Kerby v. Road Improvement District No. 4

251 S.W. 356, 159 Ark. 21, 1923 Ark. LEXIS 7
CourtSupreme Court of Arkansas
DecidedMay 21, 1923
StatusPublished
Cited by4 cases

This text of 251 S.W. 356 (Kerby v. Road Improvement District No. 4) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kerby v. Road Improvement District No. 4, 251 S.W. 356, 159 Ark. 21, 1923 Ark. LEXIS 7 (Ark. 1923).

Opinion

McCulloch, C. J.

The road improvement district involved in this controversy was organized in Saline County by order of the county court, pursuant to general statutes (Crawford & Moses’ Digest, § 5399 et seq.), for the purpose of constructing a highway beginning at the end of Arch Street, at the Pulaski County line, and running thence 6.4 miles south, through Saline County, to the Grant County line.

Appellant Kerby entered into a contract with the district to build the road in accordance with the, plans and specifications prepared by the engineer, and he gave bond to the district in the sum of $15,000, in accordance xvith the statute (Crawford & Moses’ Digest, § 5446), for the faithful performance of his contract, and containing an obligation to pay for all labor and materials supplied by any and all persons.

The contract between appellant Kei’by and the district was in writing, and he entered into an oral subcontract xvith T. H. Read for the latter to do the grading work on a mile of-the road. After the completion of the work, Read claimed a balance due him on his contract in the sum of .$617.50, and this action was instituted in the name of the district, for the benefit of Read, against appellant Kei’by and the sureties on his bond, O. B. Field and W. A. Baxley.

Appellant Kerby admitted liability to Read in the sum of $312.75, but denied liability for the remainder of the amount claimed. The -sureties pleaded that they were discharged from liability on the bond by reason of material changes in the contract between Kerby and- the. i district. Kerby also claimed, in his defense, that under the contract with Read' there was to be a retained percentage of the contract price until completion of the road, and that the road had not been completed.

There was a trial of the issues before a jury, and the verdict was in favor of appellee for the full amount of Read’s claim.

There is really no dispute in the evidence as to the correctness of the items in Read’s claim, but the dispute arises over the question of the liability of appellant for payment of the same.

The amounts in dispute are divided into two items, the first being the sum of $204.75 for what is .termed the “fourth estimate” of Read’s work, and the remaining item of $100 is for clearing and pulling stumps from two acres of ground.

. Kerby claims that he is not liable for the item of $204.75, for the reason that it was not in Ms contract with the district, and that the work was done by Read under what is termed “force account,” by direction of the engineer of the district.

Appellant requested the court to instruct the jury that if “the engineer for the district had authority to order work done for the district other than contemplated in the contract between the district and defendant Kerby, and that he directed the plaintiff to do other work than that embraced in Kerby’s contract, and that no payment was made or allowed to Kerby. by the district, you are instructed that the defendant. Kerby. .would not be liable to the plaintiff for the. amount of such woi’k.” We do not think that the evidence warranted this instruction, for, according to the evidence, the work covered by this estimate was within the contract between Kerby and the district, and also was in the contract between Kerby and Read. The work was back-filling at bridges and culverts. The evidence showed that, under the contract, the engineer had the right to direct Kerby to do any work necessary for the construction of the road, whether specified or not, and the engineer, who was introduced as a witness by appellants, testified that it was inconvenient for Kerby to go back to that work to do it, and that for that reason he directed the work to be done by Read. The proof shows that this was in Read’s contract. Since this is true, Kerby cannot escape liability because an allowance was not made to him for the work. All that the proof shows is that the work was under what is called “force account,” and that the estimate was made directly to the district by Read. Of course, Kerby is entitled to credit for this in his settlement with the district, but the fact that it has not been credited to Kerby by the district does not release Kerby from his obligation to pay the subcontractor.

As to the other item of $100 for clearing and grubbing, the proof shows that this work was embraced in Kerby’s contract with the district, and that he was to receive $125 an acre. It is not embraced in the original contract between Kerby and Read, but Kerby’s foreman made a contract with Read to do this work on two acres of ground at $50 per acre. Kerby testifies that the foreman had no authority to make this contract, but he does not claim that it was done by Read without his knowledge, and he is deemed to have ratified the unauthorized acts of his foreman.

Error of the court is assigned in submitting to the jury the issue concerning the retention of the percentage. The court told the jury, in substance, that, if there was an agreement between Kerby and Read that fifteen per centum was to be retained until the entire road was completed by Kerby, there should be no verdict for the amount of the retained percentage, but, on the other hand, if there wás no agreement for the retention of the percentage, the amount should not be deducted from Read’s recovery. There was conflicting testimony on this subject, and it' was proper to submit the issue to the jury. Kerby testified that there was an express agreement between him and Read that fifteen per cent, should be retained, but Read testified that there was no such agreement. This made an issue for the jury to settle.

It is contended on behalf of the sureties that they were discharged by reason of material changes in the contract, and error is assigned in the refusal of the court to submit that issue to the jury. Appellants invoke the familiar rule that sureties are bound only by the letter of their contract, and that any alteration of the contract between the principals discharges the sureties.

The obligation of the bond executed by the sureties was based upon the contract between Kerby and the district, and there is a clause in the contract which authorizes changes, both material and immaterial. Paragraph 27 of the contract provides that the engineer, with the consent of the board, can “alter or change any detail in the material or method of construction, or the - location of roadway or grade, which would not materially increase or decrease the cost of the work, without additional compensation to the contractor.” In the same section it is further provided that “important changes or alterations may be made, but the contractor shall not proceed with such changes or ' alterations without written orders from the engineer. The price covering such changes or alterations shall be fixed by agreement between the engineer and the contractor.” Now, this is a clear agreement for immaterial changes to be made by the engineer, or material changes to be made by agreement between the engineer and the contractor. The engineer had no right to make material changes without the consent of the contractor, but any changes made in accordance with the contract, however material, did not discharge the sureties from liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lakeside Bridge & Steel Co. v. Duvall
19 S.W.2d 1107 (Supreme Court of Arkansas, 1929)
Fulghum & Union Indemnity Co. v. State
109 So. 644 (Supreme Court of Florida, 1926)
Ætna Casualty & Surety Co. v. Henslee
260 S.W. 414 (Supreme Court of Arkansas, 1924)
Altman v. Sproles
255 S.W. 573 (Supreme Court of Arkansas, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
251 S.W. 356, 159 Ark. 21, 1923 Ark. LEXIS 7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kerby-v-road-improvement-district-no-4-ark-1923.