Kennedy Building Associates v. CBS Corp.

576 F.3d 872, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20186, 2009 U.S. App. LEXIS 18554, 2009 WL 2497695
CourtCourt of Appeals for the Eighth Circuit
DecidedAugust 18, 2009
Docket07-3622
StatusPublished
Cited by4 cases

This text of 576 F.3d 872 (Kennedy Building Associates v. CBS Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kennedy Building Associates v. CBS Corp., 576 F.3d 872, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20186, 2009 U.S. App. LEXIS 18554, 2009 WL 2497695 (8th Cir. 2009).

Opinion

JOHN R. GIBSON, Circuit Judge.

In Kennedy Building Associates v. CBS Corporation (Kennedy II), 476 F.3d 530 (8th Cir.2007), we remanded in part for *874 modification of the district court’s injunction, asking the district court to determine which requirements of the Minnesota Decision Document were necessary to accomplish the goals of the Minnesota Environmental Rights Act (MERA). Minn.Stat. § 116B.01 et seq. The district court’s modified injunction states that CBS has “substantially complied” with the Minnesota Decision Document and imposes no additional requirements. Kennedy appeals. Kennedy also argues that the district court’s order denying its requests to increase the amount of the performance bond posted by CBS and for post-judgment response costs was in error. We affirm in part and vacate and remand in part.

I.

In our previous decisions, Kennedy Building Associates v. Viacom, Inc. (Kennedy I), 375 F.3d 731 (8th Cir.2004) and Kennedy II, 476 F.3d 530 (8th Cir.2007), we have detailéd the history of the Kennedy Building site. The property was previously owned by Westinghouse, which operated an electrical transformer repair facility there. These operations led to significant contamination of the building, surrounding soil, and groundwater with polychlorinated byphenyls (PCBs) and chlorobenzenes, which are hazardous substances. Westinghouse was “virtually certain” that there was PCB contamination on the property. Despite this knowledge, Westinghouse sold the site to Hillcrest Development Company in 1980 without disclosing the probable contamination. In 1982, Gerald Trooien, a partner in Kennedy Building Associates, bought the property and transferred it to Kennedy.

In 1997, Kennedy discovered the contamination. Kennedy reported the contamination to the Minnesota Pollution Control Agency (the Agency) and began further investigations and clean-up of the site. Kennedy then brought suit against CBS, the successor in interest to Westinghouse. 1 The district court found CBS liable under the federal Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) and the Minnesota Environmental Response and Liability Act (MERLA). The court awarded Kennedy $106,393.23 in statutory response costs and issued a declaratory judgment of liability for future response costs, which CBS did not appeal. 2 See Kennedy I, 375 F.3d at 735. The court also issued an injunction under MERA, requiring CBS to clean up the contamination at the site. CBS appealed the injunction, and we reversed and remanded “for more precise definition of the specific acts required of [CBS]” and to limit its scope to only that relief authorized by MERA. 3 Id. at 748.

Before the Kennedy I proceedings, CBS entered into a consent order with the Agency that would lead to the development and implementation of a Response Action Plan (Plan) to clean up pollution at the Kennedy Building site. On remand from Kennedy I, the district court held the *875 case in abeyance for the development of the Plan. Kennedy participated in the comment process. Relevant to this appeal, Kennedy commented that absent the removal of all contaminated soils from the site, “the asphalt cap will have to be maintained indefinitely to prevent water infiltration.” Kennedy specifically objected to the inclusion of permeable, unpaved islands in the parking lot plans submitted by CBS. The Agency considered this comment and responded that any concern regarding residual contamination would be addressed by monitoring. Further, it explained that “replacement of the asphalt surface is not an integral part of the remedial action; it is solely for the purpose of Site restoration.” At the end of the administrative process, the requirements of the Plan were laid out in the Minnesota Decision Document (Decision Document) issued by the Agency. The Plan required CBS to perform site preparation and asphalt removal; soil excavation and confirmation sampling; off-site disposal, backfilling of excavated areas, site restoration, and resurfacing of excavated areas; and long term monitoring. The Decision Document also noted that CBS is obligated to perform future additional remedial action upon redevelopment or exposure of “remotely accessible” soils.

On February 8, 2006, the district court issued an order modifying the injunction to 1) incorporate the Plan requirements from the Decision Document, 2) order CBS to provide the court with the results of periodic testing, and 3) order further remedial action contingent on tests showing the spread of contamination or redevelopment that would expose unremediated soils. The court also required CBS to post a bond to cover costs of future relief, which was later set at $1,311,000. CBS appealed, arguing that the injunction was not sufficiently specific, that the evidence showed there was no need for injunctive relief under MERA, and that the district court did not have the power to require CBS to post a bond. In Kennedy II, we affirmed as to the latter two arguments, but found the injunction to lack the required specificity and remanded with instructions that the district court “expressly list those actions required by the injunction.” 476 F.3d at 534, 536.

CBS implemented the Plan, beginning work in July 2006. The Plan required CBS to excavate all contaminated soil up to twelve feet below the surface and back-fill with clean fill. This excavation covered most of the lot and was particularly extensive on the east and north sides of the Building. In order to complete the required excavation without risk of severe structural damage, CBS determined that it was necessary to install a system of three-foot-wide concrete buttresses on the east and north sides of the Building. Rather than removing the buttresses after excavation and backfill, CBS determined that it was preferable to leave them in place. They were covered with backfill and paved over when the parking lot was restored. Restoration of the site, including permanent paving of the parking lot, was completed in May 2007. Throughout the implementation of the Plan, KBA alleges that it incurred expenses due to testing soil, holding meetings, having building personnel provide access to various parts of the Kennedy Building, and obtaining advice regarding various issues.

The district court hearing regarding modification of the injunction on remand and Kennedy’s motion for additional relief was set for September 4, 2007. On August 30, 2007, the Agency issued a letter approving CBS’s Response Action Implementation Report with the addition of a “down-gradient monitoring well.” Kennedy contended that CBS’s remedial action did not comply with the requirements in *876 the Decision Document and asked the district court to impose additional requirements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
576 F.3d 872, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20186, 2009 U.S. App. LEXIS 18554, 2009 WL 2497695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kennedy-building-associates-v-cbs-corp-ca8-2009.