Ken Laster Company

CourtArmed Services Board of Contract Appeals
DecidedJuly 22, 2020
DocketASBCA No. 61292, 61828
StatusPublished

This text of Ken Laster Company (Ken Laster Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ken Laster Company, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) ASBCA Nos. 61292, 61828 Ken Laster Company ) ) Under Contract No. W9l2BV-09-D-1013 ) Task Order No. 0003 )

APPEARANCES FOR THE APPELLANT: Maria A. Luckert, Esq. Cody A. Reese, Esq. Barber & Bartz Tulsa, OK

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Jennifer A. Aranda, Esq. Engineer Trial Attorney U.S. Army Engineer District, Tulsa

OPINION BY ADMINISTRATIVE JUDGE SWEET

These appeals involve Contract No. W912BV-0-D-1013 (1013 Contract) Task Order No. 0003 between appellant Ken Laster Company (Laster) and the Army Corps of Engineers to repair service gates, liners, and discharge conduits at Pine Creek Lake, Oklahoma and Tenkillers Lake, Oklahoma. Laster completed the work late, and the government assessed liquidated damages. Laster appeals the contracting officer (CO) final decision (COFD) affirming the liquidated damages assessment. Pursuant to Board Rule 11, the parties waived a hearing, and instead submitted the appeal on the record before the Board.

In its Rule 11 brief, Laster argues that the liquidated damages assessment was erroneous because the delays underlying that liquidated damage assessment were excusable. 1 The government responds that there was no excusable delay. For the

1 Laster merely challenges the liquidated damages assessment. It does not seek any compensation for any delays (R4, tab 15 at 4216). Moreover, in its clarifying claim, Laster asserted that the government’s failure to provide stop logs, water releases, and over-inspection of welds and brass seals/bolts also delayed performance (id. at 4215). However, Laster did not raise those grounds in its Rule 11 brief (app. br. at 7). Therefore, we deem those grounds waived. Abbott Lab. v. Syntron Bioresearch, Inc., 334 F.3d 1343, 1355 (Fed. Cir. 2003). reasons discussed below, we find that there was no excusable delay. As a result, the government properly assessed liquidated damages, and we deny the appeals.

FINDINGS OF FACT

I. Background

1. On September 19, 2009, the government awarded the 1013 Contract to Timco Blasting and Coatings (Timco) (R4, tab 3B at 156). The parties subsequently modified the 1013 Contract to correct the awardee to Laster (R4, tab 3F at 241). The 1013 Contract was a multiple award task order contract for the preparation and painting of large industrial and hydraulic stationary and floating structures (R4, tab 3B at 155).

2. The 1013 Contract incorporated Federal Acquisition Regulation (FAR) Clause 52.211-12, Liquidated Damages—Construction (SEP 2000), which required Laster to pay liquidated damages if it failed to complete the work within the time specified in the 1013 Contract (R4, tab 3B at 172).

3. The government awarded Task Order No. 0003 under the 1013 Contract to Laster for repairs to the structures at Pine Creek Lake, Oklahoma and Tenkillers Lake, Oklahoma (R4, tab 3A at 1). According to Task Order No. 0003, work had to be completed 158 calendar days after Laster received the notice to proceed (id. at 33). Task Order No. 0003 also incorporated FAR 52.211-12, Liquidated Damages— Construction (SEP 2000), and authorized the government to assess $315 for each calendar day of delay (id.).

4. Laster received the notice to proceed on or about March 11, 2010, which means that the original required completion date was 158 days later on August 16, 2010 (R4, tab 10 at 3691).

5. The parties bilaterally extended the due date to May 22, 2011 (R4, tab 3I at 302).

6. Laster substantially completed work on March 5, 2012, 289 days later than May 22, 2011 (R4, tab 9 at 3690, tab 10 at 3691).

7. Therefore, unless Laster can show excusable delay, the Government is entitled to liquidated damages of 289 days multiplied by the $315 daily rate—or $91,035.

2 II. Facts Regarding Gate Painting

8. Task Order No. 0003 attached a statement of work (SOW). SOW 01 10 00a addressed the Pine Creek Lake structure, while SOW 01 10 00b addressed the Tenkillers Lake structure (R4, tab 3A at 54, 99).

9. SOW 01 10 00a permitted Laster to remove the Pine Creek Lake gates off-site for painting, stating in paragraph 1.2(e) that Laster had to provide a detailed work plan for “[r]aising each gate to the upper level, removing the gate from the gate tower, and transporting the gate to a paint shop for painting” (R4, tab 3A at 54). SOW 01 10 00b required Laster to paint the Tenkillers Lake gates on-site, stating in paragraph 1.3.2(b) that “[a]fter the government raises each gate to the appropriate level the contractor shall secure the gate for the rehabilitation process. This work shall include fall protection over the gate slot. Also the contractor shall cover the gate slot to prevent debris from falling into the conduit” (id. at 99).

10. On April 13, 2010, Laster submitted its Pine Creek Lake work plan (R4, tab 6B at 441). The plan indicated that Laster would remove the Pine Creek Lake gates by crane, and transport them to the Timco north yard for painting (id. at 442; see also id. at 448). The government did not object to Laster’s removal of the gates off-site for painting. On the contrary, it merely asked for information on the crane placement. (Id. at 444)

11. On April 16, 2010, Laster submitted its Tenkillers Lake work plan (R4, tab 6B at 453). The plan indicated that the government would hoist the gates, position them “horizontally onto a Flat bed truck, and move[] [the gates] off site to the subcontractor shop in Enid Oklahoma” for painting. Id. at 464; see also id. at 456). The government rejected Laster’s Tenkillers Lake work plan, in part because:

This plan states your intention to remove the gates from the tower and ship them to Enid, OK. There is no requirement for removal of the gates from the tower as it relates to cleaning and painting. Refer to spec section 01 27 00; Bid Item 9, “Clean and Paint”. Refer to Section 01 10 00b; page 2; para 1.3.2(g) “Clean, prepare for painting[]” Therefore, removal and shipping of the gates to Enid OK is not approved.

(R4, tab 6B at 452) 2

2 It is clear that the document at R4, tab 6B at 452 is rejecting Laster’s Tenkillers Lake work plan because it refers to (1) the “TK,” or Tenkillers, work plan, instead of the “PC,” or Pine Creek, work plan; (2) SOW 01 10 00b, which is the SOW 3 III. Facts Regarding Roller Chains Inspection

12. SOW 01 10 00b required Laster to heat treat the roller chains. After heat treatment, the roller chains had to be free of scale and cracks, “as determined by magnetic particle, florescent, or dye penetrant inspection tests.” (R4, tab 3A at 111) Laster had to submit “[c]ertified test reports” to the government for review and approval (id. at 109, 114).

13. On about March 10, 2011, Laster provided a report to the government indicating that Ramco Machine Shop (Ramco) conducted a magnetic particle test on the roller chains, and found the roller chains were free of scales and cracks (R4, tab 6B at 1796; app. supp. R4, tab 11 at 272). On March 21, 2011, the government rejected the test report (R4, tab 6B at 1796). The government was concerned that Ramco was an engine block repair machine shop for automobiles, and not an approved testing facility (R4, tab 13C at 4031). Laster resubmitted the same report on March 31, 2011, and the government again rejected it on April 25, 2011 (R4, tab 6B at 1807). On May 5, 2011, the administrative CO emailed Laster that the government would not accept the Ramco report because the contract required “testing by a certified tester in a certified lab” (app. supp. R4, tab 11 at 274).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Ken Laster Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ken-laster-company-asbca-2020.