Kennedy v. Silas Mason Co.

68 F. Supp. 576, 1946 U.S. Dist. LEXIS 1961
CourtDistrict Court, W.D. Louisiana
DecidedNovember 6, 1946
DocketNo. 1594
StatusPublished
Cited by4 cases

This text of 68 F. Supp. 576 (Kennedy v. Silas Mason Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kennedy v. Silas Mason Co., 68 F. Supp. 576, 1946 U.S. Dist. LEXIS 1961 (W.D. La. 1946).

Opinion

DAWKINS, District Judge.

Plaintiffs sued for overtime, penalties and attorneys’ fees, which they claim to be due under the Fair Labor Standards Act of June 25, 1938, C. 676, Sec. 16, 52 Stat. 1069, Title 29 U.S.C.A. § 216, alleging that they had been employed in interstate commerce and in the production of goods for commerce within the meaning of Section 3, Title 29 U.S.C.A. § 203, of said statute. The complaint admits that plaintiffs were paid all their wages at what appear to have been very liberal rates for straight time for the hours they worked.

Defendant has moved for summary judgment, for the rejection of the demands, contending that, under the undisputed facts and the law applicable thereto, plaintiffs were neither engaged in commerce nor the production of goods for commerce. In support of its motion, defendant offered the affidavit of its vice-president and general manager, one R. L. Telford, to which was attached the contract between it and the Government covering the operations involved. Telford’s affidavit is quoted as follows:

“That Silas Mason Company constructed and later operated the Louisiana Ordnance Plant under the terms of a contract with the United States of America, a copy of which is filed in the proceeding hereinafter mentioned.
“That construction of the Plant under the terms of the said contract began on or about the 7th day of July, 1941, and that operation of the Plant began on or about the 4th day of March, 1942.
“That deponent has been connected with the Silas Mason Company in an official capacity from a time long prior to the execution of the contract, above referred to, to the present time; that he was General Manager of the work performed by the Company under the said contract from the beginning of the construction to the 9th day of June, 1943; and was both General Manager as above stated, and Vice-President of the Silas Mason Company thereafter until a time subsequent to August 23, 1945, the date of the filing of Civil Action No. 1594 on the docket of the United States District Court for the Western District of Louisiana, Shreveport [578]*578Division, entitled ‘Harris Kennedy, et al., vs. Silas Mason Company.’
“That at all times involved in the complaint of complainants in the proceeding just above mentioned, the premises upon which the complainants were employed, the tools and equipment which they were using in their employment, and the property and products with which they dealt in such employment, were all the property of, and belonged to, the United States Government; that the component parts of the shells, grenades, mines, fuses, bombs, and other products with which all of the Complainants dealt were shipped to the Louisiana Ordnance Plant as property of the Government and the finished product, as property of the Government, was, by its direction, shipped out of the said premises for use by its Armed Forces in its War effort in the War with Germany, Japan, Italy, and other Nations; that at all times involved in the proceeding above mentioned, Silas Mason Company was operating the Louisiana Ordnance Plant, Shreveport, Louisiana, under the contract above mentioned, which is a cost-plus-a-fixed-fee contract with the United States Government, and under which contract the United States Government obligated itself to pay the Silas Mason Company a fixed fee for operating the said Plant, plus all expenses in connection with the operation thereof.
“That there were no rules, regulations, wage scales, or wage classifications promulgated for Silas Mason Company requiring that complainants in the above numbered proceeding be compensated for all hours in excess of 40 at time and one-half and at double time for all work performed on Sundays and Holidays; and there was no custom of Silas Mason Company involving' or requiring such compensation to complainants, or persons similarly situated.”

The contract is typical of many others that were entered into by the Government preceding and during World War II. The undisputed facts are that defendant, Silas Mason Co., Inc., hereafter called the contractor, agreed to build an ordnance plant near Minden, Louisiana, to train key personnel and to operate the plant in the manufacture of shells and munitions to be used in prosecuting the war. It was what is known as a “cost-plus-a-fixed-fee” arrangement, which meant that the Government was ultimately to reimburse the contractor for all sums spent under the contract. At all times, the title to all property, tools, materials and supplies placed or delivered upon the project was in the United States. However, the latter was not to be directly liable for any of the obligations of the contractor, although everything was to be under the control of the War Department, when necessary to exercise it. All the finished products were shipped out of the plant under the Government’s directions for the use of its armed-forces and those of its Allies. All employees save those of the War Department were hired and their compensation fixed by the contractor, subject to the veto of the army officer in charge.

The contract was divided into seven titles, and these in turn, into articles and subsections. Title I was headed “Design, Construction and Engineering”; Title II “Procurement of Production Equipment”; and Title III "Training of Key Personnel.” Each of these three titles had a subsection labeled “Eight Flour Law and Overtime Compensation” found in Article I-G of Title I, reading as follows:

“No laborer or mechanic doing any part of the work contemplated by this Title I, in the employ of the Contractor or any subcontractor contracting for any part of said work contemplated, shall be required or permitted to work more than eight hours in any one calendar day upon such work at the site thereof, except upon the condition that compensation is paid to such laborer or mechanic in accordance with the provisions of this Article. The wages of every laborer and mechanic employed by the Contractor or any subcontractor engaged in the performance of this Title I shall be computed on a basic rate of eight hours per day and work in excess of eight hours per day is permitted only upon the condition that every such laborer and mechanic shall be compensated for all hours worked in excess of eight hours per day at not less than one and one-half times the basic rate of pay. For each violation of the requirements of this Article a penal[579]*579ty of five dollars shall be imposed upon the Contractor for each laborer or mechanic for every calendar day in which such employee is required or permitted to labor more than eight hours upon said work without receiving compensation computed in accordance with this Article, and all penalties thus imposed shall be withheld for the use and benefit of the Government: Provided, That this stipulation shall be subject in all respects to the exceptions and provisions of U.S.C.A., title 40, Sections 321, 325, 324, and 326, relating to hours of labor, as in part modified by the provisions of Section 5(b) of Public Act No. 671, 76th ,Congress, approved June 28, 1940 [50 U.S. C.A.Appendix, § 1155(b) ], and Section 303 of Public Act No. 781, 76 Congress, approved September 9. 1940 [40 U.S.C.A. § 325a], relating to compensation for overtime.”

The last articles of Titles II and III (being II-D and III-D) declared that “the provisions of Article I-G (with respect to the eight hour law and overtime)' of Title I shall be applied to the work” under Titles II and III.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Cartridge Co. v. Powell
174 F.2d 718 (Eighth Circuit, 1949)
Brown v. Consolidated Vultee Aircraft Corp.
80 F. Supp. 257 (W.D. Kentucky, 1948)
Kennedy v. Silas Mason Co.
334 U.S. 249 (Supreme Court, 1948)
Barksdale v. Ford, Bacon & Davis, Inc.
70 F. Supp. 690 (E.D. Arkansas, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
68 F. Supp. 576, 1946 U.S. Dist. LEXIS 1961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kennedy-v-silas-mason-co-lawd-1946.