Kelty v. Wiseman Construction Co.

349 N.E.2d 108, 38 Ill. App. 3d 808, 1976 Ill. App. LEXIS 2469
CourtAppellate Court of Illinois
DecidedJune 3, 1976
Docket75-215
StatusPublished
Cited by15 cases

This text of 349 N.E.2d 108 (Kelty v. Wiseman Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelty v. Wiseman Construction Co., 349 N.E.2d 108, 38 Ill. App. 3d 808, 1976 Ill. App. LEXIS 2469 (Ill. Ct. App. 1976).

Opinion

Mr. PRESIDING JUSTICE THOMAS J. MORAN

delivered the opinion of the court:

Plaintiff appeals from a denial of his motion for a new trial on the issue of damages only, following a jury award of *9200, which amount he claims to be palpably inadequate since it does not represent his out-of-pocket expenses.

Defendant counters that these damages are not palpably inadequate or, if they are, that they are the result of a jury compromise on the issue of liability and damages which renders improper the award of a new trial on the issue of damages only.

On January 2,1973, plaintiff, a carpenter, was building an external wall on the second floor deck of a townhouse being constructed by defendant, general contractor for the project of 188 townhouses in Wheaton. During the preceding holidays, ice had accumulated on the deck and on building materials at the site. Plaintiff and a co-worker attempted to scrape the ice away before commencing work that morning. Plaintiff then began constructing an exterior wall in a manner customarily used in the trade: the 2" side of a 2" x 4" (the “plate”) is temporarily nailed parallel to and 4" from the edge of a second floor deck; wooden studs are then laid at right angles on the floor and nails are driven through the plate into the studs. After this is accomplished the temporary nails holding the plate to the deck are removed and the structure is uprighted into place. As plaintiff was nailing 2" x 4" studs into the plate, his left foot (which was braced against the plate and the stud to prevent the latter from shifting) slipped from under him. The record does not indicate that plaintiff lost his footing as a result of any ice remaining on the deck. Plaintiff fell 10' to the frozen ground below, fracturing the weight-supporting talus bone of his ankle. No safety lines, railings, nets, or other devices were provided to prevent such a fall.

The ankle was set in a plaster cast and plaintiff was hospitalized for 10 days. After leaving the hospital and while using crutches, swelling arose in the fractured ankle, and, to keep the leg elevated, a wheel chair was prescribed for his use through the month of May. The cast was removed in March at which time it was noticed that his ankle looked deformed, that the range of flexion in the ankle was substantially impaired, and that the big toe would not bend. Plaintiff was instructed to gradually begin bearing weight on his leg. Between March and July he took whirlpool treatments and, working first with wheelchair and crutches, then crutches, and later (in June) with a cane alone, he once again became ambulatory.

On July 2, 1973, he returned to work for the first time. He asserts that, on his return, he found his ability to perform his chosen occupation as rough carpenter permanently impaired because he could no longer pivot, walk on uneven ground, or climb ladders or scaffolding due to the reduced range of motion in the ankle. The ankle swelled and ached after a day’s work. A year after the fall, an orthopedic surgeon (other than the one who had initially treated plaintiff) examined the ankle, found an impinging piece of bone, found evidence that the ankle bone was wearing away, and found that post-traumatic arthritis, usually a progressive condition, had developed at the fracture site. This surgeon suggested a brace to slow the ankle’s deterioration and to relieve pain, and also indicated that plaintiff will probably need a major operation — an ankle fusion — to reduce the pain. Such an operation permanently removes all flexion from the ankle. 1

At trial, the jury’s general verdict awarded plaintiff *9200 in damages. Plaintiff asserts that this award is palpably inadequate because it does not compensate him for his proven out-of-pocket expenses: *1356.58 paid medical expenses, plus *9516 lost wages from January 3 to July 2,1973, for a total of *10,872.58. This amount does not include future medical expenses to fuse the ankle, lost wages for the minimum of 3 to 4 months recuperative period which this procedure wiU demand, or for pain and suffering.

Defendant contends that the *9200 award was not palpably inadequate because it covers plaintiff’s out-of-pocket medical expenses and because the jury may weU have found plaintiff’s lost wages to be less than the *9516 claimed.

Defendant contends that the jury could have taken into consideration the seasonal nature of carpentry work and plaintiff s being subject to “off-time” due to lack of work after he returned from his injury. In a portion of a deposition used to impeach plaintiff’s trial testimony, plaintiff said he was laid off by McHugh Construction Company in February of 1974, and that one of the reasons given by the company was lack of work. Under these circumstances, it is argued, the jury could have concluded that the lost wages proved were less than those claimed. To so conclude, the jury would have had to place great weight on a fact of marginal relevance (that defendant was laid off a year after the injury— when his ability to perform his duties was impaired by the injury) and would have had to assume a fact not addressed by the parties (that job availability or scarcity in the construction industry during the year of layoff was comparable to the subject year). Contrary to defendant’s suggestion, we cannot presume that the jury made such a judgment.

Defendant argues that proof of lost wages consisted only of the fact that plaintiff was injured while employed at a wage of *9.15 per hour, and there was no proof that he would have worked, had he not been injured, at the same hourly rate or that he would have been continuously employed for the same number of hours per week during the 6 months from January to July of 1973. There is evidence in the record, however, that plaintiff had been employed as a carpenter for 6 years, had worked for the same employer for 15 months, and was working full time even in the midwinter month of January on a large project of 188 townhouses. After his injury, when he was able, he returned to work for the same employer. As these proofs were uncontradicted, and there was no evidence that plaintiff would have worked fewer horns, have been laid off, or have worked for lower wages during this period, we believe there was sufficient proof to establish the lost wages claimed.

In our case of First National Bank v. Szwankowski, 109 Ill. App. 2d 268, 275-76 (1969), we said:

“We are unable to imagine the misadventure the issue of damages suffered during the deliberations of the jury. It is apparent that the jury improperly assessed the amount of the damages for the verdict bears no reasonable relationship to the loss suffered by the plaintiff. The verdict does not even satisfy the uncontradicted elements of damages relating to medical expenses and lost wages.”

We held that damages awarded were palpably inadequate in that case, and we similarly hold here. See also Hamas v. Payne, 107 Ill. App. 2d 316 (1969).

Our finding that the damages were palpably inadequate does not, automatically, necessitate the award of a new trial as to damages only. Where it appears that a damage verdict is a result of compromise on the issue of liability, the case may not be retried on the issue of damages only, for to do so could impose an injustice upon the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McKenzie v. Romeiser
563 N.E.2d 837 (Appellate Court of Illinois, 1990)
Elliott v. Koch
558 N.E.2d 493 (Appellate Court of Illinois, 1990)
Blevins v. Inland Steel Co.
535 N.E.2d 972 (Appellate Court of Illinois, 1989)
McKanna v. Duo-Fast Corp.
515 N.E.2d 157 (Appellate Court of Illinois, 1987)
Greco v. Coleman
485 N.E.2d 1118 (Appellate Court of Illinois, 1985)
Hollis v. R. Latoria Construction, Inc.
461 N.E.2d 439 (Appellate Court of Illinois, 1983)
Morrison v. Migliore Contracting Corp.
442 N.E.2d 539 (Appellate Court of Illinois, 1982)
Long v. City of New Boston
420 N.E.2d 282 (Appellate Court of Illinois, 1981)
Atchley v. Berlen
408 N.E.2d 1177 (Appellate Court of Illinois, 1980)
Sommer v. City of Taylorville
375 N.E.2d 1031 (Appellate Court of Illinois, 1978)
Bledsoe v. Amiel
372 N.E.2d 1033 (Appellate Court of Illinois, 1978)
Stark v. D & F PAVING CO.
371 N.E.2d 315 (Appellate Court of Illinois, 1977)
Duncan v. Peoria Yellow Checker Cab Corp.
359 N.E.2d 1242 (Appellate Court of Illinois, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
349 N.E.2d 108, 38 Ill. App. 3d 808, 1976 Ill. App. LEXIS 2469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelty-v-wiseman-construction-co-illappct-1976.