Kendall v. Fader

65 N.E. 318, 199 Ill. 294
CourtIllinois Supreme Court
DecidedOctober 25, 1902
StatusPublished
Cited by12 cases

This text of 65 N.E. 318 (Kendall v. Fader) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kendall v. Fader, 65 N.E. 318, 199 Ill. 294 (Ill. 1902).

Opinion

Mr. Chief Justice Magruder

delivered the opinion of the court:

The decree of the circuit court held that Fader, appellee, claiming a mechanic’s lien upon the premises in question, was entitled to a first lien thereon for $1080.20, together with interest and attorney’s fees; and that appellants, as trustees under the will of John L. Rogers,, deceased, were entitled to a second lien by virtue of the trust deed, executed to William Loeb, as trustee, to secure a note for $4000.00, owned by them. The present appeal is prosecuted by the appellants, as owners of the encumbrance, decreed to be subject to the appellee’s mechanic’s lien, and the controversy is, therefore, between the mechanic’s lien creditor and such encumbrancers, and not between the mechanic’s lien creditor and Stewart, the owner of the property. Appellants claim, that the decree of the circuit court was erroneous in holding that appellee was entitled to a lien prior to the lien of their trust deed. The decree is alleged by appellants to be erroneous upon two grounds.

First—It is contended by appellants that the statement of claim, filed with the clerk of the circuit court by appellee for a mechanic’s lien, is indefinite and insufficient. The statement is thus charged to be defective, upon the alleged ground that it does not sufficiently give or state the time or times of furnishing the labor or material. The statement, so filed, discloses that the contract between appellee and Charles F. Stewart, the owner of the property, for the erection of the building upon the premises in question was in writing, and was dated the 25th day of October, 1894; that the original contract provided for the construction of a block of three stone-front residences on the east side of Vernon avenue, but was amended on February 18, 1895, by providing that only one of the three houses was to be erected thereunder, as the other two houses had been withdrawn by previous agreement.

Work upon the houses under the contract is shown by the proof to have been begun shortly after October 25, 1894. It follows that the Mechanic’s Lien law of 1895, which was passed on June 26,1895, and by its terms went into effect at once, has no application in the present case. The form of the statement here is controlled by the Mechanic’s Lien law of 1874, as amended on May 31,1887.

The law in force at the time a contract is executed enters into and forms a part of the contract. Inasmuch as the mechanic’s lien in this case arose out of a contract, entered into prior to the passage of the Mechanic’s Lien law of 1895, the latter law does not govern the present case. It has been so held by this court in a number of decisions. (Andrews & Johnson Co. v. Atwood, 167 Ill. 249; Culver v. Atwood, 170 id. 432; Weber v. Bushnell, 171 id. 587; Stone v. Tyler, 173 id. 147; Young v. Jones, 180 id. 216; Mantonya v. Reilly, 184 id. 183). In Culver v. Atwood, supra, it was held that the Mechanic’s Lien act of 1895 gives new remedies to parties, furnishing labor or material to subcontractors, and imposes new duties upon owners, 'and cannot be allowed to control contracts, entered into before its passage, without making it obnoxious to the constitutional provision concerning laws impairing the obligation of contracts.

It being determined, then, that the law of 1887 governs the construction of the present contract and the statement of claim filed thereunder, it is necessary to refer to the law of 1887, in order to ascertain -what its requirements are. Section 4 of the act of 1887 in regard to mechanics’ liens provides that “every creditor or contractor, who wishes to avail himself of the provisions of this act, shall file with the clerk of the circuit court of the county, in which the building, erection, or other improvement to be charged with the lien is situated, a just and true statement or account or demand due him, after allowing all credits, setting forth the times when such material was furnished or labor performed, and containing a correct description of the property to be charged with the lien, and verified by an affidavit.” (Sess. Laws of 1887, p. 219). It thus appears that, by said section 4, the statement of the claim filed with the clerk must set forth “the times when such material was furnished or labor performed.” The contention is that the statement, so filed by appellee, did not set forth the times when the material was furnished or labor performed, as required by section 4. When we turn to the statement in question, it is found to set forth that, by the terms of the original contract dated October 25, 1894, appellee was to build for Stewart a block of three stoUe-front residences and provide all labor, material, etc., for the same, and that work was to be commenced on or before April 30, 1895; that, on or about February 18,1895, the parties amended the agreement of October 25, 1894, by providing that only one house (the middle house) was to be erected under the contract, and that “immediately upon the execution of the said contract this claimant proceeded to erect the said building according to the terms thereof, and completed the said building on or about the 20th day of November, 1895.” This statement was sufficient, as the labor was done and the materials were furnished under an entire contract. In Springer v. Kroeschell, 161 Ill. 358, we said (p. 365): “Where the work was done or the materials furnished under an entire contract, the different times when the work was performed, or the materials furnished, need not be stated. (Phillips on Mechanics’ Liens, sec. 359). Certainty to a common intent is all that is required in stating a mechanic’s claim, and where the law requires the time when the work was to be done to be set forth, a claim which states, that the work was done between April 16,1841, and August 29,1841, is sufficient.—Id. sec. 360.” (See also Hayes v. Hammond, 162 Ill. 133). It sufficiently appears from the statement, that the work was commenced upon the execution of the contract, and that the building was completed on the 20th day of November, 1895.

Second—It is furthermore contended by the appellants that some of the sub-contractors, furnishing labor and material for the building under appellee as contractor, took notes secured by a deed of trust upon the property in question; that the taking of these notes, alleged to have been secured by such trust deed, operated as a waiver or discharge of the liens held by such sub-contractors, and that appellee’s statement of claim, as filed with the circuit court, was for a single lump sum, to-wit, $1188.42, and that such lump sum included the amounts, for which such notes were taken by the sub-contractors. It is, therefore, argued that, inasmuch as the lump sum, named in the statement, included sums for which appellee or the sub-contractors had no liens, and which were so included as to be indistinguishable and inseparable, thereby misleading encumbrancers and others dealing with the land, the statement was insufficient and invalid.

The proof shows that quite a number of the sub-contractors accepted notes for portions of the amounts due them from Charles F. Stewart, the owner of the property. It is true that a mechanic’s lien is waived or discharged where the owner thereof takes security, either on property, or that of individuals not parties to the transaction. (Brady v. Anderson, 24 Ill. 111; Kinzey v. Thomas, 28 id. 502; Gardner v. Hall, 29 id. 277; Kankakee Coal Co.v. Crane Bros. Manf. Co. 138 id. 207; Croskey v. Corey, 48 id. 442; Clark v. Moore, 64 id. 273; Lyon & Sons Lumber Co. v. Equitable Loan and Investment Co. 174 id. 31).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glencoe State Bank v. Cole
265 Ill. App. 158 (Appellate Court of Illinois, 1932)
Francesconi v. Independent School District
214 N.W. 882 (Supreme Court of Iowa, 1927)
Manchester v. Popkin
130 N.E. 62 (Massachusetts Supreme Judicial Court, 1921)
Bailey Ornamental Iron Co. v. Goldschmidt
166 P.2d 363 (California Court of Appeal, 1917)
Oceanic Gold Mining Co. v. Steinfeld
147 P. 717 (Arizona Supreme Court, 1915)
Anderson v. Baker
175 Ill. App. 254 (Appellate Court of Illinois, 1912)
Schmidt v. Anderson
97 N.E. 291 (Illinois Supreme Court, 1911)
Natural Carbon Paint Co. v. Fred Bredel Co.
193 F. 897 (Seventh Circuit, 1911)
Treloar v. Hamilton
80 N.E. 75 (Illinois Supreme Court, 1906)
Shields v. Sorg
129 Ill. App. 266 (Appellate Court of Illinois, 1906)
Concord Apartment House Co. v. O'Brien
128 Ill. App. 437 (Appellate Court of Illinois, 1906)
McNicholas v. Tinsler
127 Ill. App. 381 (Appellate Court of Illinois, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.E. 318, 199 Ill. 294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kendall-v-fader-ill-1902.