $1,285.70 paid tó Case Credit Corp. for equipment used for the building;
• $2,500.00 paid to Smith as commission for obtaining the building from Alii-, anee;
• $825.28 paid to Smith to reimburse his expenses for a trip to Oklahoma to the manufacturer’s building site to exchange wrong parts which had been shipped for the building.

The trial court found the evidence presented by Tony was credible and that these amounts were all spent on the Higginses’ building project. The total of these expenditures was $30,771.30. The total from the amounts above when added to the price paid to Alliance for the building out of Respondents’ Account was $111,401.30. 7 Therefore, subtracting 'this amount from the total deposited for this project into Respondents’ account ($135,597.00) leaves a balance of $24,195.70.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pasch v. OnDoc, LLC
E.D. Missouri, 2023
Pearson v. Gittemeier
E.D. Missouri, 2022
Excellent Home Properties, Inc v. Candice Kinard
998 F.3d 352 (Eighth Circuit, 2021)
ServisFirst Bank v. Young
E.D. Missouri, 2020
Fink v. Wright
W.D. Missouri, 2019
Loutzenhiser v. Best
565 S.W.3d 723 (Missouri Court of Appeals, 2018)
A.O.A. v. Rennert
350 F. Supp. 3d 818 (E.D. Missouri, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
474 S.W.3d 630, 2015 Mo. App. LEXIS 1188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kevin-m-higgins-and-sue-e-higgins-v-abigail-j-ferrari-and-emmitt-f-moctapp-2015.