Ken Leahy Construction, Inc. v. Cascade General, Inc.

994 P.2d 112, 329 Or. 566, 1999 Ore. LEXIS 1032
CourtOregon Supreme Court
DecidedDecember 30, 1999
DocketCC 9307-04717; CA A85442; SC S44812
StatusPublished
Cited by31 cases

This text of 994 P.2d 112 (Ken Leahy Construction, Inc. v. Cascade General, Inc.) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ken Leahy Construction, Inc. v. Cascade General, Inc., 994 P.2d 112, 329 Or. 566, 1999 Ore. LEXIS 1032 (Or. 1999).

Opinion

*568 RIGGS, J.

This is an appeal from a declaratory judgment that held that defendant Cascade General, Inc., is the owner of certain dry docks located on the property of plaintiff Ken Leahy Construction, Inc., and that required defendant to take possession of the dry docks. The Court of Appeals reversed that judgment. Ken Leahy Construction, Inc. v. Cascade General, Inc., 149 Or App 480, 944 P2d 951 (1997). For the reasons that follow, we reverse the decision of the Court of Appeals and affirm the judgment of the trial court.

We take the following facts from the Court of Appeals’ opinion and also from the record:

“Plaintiff is a construction and development company owned by Ken Leahy and his wife. Defendant is a ship-repair company based in Portland. Ken Leahy and two partners own a tract of land adjacent to the Columbia River known as the Bradwood property. The Bradwood property consists of 270 acres of forest land and 32 acres of marine industrial land.
“In the summer of 1990, plaintiff and defendant began discussions about developing the Bradwood property as a ship-repair facility. As the discussions progressed, plaintiff contends that the parties reached an agreement under which plaintiff would develop and construct the facility for defendant at cost plus 10 percent. Plaintiff further claims that, during those discussions, defendant asked [plaintiffl to obtain a set of dry docks for the facility that were then being decommissioned by the Port of Portland.”

Id. at 482.

There is evidence that plaintiff agreed to bid on the diy docks because defendant, as a tenant of the Port of Portland (Port), did not want the Port to know of defendant’s interest in the purchase of the dry docks. Plaintiff contends that the parties agreed not to put their development agreement in writing to protect defendant’s relationship with the Port. For its part, defendant claims that any discussion about the Bradwood project only was preliminary and that plaintiff purchased the dry docks on its own accord. In any case, on October 19, 1990, plaintiff submitted a bid to the Port to *569 remove the docks from the Port’s property. The Port accepted that bid and paid plaintiff $190,000. Plaintiff moved the diy docks to the Bradwood property.

After plaintiff moved the dry docks, the parties continued their discussions about the development project. Plaintiff retained several consultants and an engineer to develop specifications for the construction and development of the Bradwood site as a dry dock facility. Defendant began negotiating with a potential tenant for the site. Defendant also supplied plaintiff’s engineer with defendant’s specifications. The engineer’s plans, however, did not include plans or cost estimates for dry dock repair and restoration. Plaintiff explained that it never contemplated that it ultimately would be responsible for the dry docks themselves, because plaintiff understood that defendant was to have sole responsibility for them upon completion of the agreements between plaintiff and defendant.

As the discussions progressed, the parties reached sufficient agreement on the scope of the work and their respective responsibilities for the agreement to become an enforceable contract. As part of that contract, defendant agreed to purchase the dry docks from plaintiff for one dollar.

Ultimately, defendant’s negotiations to secure a tenant for the site failed. Defendant, because of its erroneous belief that it had not formed an enforceable agreement with plaintiff, felt free to walk away from the discussions without penalty, and it did so.

Plaintiff sued defendant for breach of contract, unjust enrichment, and fraud. Additionally, plaintiff sought declaratory and injunctive relief. At trial, the court granted defendant’s motion for a directed verdict against plaintiff’s unjust enrichment claim. Plaintiff introduced evidence supporting its other claims, including evidence that the dry docks had no value to plaintiff, because it could not run a dry dock facility without defendant’s participation. Plaintiff also introduced evidence that dismantling the dry docks and removing them from the Bradwood property would cost an estimated $548,000.

*570 The contract and fraud claims were submitted to a jury. The jury found that the parties had an enforceable oral contract and that defendant had breached that contract. The jury also found that the contract included, as one of its terms, a promise by defendant to buy the dry docks from plaintiff for one dollar. The jury found, however, that plaintiff had sustained no damage from defendant’s breach of the contract and that defendant had not committed fraud.

Following trial and the jury’s verdict on the contract and fraud claims, the trial court then decided plaintiff s claim for declaratory and injunctive relief. Plaintiff had based that claim on the alleged breach of contract and further allegations that the dry docks constituted a nuisance, a trespass, and were a continuing financial liability. The court issued a declaration in the form that plaintiff had requested:

“Pursuant to the Fourth Claim for Relief, the Court declares that title to the dry docks * * * is vested in defendant and that defendant shall accept responsibility for and take possession of the dry docks immediately upon entry of this Judgment.”

The trial court, however, did not make any findings of fact concerning its judgment.

Defendant appealed, assigning error to the trial court’s declaration, but not to the jury’s verdict on the breach-of-contract claim. The Court of Appeals first resolved a disputed fact by finding that the parties had an enforceable contract by which defendant was required to buy the docks for one dollar. The Court of Appeals’ majority reversed and remanded to the trial court, because there was “no evidence that defendant fulfilled its contractual obligation to buy [the dry docks for one dollar], which is a factual predicate to a declaration that it owns them.” 1 Ken Leahy, 149 Or App at 484. To the contraiy, the court continued, plaintiff had proved that defendant had not fulfilled its contractual duty to purchase the docks. Under those circumstances, the Court of *571 Appeals held, the trial court in effect had “granted specific performance of the contract through its declaration * * Id.

Granting specific performance was improper, the Court of Appeals reasoned, because plaintiff had not shown that it lacked an adequate remedy at law, which is a prerequisite to obtaining specific performance. The court noted that plaintiff would have been entitled to a declaration that defendant was obligated by contract to buy the dry docks and that plaintiff also could have obtained specific performance by proving the elements of that equitable remedy dining the trial or in a later proceeding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perma Treat, Inc. v. Toma Investments, LLC
344 Or. App. 725 (Court of Appeals of Oregon, 2025)
Kessler v. City of Portland
340 Or. App. 185 (Court of Appeals of Oregon, 2025)
Pringle Square, LLC v. Berrey Family, LLC
497 P.3d 1242 (Court of Appeals of Oregon, 2021)
Deschutes County v. Pink Pit, LLC
475 P.3d 910 (Court of Appeals of Oregon, 2020)
Bova v. City of Medford
350 P.3d 607 (Court of Appeals of Oregon, 2015)
Funke v. Aggregate Construction, Inc.
2015 ND 123 (North Dakota Supreme Court, 2015)
Nordbye v. BRCP/GM Ellington
349 P.3d 639 (Court of Appeals of Oregon, 2015)
Doyle v. City of Medford
Oregon Supreme Court, 2014
Morgan v. Sisters School District 6
301 P.3d 419 (Oregon Supreme Court, 2013)
C-LAZY-K RANCH, INC. v. Alexanderson
259 P.3d 53 (Court of Appeals of Oregon, 2011)
Spears v. Dizick
234 P.3d 1037 (Court of Appeals of Oregon, 2010)
Lisoski v. Broehl
230 P.3d 63 (Court of Appeals of Oregon, 2010)
Thunderbird Mobile Club, LLC v. City of Wilsonville
228 P.3d 650 (Court of Appeals of Oregon, 2010)
Macland v. Allen Family Trust
142 P.3d 87 (Court of Appeals of Oregon, 2006)
Osborne v. Nottley
136 P.3d 81 (Court of Appeals of Oregon, 2006)
Carey v. Lincoln Loan Co.
125 P.3d 814 (Court of Appeals of Oregon, 2005)
Frasier v. Nolan
98 P.3d 392 (Court of Appeals of Oregon, 2004)
Berenergy Corp. v. Zab, Inc.
94 P.3d 1228 (Colorado Court of Appeals, 2004)
American Trucking Associations, Inc. v. State
90 P.3d 15 (Court of Appeals of Oregon, 2004)
Swett v. Bradbury
67 P.3d 391 (Oregon Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
994 P.2d 112, 329 Or. 566, 1999 Ore. LEXIS 1032, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ken-leahy-construction-inc-v-cascade-general-inc-or-1999.