Kern River Gas Transmission Co. v. 6.17 Acres of Land, More or Less, in Salt Lake County

156 F. App'x 96
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 2, 2005
Docket04-4033
StatusUnpublished
Cited by14 cases

This text of 156 F. App'x 96 (Kern River Gas Transmission Co. v. 6.17 Acres of Land, More or Less, in Salt Lake County) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kern River Gas Transmission Co. v. 6.17 Acres of Land, More or Less, in Salt Lake County, 156 F. App'x 96 (10th Cir. 2005).

Opinion

ORDER AND JUDGMENT *

EBEL, Circuit Judge.

After examining the briefs and appellate record, this panel has determined unanimously to grant the parties’ request for a decision on the briefs without oral argument. See Fed. R.App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument.

Plaintiff Kern River Gas Transmission Co. filed an action under the Natural Gas Act, 15 U.S.C. § 717f(h), to condemn certain property in Utah, including property owned by defendant JMS-Meadow, for an interstate natural gas pipeline. The district court granted immediate occupancy of the JMS-Meadow property to Kern River, and later held a bench trial to determine the value of the easement. JMS-Meadow appeals the district court’s decisions excluding it from presenting expert testimony, the expert’s report, or other documents at the bench trial and refusing to reopen the trial to take additional testimony. We affirm. 1

The relevant facts are largely undisputed. The parties scheduled a Fed.R.Civ.P. 26(f) attorney’s planning meeting on November 18, 2002. When JMS-Meadow did not send a representative, Kern River *99 postponed the meeting and allowed JMS-Meadow to participate by telephone. After the parties set dates at the meeting, Kern River agreed, at JMS-Meadow’s request, to adjust those dates back one month. On January 22, 2008, Kern River filed the Attorneys’ Planning Meeting Report with the district court, explaining that JMS-Meadow failed to sign the report despite Kern River making several requests for it to do so. The report stated that the parties would make initial disclosures by February 3, submit expert reports by February 28, and complete discovery by May 30.

JMS-Meadow failed to meet the Fed. R.Civ.P. 26(a) initial disclosures date of February 3. It ignored Kern River’s later requests for initial disclosures. JMS-Meadow still had not met the initial disclosures requirements by February 26, the date of the initial pretrial conference. At that conference, the magistrate judge extended the time for JMS-Meadow to provide its initial disclosures to March 31. The magistrate judge also ordered disclosure of JMS-Meadow’s expert reports by April 30, a date two months beyond the time agreed by the parties. The magistrate judge left May 30 as the discovery cut-off date and set August 7 as the trial date.

JMS-Meadow did not provide initial disclosures by the new date of March 31. Nor did it request an extension of time to do so. In response to an April 10 request by Kern River for initial disclosures, JMS-Meadow, on April 16, sent an initial disclosures pleading with no documents attached. On April 22, Kern River requested the documents referred to in the initial disclosures, but JMS-Meadow did not produce them.

Although the magistrate judge had ordered disclosure of the expert reports by April 30, JMS-Meadow again failed to comply. On May 12, Kern River agreed to allow JMS-Meadow until May 16 to provide its initial disclosures documents and its expert report. But Kern River clarified that in light of the May 30 discovery deadline, it would not agree to any further extensions and would seek to exclude any evidence not produced by May 16. It noted that the discovery cut-off date was three weeks away, and JMS-Meadow’s actions were to the point of prejudicing Kern River. On May 16, JMS-Meadow provided Kern River a letter from its appraiser, William Lifferth, indicating that he had done a “preliminary investigation,” but not an appraisal or report. Aplt.App., Vol. I at 184 02, 184 04. JMS-Meadow also provided a letter from Scott Turville, the manager of JMS-Meadow, criticizing Kern River’s expert report.

On May 28, Kern River sent notice to JMS-Meadow that it would take depositions on May 30, the last day of the discovery period, of JMS-Meadow’s designated fact witnesses, Mr. Turville and Hal Rosen, its accountant, and of its expert, Mr. Lifferth. JMS-Meadow sought an extension of time from Kern River, which was denied. JMS-Meadow then failed to produce these persons for deposition. On the May 30 ending date for discovery, Kern River filed, pursuant to Fed.R.Civ.P. 37, a motion to exclude JMS-Meadow’s evidence at trial or to compel and for sanctions, arguing that no documents had been produced during discovery as required by Rule 26(a)(1)(B) and (C), JMS-Meadow’s witnesses had not appeared for depositions, JMS-Meadow did not provide an expert report complying with Rule 26(a)(2), the discovery period had ended, and the trial date was two months away. JMS-Meadow countered with a motion for protective order asserting that it had not received sufficient time before the depositions were to be taken, and Kern River *100 refused to permit an extension. JMS-Meadow, for the first time in its reply in support of its motion for protective order, indicated that Mr. Turville, who allegedly was the only person who could act on JMS-Meadow’s behalf, was dealing with family and personal health issues.

The magistrate judge granted Kern River’s motion and denied JMS-Meadow’s motion. The magistrate judge ordered JMS-Meadow to produce its two fact witnesses for deposition and precluded, pursuant to Rule 37, JMS-Meadow from introducing at the trial any expert evidence or documents not produced during discovery. The magistrate judge found that JMS-Meadow had failed to comply with Rule 26(a) despite the scheduling order and receiving numerous extensions and that Kern River would be prejudiced by further delay.

JMS-Meadow appealed to the district court arguing that Rule 26(a)(1)(B) only requires identification and not production of documents; Kern River did not make a Fed.R.Civ.P. 34 document request; there was no Rule 26(a) failure to produce documents; even if there had been a Rule 26(a) violation, there was no prejudice to Kern River; JMS-Meadow should have been given an opportunity to cure; there was still time to cure; JMS-Meadow did not act in bad faith; and Mr. Lifferth’s report was only technically deficient. The district court upheld the magistrate judge’s order.

Thereafter, the district court held a bench trial on the issue of just compensation for the land taking. The evidence showed that based on Kern River’s easement, JMS-Meadow would lose 67 townhouse units from the total 465 housing units that West Valley City, Utah had approved for JMS-Meadow’s townhouse and condominium development. Gary Free, Kern River’s expert witness, testified that any alterations to the approved plan would require another approval by West Valley City, but that Steve Pastorik of the city planning department had told Mr. Free that any revision would be done administratively and would not require a public hearing process. Aplt.App., Vol. II at 558, 565 (trial testimony); Aplee App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
156 F. App'x 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kern-river-gas-transmission-co-v-617-acres-of-land-more-or-less-in-ca10-2005.