Kendallville Lumber Co. v. Adams

176 N.E. 555, 93 Ind. App. 141, 1931 Ind. App. LEXIS 106
CourtIndiana Court of Appeals
DecidedJune 4, 1931
DocketNo. 14,095.
StatusPublished
Cited by7 cases

This text of 176 N.E. 555 (Kendallville Lumber Co. v. Adams) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kendallville Lumber Co. v. Adams, 176 N.E. 555, 93 Ind. App. 141, 1931 Ind. App. LEXIS 106 (Ind. Ct. App. 1931).

Opinion

Curtis, J.

r-On June 12, 1926, Homer B. Adams and his wife, Margaret M. Adams (appellees herein), entered into a written contract with appellee Flesher, by which the latter agreed to construct a house, garage and driveway according to certain plans and specifications on certain described real estate owned by Adams and wife.

The evidence shows that the Kendallville Lumber Company (appellant herein) furnished to Flesher (hereinafter referred to as “the contractor”) building material and lumber for the construction of a house, garage and driveway, which was to be constructed for the Adamses, such materials being furnished from June 17, 1926, to November 1, 1926, and was of the reason *143 able value of $2,632.66; that on November 1, 1926, the contractor ceased and abandoned work on the buildings in question and before such buildings were completed; that Homer B. Adams, one of the owners, completed the construction of the house, garage and driveway; that appellant furnished materials from November 3 to December 10, 1926, for the completion of the work in the amount of $181.30. The Kendallville Lumber Company, on January 10, 1927, filed its notice of intention to hold a mechanic’s lien for the amount of $2,832.16, which amount included the $2,632.66 for materials furnished the contractor between June 17, 1926, and November 1, 1926, and the $181.30 for materials furnished Adams for the completion of the buildings.

This action was based upon appellant’s complaint in one paragraph to foreclose the mechanic’s lien above mentioned. Appellees Adams and Adams filed answer in three paragraphs, the first in general denial, the second of payment, and the third averred, in substance.: That the materials purchased from appellant by the contractor and used in the improvements under consideration were sold to such contractor and charged to- him upon appellant’s books; that, on or about November !, 1926, and at a time when the dwelling house was finished or nearly so, but before the garage had been completed, the contractor became insolvent and abandoned the construction of the house, garage and improvements mentioned in the complaint and thereafter neither did any work on the same nor furnished any materials therefor; that the contractor notified appellee Homer B. Adams of his ' (the contractor’s) abandonment of the contract and that Adams, more than 60 days prior to January 10, 1927, notified appellant of the contractor’s abandonment of the contract and, at the same time, notified appellant not to sell to such contractor any further materials to be used in the construction of the *144 house, garage and improvements in question, but to charge any further materials that might be ordered for the completion' of such work to appellee Homer B. Adams and that he (Adams) would pay for the same, all of which was agreed to by appellant; that, after such agreement between Adams and appellant, no further materials were furnished the contractor for the buildings in question; that, after such agreement, all materials furnished by appellant to be used in said buildings were charged to Adams and that none of the materials sold and furnished to the contractor by appellant for use in the construction of the house, garage and improvements described in the complaint were sold or furnished within 60 days immediately preceding January 10. ‘To this answer, appellant filed reply in two paragraphs, the first a general denial, and the second stating that appellant would have filed its notice of intention to hold a mechanic’s lien on or before December 20, 1926, on the real estate in question, had it not been for appellee Adams admitting to appellant’s attorneys his liability of the entire amount and representing to them that he would pay the same as soon as he made a settlement with Flesher.

Trial was had by the court upon the issues thus formed. The court found that there was due appellant from Adams and Adams the sum of $181.30, and that there was due appellant from Flesher the sum of $2,-632.66. The court rendered judgment against Adams and Adams for $181.30, plus interest and attornéy’s fees, and declared the same to be a lien upon the premises described in the complaint and ordered the lien foreclosed. The court further rendered personal judgment against the contractor for $2,632.66, with interest,'but refused to declare this last-named amount to be a lien on the real estate. From this judgment, appellant appealed and assigned as error the court’s overruling of *145 its motion for a new trial, under which it claims that the decision is contrary to law; that it is not supported by sufficient evidence; and that the amount of recovery is erroneous, being too small.

The two questions presented by the appeal in this case are: (1) Is there evidence sufficient to support a finding that the materials were furnished under two separate and independent contracts, one for the larger amount with Guy C. Flesher, the contractor, and one for the smaller amount with Homer B. Adams, the owner, and one of the appellees herein; and (2) if there were two separate contracts, can the latter be tacked to the former to make the lien filed January 10, 1927, sufficient to cover the earlier claim?

Appellant contends that, since the lien was for materials furnished by appellant for “the same identical job and for the same identical improvements located on one lienable unit of land,” the time for filing the statutory notice of intention to hold a lien dates “not from the time the last item was furnished while the contractor was in charge, but from the time the last item was furnished after the owner requested the materialman to furnish the material necessary to complete the job.” There might be merit in this contention had there been but one contract involved in the transactions. But the court, to arrive at its judgment, must necessarily have found that there were two contracts involved, one between the contractor and appellant and the other between the appellant and the appellee Adams. Whether all the items of charges for materials were furnished under a single contract or whether they were furnished under two separate and independent contracts is a question of fact for the court-in a case tried without a jury. Nye & Schneider Co. v. Fred Berger (1897), 52 Nebr. 758, 73 N. W. 274. If *146 there is evidence to support the decision of the court on this point, its finding in relation thereto will not be disturbed.

Appellee Adams testified, in part, as follows: That he went to the office of the Kendallville Lumber Company on November 3 or-5 and talked to Sabrosky, manager of appellant company, and “I told him Flesher was going on the road for Whiteford Brothers. He was not going to finish my house and garage and walks and that I would have to finish them myself. I told him further that he should send anything that I ordered or the men ordered to complete the house and I would give him a check for the full payment. Sabrosky said he would.” He further testified that he told Sabrosky: ■ “I will have to finish Flesh-er’s contract on my house and garage and from now on charge everything that is ordered to me, or the men that work on the house, charge everything to me. When it is completed, I will give you a check for it. . . . Sabrosky said all right.” Guy -C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Potter v. Cline
316 N.E.2d 422 (Indiana Court of Appeals, 1974)
Saint Joseph's College v. Morrison, Inc.
302 N.E.2d 865 (Indiana Court of Appeals, 1973)
Miller Monuments, Inc. v. Asbestos Insulating & Roofing Co.
185 N.E.2d 533 (Indiana Court of Appeals, 1962)
Anderson v. Taylor
347 P.2d 536 (Washington Supreme Court, 1959)
Warner Co. v. Leedom Construction Co.
93 A.2d 316 (Superior Court of Delaware, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
176 N.E. 555, 93 Ind. App. 141, 1931 Ind. App. LEXIS 106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kendallville-lumber-co-v-adams-indctapp-1931.