Kesting v. Donahue

13 Ohio C.C. 653
CourtOhio Circuit Courts
DecidedJanuary 15, 1895
StatusPublished

This text of 13 Ohio C.C. 653 (Kesting v. Donahue) is published on Counsel Stack Legal Research, covering Ohio Circuit Courts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kesting v. Donahue, 13 Ohio C.C. 653 (Ohio Super. Ct. 1895).

Opinion

King, J.

This case comes into this court on appeal from the common pleas court of this county. The action is brought by Joseph Keating to foreclose a mechanic’s lien, and to establish the amount, validity and priority of mechanics’ liens as well as certain mortgages.

The plaintiff was a sub-contractor, who did the mason work under a contract with the defendant, Michael Weibel, the principal contractor, and the other lienors are material and labor men who furnished material and labor for Michael Weibel, the principal contractor, and upon the building in question. The evidence in the case establishes, without contradiction, the following facts:

That the defendant, Lena Donahue, was the owner of a lot in Toledo, and her husband, Michael Donahue, desired to erect thereon a building to be used as a residence and store room. Having no money to pay for the building, he applied to the defendant, The Mutual Aid Building & Loan Company, by a written application, dated May 15, 1893, to which he signed the name of Lena Donahue and of Michael Donahue, and in this case, so far as Michael has acted, he has acted as the agent of his wife. The application for a lean was referred by the Loan Company to a committee to examine the property, and the committee made a report in writing, finding that the lot was worth .$750; that it was proposed to erect a building thereon worth about $2,600,and they recommended that the loan be made to the amount of $2,200. This application and report was then referred tc the attorney of the corporation, who on June 15, a month after the original application was signed, reported that the title of the property was all right, and on June 15, 1893, Michael Donahue andjiiswifej executed to the Loan Com[655]*655pany a mortgage upon these premises for the sum of $2,200, the mortgage reeiting that the money has been paid, and is, in the mortgage, receipted for. It was, however, outside of the mortgage, the understanding of the parties that it should not all of it be then paid. On the 20th of May, five days after the application to the Lean Company had been made, and probably after Donahue had received an assurance that the Loan Company would let him have the money, he entered into a contract with Michael Weibel to erect and complete the building in question for the sum of $2,698, to be payable in installments as the work progressed. On June 15th the first installment became due on this contract, that, by the terms of it being payable when the cellar walls should be up ready to receive the superstructure. And on this day, as uefore stated, the Building & Loan Company received the mortgage, and on that day advanced and xiaid on account of their agreement to loan, the sum of $23.60 to Mr. Donahue, and on his order, paid to Weibel, the contractor, $500, making the total sum of $523.60.

On the 24th day of July, a second installment became due to Michael Weibel on the contract, and the Loan Company were again called upon to make a payment. Before making a second payment, they required that the owner and Weibel, the contractor, should execute a x')aPer setting forth the material conditions of the contract between them, and on the part of Weibel waiving any right to a mechanic’s lien. This having been signed both by Donahue and Weibel, the Loan Company on that day paid directly to Donahue $56, and to Weibel, on the order of Donahue, $600, making on that day $656, or a. total amount up to this date of $1,179.60.

On August 8, they paid to Donahue directly $28 more, making the total amount advanced on account of the loan $1,207.60, and then leaving to be yet advanced, $992.40. It appears that of the $600 paid to Weibel $550, went directly to the defendants, Chesbrough Bros., and this was with the knowledge of the Loan Company. Chesbrough Bros, had furnished some lumber towards the erection of the building, and had an account for it amounting to about $550; but the contractor, Weibei, was indebted to them in an amount of more than $600 for materials furnished to other buildings.

On August 22, 1893, the building was nearly completed. The work then remaining to be done was afterwrds performed at a cost of $117.55. At this date the work came to a standstill, and Weibel was unable to pay his men,and they refused to work until paid. The material men were also demanding [656]*656their pay; the Loan Company was also insisting that as it appeared that Donahue would have to borrow more money in order to pay the contract price, that he should make such arrangement, which must in any event be subsequent to the lien of the Loan Company, and which would release the contract to the extent of the difference between the' amount to be furnished by the Loan Company, and the amount of the contract, which, including certain small sums advanced to Donahue, was said to be about $600.

Donahue undertook to borrow that amount of money, but could find no one willing to loan it and take a mortgage subject to the Loan Company’s mortgage, until after some talk, Weibel had arranged with Chesbrough Bros, to accept from him, Weibel, as a payment of his indebtedness to them a mortgage for $600, to be given by Donahue subject to the mortgage of the Loan Company, and which mortgage Weibel was willing to accept as a payment to him on the contract of $600. Accordingly Donahue and his wife gave the note and mortgage for $600 to Weibel, who transferred it to Chesbrough Bros. At this time, August 22, the third installment, amounting to $800, was past due. The work required to be performed in the contract before it was due had been completed, and some additional. No liens had been filed, no notice had been served of an intention to procure liens, although Donahue knew that the labor men, many of them, had not been paid, but he gave the mortgage and note to satisfy his contract with Weibel to the extent of $600, and because the Loan Company had so far refused to advance any more money until some arrangement should be made having this effect. Thereupon Donahue and Weibel went to the office of the Loan Company. What took place there, is in dispute.

We find from the evidence that a Mr. Schmidt was the secretary of the Loan Company, and was in the office at the time when Donahue and Weibel came. That Donahue and Weibel informed him that the $600 that had been previously spoken about had been arranged for. That Chesbrough Bros, had taken the mortgage. Thereupon Schmidt telephoned to the office of Chesbrough Bros., who responded to the effect that they had done so. Schmidt on the witness stand claims that he had misunderstood both the conversation and the telephone. That it was his understanding at the time that Chesbrough Bros, had taken a mortgage and had advanced $600 to Donahue, and he supposed that Weibel had had the benefit of $600 in money. There does not appear in the evi[657]*657dence any reason for that misunderstanding. But it is not deemed material. Schmidt had been insisting that Donahue should take care of the contract to the extent of $600, and the effect of the mortgage made to Weibel and transferred to Chesbrough Bros., was to do exactly that.

We conclude as a matter of law, that the mortgage was made and accepted by Weibel as a payment upon his contract. That Donahue had right to make it in that way, and Weibel a right to accept it, and the mortgage is valid in the hands of Chesbrough Bros., but will be subject to the mortgage of the Loan Company. .

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
13 Ohio C.C. 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kesting-v-donahue-ohiocirct-1895.