Kentucky Lumber & Millwork Co. v. George H. Rommel Co.

78 S.W.2d 52, 257 Ky. 371, 1934 Ky. LEXIS 563
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedNovember 30, 1934
StatusPublished
Cited by3 cases

This text of 78 S.W.2d 52 (Kentucky Lumber & Millwork Co. v. George H. Rommel Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kentucky Lumber & Millwork Co. v. George H. Rommel Co., 78 S.W.2d 52, 257 Ky. 371, 1934 Ky. LEXIS 563 (Ky. 1934).

Opinion

*372 Opinion op the Court by

Judge Perry

Affirming.

This is an appeal from a judgment of the Jefferson circuit court (chancery branch) in an action brought under the Declaratory Judgments Act (Civ. Code Prac. sec. 639a-1 et seq.) for a declaration of the rights of the parties under a contract to furnish millwork and under which, as construed, it was declared and adjudged that the appellee, George H. Rommell Compay, should recover of the appellant damages in the sum of $4,410 with interest and costs for its breach.

It appears that the appellee, George H. Rommell Company, was a building contractor and as such had contracted with the Board of Education of Louisville to construct a city school building* according to certain agreed plans and specifications. Further, having so contracted, it let to the appellant a subcontract to furnish and install in the building, as its construction advanced, certain wooden millwork called for by the building specifications at a price of $18,000. After so contracting, the appellant proceeded to manufacture in its own lumber and millwork plant the special woodwork therefor as required, up until July, 1933, when its one planing mill was totally destroyed by fire. The appellant thereupon, for the purpose of avoiding delay in construction of the building, arranged with the Anderson Manufacturing Company of Louisville to immediately fulfill its contract obligation with the Rommell Company, by manufacturing and furnishing from its own mill plant the specified finished woodwork as required. Such arrangement continued until the following September, when appellant notified the Rommell Company that, because of the destruction by fire of its mill plant in the prior July, it had been deprived of the means of performing its contract to manufacture and install this millwork; that, by reason of such fortuitious loss of its mill, it was excused from further performance of the contract; and that for such cause both parties were released from liability thereunder.

The appellee not agreeing with appellant’s position or claim in this and acting upon its refusal to further perform its contract, it arranged with the Anderson Manufacturng Company to fulfill appellant’s unfinished contract by manufacturing and delivering from its mill the millwork covered by the appellant’s contract. This subtitution of the Anderson Manufacturing Company for the appellant, to fulfill the latter’s contract, was secur *373 ed at an additional cost of $6,000, and as to the payment of which extra cost a controversy has arisen between the contracting parties as to whose is the liability therefor.

For the determination of this question, the appellant instituted its action, as stated, seeking a construction of their contract of October, 1932, and for a declaration of the rights of the parties thereunder.

Upon submission of the cause upon the pleadings, agreed stipulation of facts and .additional proof taken, it was adjudged and declared by the court that the Eommell Company was entitled under the contract to recover this additional amount of $6,000 paid the Anderson Manufacturing Company for fulfilling appellant’s contract (which it had refused to carry out), subject to a credit thereon by the amount owing it, at the contract price, for such millwork as it had made and delivered the appellee prior to its .September notice disclaiming further obligation under the contract to perform. In so holding, the court construed the parties’ contract as one obligating plaintiff to furnish the specified millwork as required at the agreed price of $18,000 and that the continued existence of the appellant’s mill was not by- the parties made a condition of its performance and that neither from the language of the -contract nor the facts and circumstances surrounding its making could it be inferred that it was within the contemplation of the parties to regard the subsequent continued existence of appellant’s particular mill as being a necessary means for performing the contract or as an implied subsequent condition thereof. The learned chancellor, in his written opinion announcing the grounds or legal principles upon which his judgment was based, states, in substance, his conclusion to be that if it were in contemplation of the parties that the appellant was to furnish from its mill, and only from its mill, the contracted millwork, the destruction of the mill might then excuse its further performance;' but that, in order to find such a condition existed within the contemplation of the contracting parties, the court must read it into the contract, which was not here to be done, as it was evident that such an implied condition was not contemplated by the appellant company for the reason that, after the burning of its mill, it went ahead, on its own initiative and responsibility, and had another *374 planing mill finish in part the contract it had with the Rommell Company, at its own expense.

After a careful study and consideration of the. record and the able and exhaustive briefs submitted alike by opposing counsel herein, we are inclined to concur in the conclusion announced by the trial court.

By the provisions of the contract entered into on October 28, 1932, the appellant expressly thereby agreed and undertook to furnish “all labor and material necessary to complete, and to perform in a good workmanlike manner all millwork delivered to the building according to plans and specifications and addenda pertaining to the erection of Junior and Senior High School, Second and Lee, for Board of Education,” and further “to promptly pay for all labor performed and all material used or furnished in completing said work and carrying out said contract.”

It will be noted that while the appellant does hereby undertake to furnish all labor and material necessary to complete and perform in a good workmanlike manner all millwork required, it is nowhere indicated by the terms of the contract that the appellant in so furnishing this labor and millwork was to be confined to its own one manufacturing plant as the one specific or exclusive means or agency through which it was to render performance, or that the continued subsequent existence of its own one millwork factory was, when contracting, contemplated by the parties as the single or necessary specific agency through which this mill-work could alone be satisfactorily furnished. The evidence clearly shows that, while under the contract specifications for this work some of it was to be specially made in accordance therewith, nevertheless this specified millwork not only could be made in and was obtainable from the one factory of appellant but was also obtainable from other local millwork industries in Louisville, to one of which (the Anderson Manufacturing Company) the appellant, when its mill was destroyed by fire, had turned and arranged to have its contract properly and acceptably performed by it for the Rommell Company. It is apparent that had appellant’s contract, as construed by it, been in its character one strictly for a personal service, calling for the manufacture and delivery of this millwork exclusively by its own milling plant and as the special handiwork of its own employees, it could not, upon the event of its *375

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
78 S.W.2d 52, 257 Ky. 371, 1934 Ky. LEXIS 563, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kentucky-lumber-millwork-co-v-george-h-rommel-co-kyctapphigh-1934.