Kesting v. Donahoe

6 Ohio Cir. Dec. 262
CourtLucas Circuit Court
DecidedMarch 16, 1895
StatusPublished

This text of 6 Ohio Cir. Dec. 262 (Kesting v. Donahoe) is published on Counsel Stack Legal Research, covering Lucas Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kesting v. Donahoe, 6 Ohio Cir. Dec. 262 (Ohio Super. Ct. 1895).

Opinion

King, J.

This case comes into this court on appeal from the common pleas court of this county. The action is brought by Joseph Kesting to foreclose a mechanics’ lien, and to establish the amount, validity and. priority of mechanics’ liens, as well as certain mortgages.

The plaintiff was a subcontractor, who did the mason work under a contract with the defendant, Michael Weibel, the principal contractor, and the othen lienors are material and labor men who furnished material and labor for Michael Weibel, the principal contractor, and upon the building in question. The evidence in the case establishes without contradiction, the following facts:

■ That the defendant, Lena Donahoe, was the owner of a lot in Toledo, and her husband, Michael Donahoe, desired to erect thereon a building to be used as a residence and store room. Having no money to pay for the building, he applied to the defendant, The Mutual Aid Building and Loan company, by a written application, dated May 15,1893, to which is signed the name of Lena Donahoe and of Michael Donahoe, and in this case, so far as Michael has acted, he has acted as the agent of his wife. The application for a loan was referred by the Loan company to a committee to examine the property, and the committee made a report in writing, finding that the lot was worth $750; that it' was proposed to erect a [263]*263building thereon worth about $2,600, and they recommended that the loan be made to the amount of $2,200. This application and report was then referred to the attorney of the corporation, and on June 15, a month after the original application was signed, reported that the title of the property was all right, and on June 15, 1898, Michael Donahoe and his wife, executed to the Doan company a mortgage upon these premises for the sum of $2,200, the mortgage reciting that the money has been paid, and is, in the mortgage receipted for. It was, however, outside of the mortgage, the understanding of the parties that it should mot all of it be then paid. On the 20th of May, five days after the application to the Doan company had been made, and probably after Mr. Donahoe had received an assurance that the Doan company would let him have the money, he entered into a contract with Michael Weibel to erect and complete the building in question for the sum of $2,698, to be payable in installments as the work progressed. On June 15, the first installment became due on this contract, that, by the terms -of it being payable when the cellar walls should be up ready to receive the superstructure. And on this day, as before stated, the Building and Doan company received the mortgage, and on that day advanced and paid on account of their agreement to loan the sum of $23.60, to Mr. Donahoe and on his order paid to Weibel, the contractor, $500, making the total sum $523.60.

On the 24th day of July a second installment became due to Michael Weibel on the contract, and the Doan company were again called upon to make a payment. Before making a second payment, they required that the owner and Wei-bel, the contractor, should execute a paper setting forth the material conditions of the contract between them, and on the part of Weibel waiving any right to a mechanics’ lien. This having been signed both by Donahoe and Weibel, the Doan company on that day paid directly to Donahoe $56, and to Weibel on the order of Donahoe $600, making on that day, $656, or a total payment up to this •date of $1,179.60.

. On August 8, they paid to Donahoe directly $28 more, making the total amount advanced on account of the loan, $1,207.60, and then leaving to be yet advanced, $992.40. It appears that of the $600 paid to Weibel $550 went directly to the defendants, Chesbrough Bros., and this was with the knowledge of the Doan company. Chesbrough Bros, had furnished some lumber towards the erection of the building and had an account for it amounting to about $550, but the •contractor, Weibel, was indebted to them in an amount of more than $600 for material furnished to other buildings.

On August 22, 1893, the building was nearly completed. The work then remaining to be done was afterwards performed at a cost of $117.55. At this date the work came to a standstill and Weibel was unable to pay his men, and they refused to work until paid. The material men were also demanding their pay;, the Doan company was also insisting that as it appeared that Donahoe would have to borrow more money in order to pay the entire contract price, that he should make such arrangement, which must in any event be subsequent to the lien of the Doan company, and which would release the contract to the extent of the difference between the amount to be furnished by the Doan company, and the amount of the contract, which including certain small sums advanced to Donahoe was said to be about $600.

Donahoe undertook to borrow that amount of money, but could find no one willing to loan it, and take a mortgage subject to the Doan company’s mortgage, until" after some talk Weibel had arranged with Chesbrough Bros, to accept from him, Weibel, as a payment on his indebtedness to them a mortgage for $600, to be given by Donahoe, subject to the mortgage of the Doan company, and which mortgage Weibel was willing to accept as a payment to him on the contract of $600. Accordingly Donahoe and his wife gave the note and mort.gage for $600 to Weibel, who transferred it to Chesbrough Bros. At this time, August 22, the third installment, amounting to $800, was past due. The work required to be performed in the contract before it was due had been completed, [264]*264and some additional. No liens had been filed, no notice had been served of an. intention to procure liens, although Donahoe knew that the labor men, many of them had not been paid, but he gave the mortgage and note to satisfy his contract with Weibel to the extent of $600, and because the Doan company had SO' far refused to advance any more money until some arrangement should be made having this effect. . Thereupon Donahoe and Weibel went to the office of the Doan company. What took place there is in dispute.

We find from the evidence that a Mr. Schmitt, was the secretary of the Doan company, and was in the office' at the time when Donahoe and Weibel came. •That Donahoe and Weibel informed him that the $600.00 that had been previously spoken about, had been arranged for. That Chesbrough Bros, had taken the mortgage. Thereupon Schmitt telephoned to the office of Chesbrough Bros., who responded to the effect that they had done so. Schmitt, on the witness stand, claims that he misunderstood both the conversation and the telephone. That it was his understanding at the time that Chesbrough Bros, had taken.a mortgage, and had advanced $600.00 to Donahoe, and he supposed that Weibel had had the benefit of $600.00 in money. There does not appear in the evidence any reason for that understanding. But it is not deemed material. Schmitt had been insisting that Donahoe should take care of the contract to the extent of $600, and the effect of the mortgage made to Weibel and transferred to Chesbrough Bros., was to do exactly that.

We conclude, as a matter of law, that the mortgage was made and accepted by Weibel as a payment upon his contract. That Donahoe had a right to make it in that way, and Weibel a right to accept it, and the mortgage is valid in the hands of Chesbrough Bros., but will be subject to the mortgage of the Doan company.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
6 Ohio Cir. Dec. 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kesting-v-donahoe-ohcirctlucas-1895.