Kenite Corp. v. United States

157 Ct. Cl. 721, 1962 U.S. Ct. Cl. LEXIS 214, 1962 WL 9311
CourtUnited States Court of Claims
DecidedJune 6, 1962
DocketNo. 298-58
StatusPublished

This text of 157 Ct. Cl. 721 (Kenite Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kenite Corp. v. United States, 157 Ct. Cl. 721, 1962 U.S. Ct. Cl. LEXIS 214, 1962 WL 9311 (cc 1962).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

Plaintiff Kenite Corporation was organized in 1948 to acquire a diatomite processing plant and diatomite deposits in Grant County, Washington.1 On August 24,1948, plaintiff purchased 520 acres in fee simple from Dia-cousti-lite Products Company, Incorporated. Through subsequent transactions, plaintiff, by the fall of 1957, owned approximately 735 acres in fee and leased an additional 320 acres— in toto an estimated 1,563,080 tons of diatomite reserves.

In this action plaintiff sues for just compensation for the taking of these diatomaceous earth deposits by the invasion of water from defendant’s Columbia Basin Project.

Finished diatomite products are used extensively in various commercial enterprises, viz., filter aids, fillers, absorbents, brighteners, carriers, and insulating products. Plaintiff processed crude diatomite obtained directly from its section 20 quarry2 and from certain stockpiles during the period October 5, 1948, to December 1952, without experiencing any difficulties in its plant operations attributable to excessive moisture in the crude. However, production difficulties began in early 1953.

It is not economically feasible to process crude diatomite with a moisture content of 50 percent or more. The record in this case, as indicated by extensive findings of fact by the commissioner and which we adopt, clearly shows that the moisture content of plaintiff’s deposits did not exceed 25 percent prior to the construction and operation of the Columbia Basin Project. It further shows that such moisture thereafter increased until, by the fall of 1957, the deposits averaged over 50 percent in moisture content.

The Columbia Basin Project was constructed to provide for storage and delivery of water for land reclamation, electric energy and flood control. A major facility is the Grand Coulee Equalizing Reservoir, a body of water 70 [724]*724feet deep, 27 miles long, and from 1 to 5 miles wide, which extends in a southerly direction, commencing 2 or 3 miles from the site of Grand Coulee Dam. The Reservoir was filled with water by August 1951, and its surface elevation has varied from 1,550 to 1,570 feet m.s.l. since that time.

Plaintiff’s lands are located on Babcock Ridge at surface elevations of about 1,350 feet m.s.l. The distances from the south dam of the Equalizing Reservoir to plaintiff’s deposits vary from 44 to 52 airline miles in a southwesterly direction.

It is contended by plaintiff that leakage of water from the Equalizing Reservoir into deep aquifers (zones of permeable basalt) raised the piezometric water surface in the area of plaintiff’s lands to the extent that the diatomaceous earth deposits were saturated by capillary action.3 Defendant keeps records of the quantity of water pumped into and released from the Equalizing Reservoir. Records of both input and output are accurate within 2 or 3 percent. Any difference between water pumped in and that released from the Reservoir is attributed to either .evaporation or deep percolation. The latter falls within the 2 or 3 percent margin of error. Thus, water loss from deep percolation could possibly amount to as much as 6 percent of the water passing through the Equalizing Reservoir.

The commissioner has found as not supported by the evidence two arguments of defendant in explanation of the increased moisture: one, that the high moisture content had always existed in plaintiff’s deposits due to entrapment of water therein by the last lava flow after exposure to ancient lakes; second, that the increase was caused by natural precipitation into plaintiff’s open-pit operations. We accept these findings.

As we stated in Pashley v. United States, 140 Ct. Cl. 535, 538 (1957), defendant’s liability in this type case “depends not on its want of care, but on the fact of taking as the natural consequence of [its] * * * acts.” Considering the record as a whole, it is reasonable to conclude that the nat[725]*725ural consequence of defendant’s activities in connection with the Columbia Basin Project resulted in a raising of the piezometric surface of water located beneath plaintiff’s diatomite deposits to such an extent that the moisture content of the crude was so increased as to make it uneconomical to process the crude into finished products.4

It is difficult to accurately measure the damages which have been caused to plaintiff’s land. But, from the testimony as a whole, we have arrived at $30,000 as the amount which will compensate plaintiff for the decrease in the fair market value of its land — both that held in fee and by lease.5

Plaintiff is entitled to recover the decrease in the fair market value of its holdings in the amount of $30,000, and judgment will be entered to that effect with interest thereon computed at 4 percent per annum as a part of just compensation from December 1, 1957, until date of payment.

It is so ordered.

Davis, Judge; Durpee, Judge; and Laramore, Judge, concur.

Whitaker, Judge,

delivered the following opinion:

I am not persuaded that the piezometric pressure from the Equalizing Beservoir caused the wetting of plaintiff’s diato-maceous deposits. Before filling the reservoir, defendant had drilled a number of wells between the reservoir and plaintiff’s deposits. These wells extended through 7 or 8 horizons or strata of lava; that is to say, 7 or 8 different flows of lava. These wells were dug to a depth of some 500 feet or so. After the reservoir had been filled, the water rose decreasingly less the farther the well was from the reservoir, and in those farthest removed, three or four miles away, it did not rise substantially. Plaintiff’s deposits were 40 to 50 [726]*726miles away, on an air line. We know, therefore, that any aquifer that may have existed in these 7 or 8 horizons did not carry the water up to plaintiff’s deposits.

However, plaintiff’s witness, who was a lecturer in Engineering Geology at Harvard University, surmised that there were aquifers in lower levels of the lava flows, which might have been filled with water, and that the pressure from the reservoir might have caused this water to rise through supposed faults or fissures in the lava underneath plaintiff’s deposits until it came in contact with them. If it did, it would have been forced up through these fissures 400 or 500 feet. She admits that her theory is only speculation. She says it might have been the cause of the wetting of the deposits.

But the burden is on plaintiff to prove that the defendant did wet it. . Aside from the speculation of this geologist, we have only the fact that the deposit was not wet before the reservoir was filled with water, and it was wet thereafter. But it is significant that there is no recofid of the water having been forced up so high at any other place in the 40 or 50 miles between the reservoir and the deposits. At no place did the water rise more than 47 feet, as set out in the trial commissioner’s finding 104, and at most places it rose less than 10 feet.

I do not think this is sufficient proof to show that defendant was responsible for the wetting, although, I must confess, I can think of no other explanation therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pashley v. United States
156 F. Supp. 737 (Court of Claims, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
157 Ct. Cl. 721, 1962 U.S. Ct. Cl. LEXIS 214, 1962 WL 9311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kenite-corp-v-united-states-cc-1962.